Quality Plans and Systems. (a) Project Co shall cause all of the Works to be the subject of quality management systems, which shall include a Design Quality Plan and a Construction Quality Plan (collectively, the “Quality Plans”), which may be incorporated into one document. (b) All Quality Plans shall be consistent with the requirements of the Output Specifications, the Phase Commissioning Program and the Final Commissioning Program. (c) The Design Quality Plan is attached as part of Schedule 11 – Design Quality Plan and Construction Quality Plan. (d) The Construction Quality Plan shall, at a minimum, comply with the requirements of the outline of the Construction Quality Plan attached as part of Schedule 11 – Design Quality Plan and Construction Quality Plan. Project Co shall submit its proposed Construction Quality Plan to Contracting Authority within 60 days following Financial Close. (e) All Quality Plans shall be subject to review by Contracting Authority pursuant to Schedule 10 – Review Procedure, and Project Co shall not be entitled to implement or cause the implementation of any Quality Plan unless and until Project Co is entitled to proceed with such implementation pursuant to Schedule 10 – Review Procedure. (f) Project Co shall implement the Quality Plans, shall perform and cause to be performed the Works in compliance with the Quality Plans, including by causing the Construction Contractor to implement the Design Quality Plan and the Construction Quality Plan. (g) Where any aspect of the Works is performed by more than one Project Co Party, then this Article 15, in so far as relevant or appropriate to the activities to be performed by such Project Co Party, shall apply in respect of each of them and references in this Article 15 to such Project Co Party, including the Construction Contractor, shall be construed accordingly.
Appears in 2 contracts
Samples: Project Agreement, Project Agreement
Quality Plans and Systems. (a) Project Co shall cause all of the Works to be the subject of quality management systems, which shall include a Design Quality Plan and a Construction Quality Plan (collectively, the “Quality Plans”), which may be incorporated into one document.
(b) All Quality Plans shall be consistent with the requirements of the Output Specifications, each Phase Commissioning Program, the Phase Tower Interim Completion Commissioning Program and the Final Commissioning Program.
(c) The Design Quality Plan is attached as part of Schedule 11 – Design Quality Plan and Construction Quality Plan.
(d) The Construction Quality Plan shall, at a minimum, comply with the requirements of the outline of the Construction Quality Plan attached as part of Schedule 11 – Design Quality Plan and Construction Quality Plan. Project Co shall submit its proposed Construction Quality Plan to Contracting Authority JBH within 60 days following Financial Close.
(e) All Quality Plans shall be subject to review by Contracting Authority JBH pursuant to Schedule 10 – Review Procedure, and Project Co shall not be entitled to implement or cause the implementation of any Quality Plan unless and until Project Co is entitled to proceed with such implementation pursuant to Schedule 10 – Review Procedure.
(f) Project Co shall implement the Quality Plans, shall perform and cause to be performed the Works in compliance with the Quality Plans, including by causing the Construction Contractor to implement the Design Quality Plan and the Construction Quality Plan.
(g) Where any aspect of the Works is performed by more than one Project Co Party, then this Article 15, in so far as relevant or appropriate to the activities to be performed by such Project Co Party, shall apply in respect of each of them and references in this Article 15 to such Project Co Party, including the Construction Contractor, shall be construed accordingly.
Appears in 1 contract
Samples: Project Agreement
Quality Plans and Systems. (a) Project Co shall cause all of the Works to be the subject of quality management systems, which shall include a Design Construction Quality Plan and a Construction Quality an Infection, Prevention and Control Plan (collectively, the “Quality Plans”), which may be incorporated into one document.
(b) All Quality Plans shall be consistent with the requirements of the Output Specifications, the Phase Commissioning Program Contract Documents and the Final Commissioning Program.
(c) The Design Quality Plan is attached as part of Schedule 11 – Design Quality Plan and Construction Quality PlanIntentionally deleted.
