Protection of the Site; Fencing. 5.7.1 After receiving the Lease Rights, to the Commercial Development Assets, the Developer shall ensure that the land remains free from all encroachments during the Lease Tenure. Further, the Developer shall ensure that for the duration commencing from the time when the Station Development Land and the Redevelopment Land is handed over to the Developer by Authority (and/ or its nominee) for the purpose of the Project, and ending at the date on which same are handed back by the Developer to Authority (and/ or its nominee), the Station Development Land and the Redevelopment Land remains free of all encroachments. 5.7.2 Within 15 (fifteen days) of receipt of right of access of the Project Land, the Developer shall secure the Project Land with environment friendly hoarding of height as per Applicable Law, not less than 1.8 meters of steel, on all sides (for outdoor areas), in each case with access controlled gate in the manner approved by the Nodal Officer. The steel hoarding should have a smooth painted surface with a pre-approved design bearing names and logo of the Project, relevant Railway, Authority, and the Developer. No construction debris, equipments, material should be kept outside the enclosed Project Land without specific permission of the Railway Administration. Provided that the hoarding in respect of indoor work areas shall be made from approved materials (as approved by the Nodal Officer), and be provided from floor to ceiling. 5.7.3 The Developer shall not commence any construction and development work upon the Project Land, except securing the Project through fencing/boundary wall until requisite approval from the Government Authorities, and approval of the relevant works programme from the PMC and approval of the Commercial Development Plan from the Nodal Officer. 5.7.4 Within 15 (fifteen days) of receipt of right of way to the Project Land (or any part thereof), the Developer shall secure the Project Land in accordance with the provision of Schedule 24 (Project Work, Safety and Access Requirements). 5.7.5 No activity related to construction shall block the adjacent roads in the circulating area at any time or hinder passenger or vehicle movement or cause congestion. 5.7.6 During the period of construction, the Developer shall not permit entry of any unauthorised person to the Project Land and further also maintain separate visitors log system(s) to record entry and exit of Persons in / from the Site and Redevelopment Land and to check unauthorized entry to the same. 5.7.7 The Developer shall appropriately cover walkways and passenger access areas so as to protect public/users/persons from debris / falling objects near and around the work site.
Appears in 13 contracts
Samples: Development Agreement, Development Agreement, Development Agreement
Protection of the Site; Fencing. 5.7.1 After receiving the Lease Rights, to the Commercial Development Assets, the Developer shall ensure that the land remains free from all encroachments during the Lease Tenure. Further, the Developer shall ensure that for the duration commencing from the time when the Station Development Land and the Redevelopment Land is handed over to the Developer by Authority (and/ or its nominee) for the purpose of the Project, and ending at the date on which same are handed back by the Developer to Authority (and/ or its nominee), the Station Development Land and the Redevelopment Land remains free of all encroachments.
5.7.2 Within 15 (fifteen days) of receipt of right of access of the Project Land, the Developer shall secure the Project Land with environment friendly hoarding of height as per Applicable Law, not less than 1.8 meters of metersof steel, on all sides (for outdoor areas), in each case with access controlled gate in the manner approved by the Nodal Officer. The steel hoarding should have a smooth painted surface with a pre-approved design bearing names and logo of the Project, relevant Railway, Authority, and the Developer. No construction debris, equipments, material should be kept outside the enclosed Project Land without specific permission of the Railway Administration. Provided that the hoarding in respect of indoor work areas shall be made from approved materials (as approved by the Nodal Officer), and be provided from floor to ceiling.
5.7.3 The Developer shall not commence any construction and development work upon the Project Land, except securing the Project through fencing/boundary wall until requisite approval from the Government Authorities, and approval of the relevant works programme from the PMC and approval of the Commercial Development Plan from the Nodal Officer.
5.7.4 Within 15 (fifteen days) of receipt of right of way to the Project Land (or any part thereof), the Developer shall secure the Project Land in accordance with the provision of Schedule 24 (Project Work, Safety and Access Requirements).
5.7.5 No activity related to construction shall block the adjacent roads in the circulating area at any time or hinder passenger or vehicle movement or cause congestion.
5.7.6 During the period of construction, the Developer shall not permit entry of any unauthorised person to the Project Land and further also maintain separate visitors log system(s) to record entry and exit of Persons in / from the Site and Redevelopment Land and to check unauthorized entry to the same.
5.7.7 The Developer shall appropriately cover walkways and passenger access areas so as to protect public/users/persons from debris / falling objects near and around the work site.
Appears in 2 contracts
Samples: Development Agreement, Development Agreement
Protection of the Site; Fencing. 5.7.1 After receiving the Lease Rights, to the Commercial Development Assets, the Developer shall ensure that the land remains free from all encroachments during the Lease TenureTerm. Further, the Developer shall ensure that for the duration commencing from the time when the Station Development Land and the Redevelopment Land is handed over to the Developer by Authority (and/ or its nominee) for the purpose of the Project, and ending at the date on which same are handed back by the Developer to Authority (and/ or its nominee), the Station Development Land and the Redevelopment Land remains free of all encroachments.
5.7.2 Within 15 (fifteen days) of receipt of right of access of the Project Land, the Developer shall secure the Project Land with environment friendly hoarding of height as per Applicable Law, not less than 1.8 meters of steel, on all sides (for outdoor areas), in each case with access controlled gate in the manner approved by the Nodal Officer. The steel hoarding should have a smooth painted surface with a pre-approved design bearing names and logo of the Project, relevant Railway, Authority, and the Developer. No construction debris, equipments, material should be kept outside the enclosed Project Land without specific permission of the Railway Administration. Provided that the hoarding in respect of indoor work areas shall be made from approved materials (as approved by the Nodal Officer), and be provided from floor to ceiling.
5.7.3 The Developer shall not commence any construction and development work upon the Project Land, except securing the Project through fencing/boundary wall until requisite approval from the Government Authorities, and approval of the relevant works programme from the PMC and approval of the Commercial Development Plan from the Nodal Officer.
5.7.4 Within 15 (fifteen days) of receipt of right of way to the Project Land (or any part thereof), the Developer shall secure the Project Land in accordance with the provision of Schedule 24 (Project Work, Safety and Access Requirements).
5.7.5 No activity related to construction shall block the adjacent roads in the circulating area at any time or hinder passenger or vehicle movement or cause congestion.
5.7.6 During the period of construction, the Developer shall not permit entry of any unauthorised person to the Project Land and further also maintain separate visitors log system(s) to record entry and exit of Persons in / from the Site and Redevelopment Land and to check unauthorized entry to the same.
5.7.7 The Developer shall appropriately cover walkways and passenger access areas so as to protect public/users/persons from debris / falling objects near and around the work site.
Appears in 1 contract
Samples: Development Agreement