(d) The Construction Quality Plan and the Infection, Prevention and Control Plan shall, at a minimum, comply with the requirements of the outline of the Construction Quality Plan and the outline of the Infection, Prevention and Control Plan attached as part parts of Schedule 11 – Design Quality Plan and Construction Quality PlanPlans. Project Co shall submit its proposed Construction Quality Plan and Infection, Prevention and Control Plan to Contracting Authority within 60 30 days following Financial Close.
(e) All Quality Plans shall be subject to review by Contracting Authority and the Consultant pursuant to Schedule 10 – Review Procedure, and Project Co shall not be entitled to implement or cause the implementation of any Quality Plan unless and until Project Co is entitled to proceed with such implementation pursuant to Schedule 10 – Review Procedure.
(f) Project Co shall implement the Quality Plans, shall perform and cause to be performed the Works in compliance with the Quality Plans, including by causing the Construction Contractor to implement the Design Construction Quality Plan and the Construction Quality Infection, Prevention and Control Plan.
(g) Where any aspect of the Works is performed by more than one Project Co Party, then this Article Section 15, in so far as relevant or appropriate to the activities to be performed by such Project Co Party, shall apply in respect of each of them and references in this Article Section 15 to such Project Co Party, including the Construction Contractor, shall be construed accordingly.
Appears in 1 contract
Samples: Project Agreement
Quality Plans and Systems. (a) Project Co shall cause all of the Works to be the subject of quality management systems, which shall include a Design Quality Plan and a Construction Quality Plan (collectively, the “Quality Plans”), which may be incorporated into one document.
(b) All Quality Plans shall be consistent with the requirements of the Output Specifications, each Phase Commissioning Program, the Phase Tower Interim Completion Commissioning Program and the Final Commissioning Program.
(c) The Design Quality Plan is attached as part of Schedule 11 – Design Quality Plan and Construction Quality Plan.
(d) The Construction Quality Plan shall, at a minimum, comply with the requirements of the outline of the Construction Quality Plan attached as part of Schedule 11 – Design Quality Plan and Construction Quality Plan. Project Co shall submit its proposed Construction Quality Plan to Contracting Authority SMH within 60 days following Financial Close.
(e) All Quality Plans shall be subject to review by Contracting Authority SMH pursuant to Schedule 10 – Review Procedure, and Project Co shall not be entitled to implement or cause the implementation of any Quality Plan unless and until Project Co is entitled to proceed with such implementation pursuant to Schedule 10 – Review Procedure.
(f) Project Co shall implement the Quality Plans, shall perform and cause to be performed the Works in compliance with the Quality Plans, including by causing the Construction Contractor to implement the Design Quality Plan and the Construction Quality Plan.
(g) Where any aspect of the Works is performed by more than one Project Co Party, then this Article 15, in so far as relevant or appropriate to the activities to be performed by such Project Co Party, shall apply in respect of each of them and references in this Article 15 to such Project Co Party, including the Construction Contractor, shall be construed accordingly.
Appears in 1 contract
Samples: Project Agreement
Quality Plans and Systems. (a) Project Co shall cause all of the Works to be the subject of quality management systems, which shall include a Design Quality Plan and a Construction Quality Plan (collectively, the “Quality Plans”), which may be incorporated into one document.
(b) All Quality Plans shall be consistent with the requirements of the Output Specifications, the each Phase Commissioning Program and the Final Commissioning Program.
(c) The Design Quality Plan is attached as part of Schedule 11 – Design Quality Plan and Construction Quality Plan.
(d) The Construction Quality Plan shall, at a minimum, comply with the requirements of the outline of the Construction Quality Plan attached as part of Schedule 11 – Design Quality Plan and Construction Quality Plan. Project Co shall submit its proposed Construction Quality Plan to Contracting Authority within 60 days following Financial Close.
(e) All Quality Plans shall be subject to review by Contracting Authority pursuant to Schedule 10 – Review Procedure, and Project Co shall not be entitled to implement or cause the implementation of any Quality Plan unless and until Project Co is entitled to proceed with such implementation pursuant to Schedule 10 – Review Procedure.
(f) Project Co shall implement the Quality Plans, shall perform and cause to be performed the Works in compliance with the Quality Plans, including by causing the Construction Contractor to implement the Design Quality Plan and the Construction Quality Plan.
(g) Where any aspect of the Works is performed by more than one Project Co Party, then this Article 15, in so far as relevant or appropriate to the activities to be performed by such Project Co Party, shall apply in respect of each of them and references in this Article 15 to such Project Co Party, including the Construction Contractor, shall be construed accordingly.
Appears in 1 contract
Samples: Project Agreement
Quality Plans and Systems. (a) Project Co shall cause all of the Works to be the subject of quality management systems, which shall include a Design Quality Plan and a Construction Quality Plan (collectively, the “Quality Plans”), which may be incorporated into one document.
(b) All Quality Plans shall be consistent with the requirements of the Output Specifications, the Phase Commissioning Program and the Final Commissioning Program.
(c) The Design Quality Plan is attached as part of Schedule 11 – Design Quality Plan and Construction Quality Plan.
(d) The Construction Quality Plan shall, at a minimum, comply with the requirements of the outline of the Construction Quality Plan attached as part of Schedule 11 – Design Quality Plan and Construction Quality Plan. Project Co shall submit its proposed Construction Quality Plan to Contracting Authority HMQ within 60 days following Financial Close.
(e) All Quality Plans shall be subject to review by Contracting Authority HMQ pursuant to Schedule 10 – Review Procedure, and Project Co shall not be entitled to implement or cause the implementation of any Quality Plan unless and until Project Co is entitled to proceed with such implementation pursuant to Schedule 10 – Review Procedure.
(f) Project Co shall implement the Quality Plans, shall perform and cause to be performed the Works in compliance with the Quality Plans, including by causing the Construction Contractor to implement the Design Quality Plan and the Construction Quality Plan.
(g) Where any aspect of the Works is performed by more than one Project Co Party, then this Article Section 15, in so far as relevant or appropriate to the activities to be performed by such Project Co Party, shall apply in respect of each of them and references in this Article Section 15 to such Project Co Party, including the Construction Contractor, shall be construed accordingly.
Appears in 1 contract
Samples: Project Agreement
Quality Plans and Systems. (a) Project Co shall cause all of the Works to be the subject of quality management systems, which shall include a Design Quality Plan and a Construction Quality Plan (collectively, the “Quality Plans”), which may be incorporated into one documentdocument that applies to all Facilities.
(b) All Quality Plans shall be consistent with the requirements of the Output Specifications, the Phase Commissioning Program and the Final Commissioning Program.
(c) The Design Quality Plan is attached as part of Schedule 11 – Design Quality Plan and Construction Quality Plan.
(d) The Construction Quality Plan shall, at a minimum, comply with the requirements of the outline of the Construction Quality Plan attached as part of Schedule 11 – Design Quality Plan and Construction Quality Plan. Project Co shall submit its proposed Construction Quality Plan to Contracting Authority the CTC within 60 days following Financial Close.
(e) All Quality Plans shall be subject to review by Contracting Authority the CTC pursuant to Schedule 10 – Review Procedure, and Project Co shall not be entitled to implement or cause the implementation of any Quality Plan unless and until Project Co is entitled to proceed with such implementation pursuant to Schedule 10 – Review Procedure.
(f) Project Co shall implement the Quality Plans, shall perform and cause to be performed the Works in compliance with the Quality Plans, including by causing the Construction Contractor to implement the Design Quality Plan and the Construction Quality Plan.
(g) Where any aspect of the Works is performed by more than one Project Co Party, then this Article 15, in so far as relevant or appropriate to the activities to be performed by such Project Co Party, shall apply in respect of each of them and references in this Article 15 to such Project Co Party, including the Construction Contractor, shall be construed accordingly.
Appears in 1 contract
Samples: Project Agreement
Quality Plans and Systems. (a) Project Co shall cause all of the Works to be the subject of quality management systems, which shall include a Design Quality Plan and a Construction Quality Plan (collectively, the “Quality Plans”), which may be incorporated into one document.
(b) All Quality Plans shall be consistent with the requirements of the Output Specifications, the Phase Commissioning Program and the Final Commissioning Program.
(c) The Design Quality Plan is attached as part of Schedule 11 – Design Quality Plan and Construction Quality Plan.
(d) The Construction Quality Plan shall, at a minimum, comply with the requirements of the outline of the Construction Quality Plan attached as part of Schedule 11 – Design Quality Plan and Construction Quality Plan. Project Co shall submit its proposed Construction Quality Plan to Contracting Authority the CTC within 60 days following Financial Close.
(e) All Quality Plans shall be subject to review by Contracting Authority the CTC pursuant to Schedule 10 – Review Procedure, and Project Co shall not be entitled to implement or cause the implementation of any Quality Plan unless and until Project Co is entitled to proceed with such implementation pursuant to Schedule 10 – Review Procedure.
(f) Project Co shall implement the Quality Plans, shall perform and cause to be performed the Works in compliance with the Quality Plans, including by causing the Construction Contractor to implement the Design Quality Plan and the Construction Quality Plan.
(g) Where any aspect of the Works is performed by more than one Project Co Party, then this Article 15, in so far as relevant or appropriate to the activities to be performed by such Project Co Party, shall apply in respect of each of them and references in this Article 15 to such Project Co Party, including the Construction Contractor, shall be construed accordingly.
Appears in 1 contract
Samples: Project Agreement
Quality Plans and Systems. (a) Project Co shall cause all of the Works to be the subject of quality management systems, which shall include a Design Quality Plan and a Construction Quality Plan (collectively, the “Quality Plans”), which may be incorporated into one document.
(b) All Quality Plans shall be consistent with the requirements of the Output Specifications, the Phase Commissioning Program Specifications and the Final Commissioning Program.
(c) The Design Quality Plan is attached as part of Schedule 11 – - Design Quality Plan and Construction Quality Plan.
(d) The Construction Quality Plan shall, at a minimum, comply with the requirements of the outline of the Construction Quality Plan attached as part of Schedule 11 – - Design Quality Plan and Construction Quality Plan. Project Co shall submit its proposed Construction Quality Plan to Contracting Authority HMQ within 60 days following Financial Close.
(e) All Quality Plans shall be subject to review by Contracting Authority HMQ pursuant to Schedule 10 – - Review Procedure, and Project Co shall not be entitled to implement or cause the implementation of any Quality Plan unless and until Project Co is entitled to proceed with such implementation pursuant to Schedule 10 – - Review Procedure.
(f) Project Co shall implement the Quality Plans, shall perform and cause to be performed the Works in compliance with the Quality Plans, including by causing the Construction Contractor to implement the Design Quality Plan and the Construction Quality Plan.
(g) Where any aspect of the Works is performed by more than one Project Co Party, then this Article Section 15, in so far as relevant or appropriate to the activities to be performed by such Project Co Party, shall apply in respect of each of them and references in this Article Section 15 to such Project Co Party, including the Construction Contractor, shall be construed accordingly.
Appears in 1 contract
Samples: Project Agreement
Quality Plans and Systems.
(a) Project Co shall cause all of the Works to be the subject of quality management systems, which shall include a Design Quality Plan and a Construction Quality Plan (collectively, the “Quality Plans”), which may be incorporated into one document.
(b) All Quality Plans shall be consistent with the requirements of the Output Specifications, the Phase Commissioning Program Specifications and the Final Commissioning Program.
(c) The Design Quality Plan is attached as part of Schedule 11 – Design Quality Plan and Construction Quality Plan.
(d) The Construction Quality Plan shall, at a minimum, comply with the requirements of the outline of the Construction Quality Plan attached as part of Schedule 11 – Design Quality Plan and Construction Quality Plan. Project Co shall submit its proposed Construction Quality Plan to Contracting Authority the College within 60 days following Financial Close.
(e) All Quality Plans shall be subject to review by Contracting Authority the College pursuant to Schedule 10 – Review Procedure, and Project Co shall not be entitled to implement or cause the implementation of any Quality Plan unless and until Project Co is entitled to proceed with such implementation pursuant to Schedule 10 – Review Procedure.
(f) Project Co shall implement the Quality Plans, shall perform and cause to be performed the Works in compliance with the Quality Plans, including by causing the Construction Contractor to implement the Design Quality Plan and the Construction Quality Plan.
(g) Where any aspect of the Works is performed by more than one Project Co Party, then this Article 15, in so far as relevant or appropriate to the activities to be performed by such Project Co Party, shall apply in respect of each of them and references in this Article 15 to such Project Co Party, including the Construction Contractor, shall be construed accordingly.
Appears in 1 contract
Samples: Project Agreement
Quality Plans and Systems. (a) Project Co shall cause all of the Works to be the subject of quality management systems, which shall include a Design Quality Plan and a Construction Quality Plan (collectively, the “Quality Plans”), which may be incorporated into one document.
(b) All Quality Plans shall be consistent with the requirements of the Output Specifications, the Phase Commissioning Program and the Final Commissioning Program.
(c) The Design Quality Plan is attached as part of Schedule 11 – Design Quality Plan and Construction Quality Plan.
(d) The Construction Quality Plan shall, at a minimum, comply with the requirements of the outline of the Construction Quality Plan attached as part of Schedule 11 – Design Quality Plan and Construction Quality Plan. Project Co shall submit its proposed Construction Quality Plan to Contracting Authority the College within 60 days following Financial Close.
(e) All Quality Plans shall be subject to review by Contracting Authority the College pursuant to Schedule 10 – Review Procedure, and Project Co shall not be entitled to implement or cause the implementation of any Quality Plan unless and until Project Co is entitled to proceed with such implementation pursuant to Schedule 10 – Review Procedure.
(f) Project Co shall implement the Quality Plans, shall perform and cause to be performed the Works in compliance with the Quality Plans, including by causing the Construction Contractor to implement the Design Quality Plan and the Construction Quality Plan.
(g) Where any aspect of the Works is performed by more than one Project Co Party, then this Article 15, in so far as relevant or appropriate to the activities to be performed by such Project Co Party, shall apply in respect of each of them and references in this Article 15 to such Project Co Party, including the Construction Contractor, shall be construed accordingly.
Appears in 1 contract
Samples: Project Agreement
Quality Plans and Systems. (a) Project Co shall cause all of the Works to be the subject of quality management systems, which shall include a Design Quality Plan and a Construction Quality Plan (collectively, the “Quality Plans”), which may be incorporated into one document.
(b) All Quality Plans shall be consistent with the requirements of the Output Specifications, the Phase Commissioning Program Specifications and the Final Commissioning Program.
(c) The Design Quality Plan is attached as part of Schedule 11 – Design Quality Plan and Construction Quality Plan.
(d) The Construction Quality Plan shall, at a minimum, comply with the requirements of the outline of the Construction Quality Plan attached as part of Schedule 11 – Design Quality Plan and Construction Quality Plan. Project Co shall submit its proposed Construction Quality Plan to Contracting Authority the College within 60 days following Financial Close.
(e) All Quality Plans shall be subject to review by Contracting Authority the College pursuant to Schedule 10 – Review Procedure, and Project Co shall not be entitled to implement or cause the implementation of any Quality Plan unless and until Project Co is entitled to proceed with such implementation pursuant to Schedule 10 – Review Procedure.
(f) Project Co shall implement the Quality Plans, shall perform and cause to be performed the Works in compliance with the Quality Plans, including by causing the Construction Contractor to implement the Design Quality Plan and the Construction Quality Plan.
(g) Where any aspect of the Works is performed by more than one Project Co Party, then this Article 15, in so far as relevant or appropriate to the activities to be performed by such Project Co Party, shall apply in respect of each of them and references in this Article 15 to such Project Co Party, including the Construction Contractor, shall be construed accordingly.
Appears in 1 contract
Samples: Project Agreement