Railway Flagger Services. 1.05.01 The Contractor must give Railway’s Roadmaster Xxxxx Xxxxxxxxxxx at xxxxx.xxxxxxxxxxx@xxxx.xxx and Rail Pros Field Services at xxxxxxxx@xxxxxxxxxx.xxx a minimum of thirty (30) calendar days advance notice when flagging services will be required so that the Roadmaster can make appropriate arrangements (i.e., bulletin the flagger’s position). If flagging services are scheduled in advance by the Contractor and it is subsequently determined by the parties hereto that such services are no longer necessary, the Contractor must give the Roadmaster five (5) working days advance notice so that appropriate arrangements can be made to abolish the position pursuant to union requirements. 1.05.02 Unless determined otherwise by Railway’s Project Representative, Railway flagger will be required and furnished when Contractor’s work activities are located over, under and/or within twenty-five (25) feet measured horizontally from centerline of the nearest track and when cranes or similar equipment positioned beyond 25-feet from the track centerline could foul the track in the event of tip over or other catastrophic occurrence, but not limited thereto for the following conditions:
Appears in 2 contracts
Samples: Contract Proposal, Contract Proposal
Railway Flagger Services. 1.05.01 The Contractor must give Railway’s Roadmaster Xxxxx Xxxxxxxxxxx at xxxxx.xxxxxxxxxxx@xxxx.xxx (telephone 000-000-0000) and Railway’s contractor (Rail Pros Field Services at xxxxxxxx@xxxxxxxxxx.xxx Pros- xxxxxxxx@xxxxxxxxxx.xxx) a minimum of thirty (30) calendar days advance notice when flagging services will be required so that the Roadmaster can make appropriate arrangements (i.e., bulletin the flagger’s position). If flagging services are scheduled in advance by the Contractor and it is subsequently determined by the parties hereto that such services are no longer necessary, the Contractor must give the Roadmaster five (5) working days advance notice so that appropriate arrangements can be made to abolish the position pursuant to union requirements.
1.05.02 Unless determined otherwise by Railway’s Project Representative, Railway flagger will be required and furnished when Contractor’s work activities are located over, under and/or within twenty-five (25) feet measured horizontally from centerline of the nearest track and when cranes or similar equipment positioned beyond 25-feet from the track centerline could foul the track in the event of tip over or other catastrophic occurrence, but not limited thereto for the following conditions:
Appears in 1 contract
Samples: Contract Proposal
Railway Flagger Services. 1.05.01 The Contractor must give Railway’s Roadmaster Roadmaster Xxxxx Xxxxxxxxxxx at xxxxx.xxxxxxxxxxx@xxxx.xxx Xxxxx.Xxxxxxxxxxx@xxxx.xxx and Rail Pros BNSF Third Party Consultant RailPros Field Services at xxxxxxxx@xxxxxxxxxx.xxx a minimum of thirty (30) calendar days advance notice when flagging services will be required so that the Roadmaster can make appropriate arrangements (i.e., bulletin the flagger’s position). If flagging services are scheduled in advance by the Contractor and it is subsequently determined by the parties hereto that such services are no longer necessary, the Contractor must give the Roadmaster five (5) working days advance notice so that appropriate arrangements can be made to abolish the position pursuant to union requirements.
1.05.02 Unless determined otherwise by Railway’s Project Representative, Railway flagger will be required and furnished when Contractor’s work activities are located over, under and/or within twenty-five (25) feet measured horizontally from centerline of the nearest track and when cranes or similar equipment positioned beyond 25-feet from the track centerline could foul the track in the event of tip over or other catastrophic occurrence, but not limited thereto for the following conditions:
Appears in 1 contract
Samples: Contract Proposal
Railway Flagger Services. 1.05.01 The Contractor must give Railway’s Roadmaster Xxxxx Xxxxxxxxxxx at xxxxx.xxxxxxxxxxx@xxxx.xxx Xxxx Xxxxxxxxx and Rail Pros BNSF Third Party Consultant RailPros Field Services at xxxxxxxx@xxxxxxxxxx.xxx a minimum of thirty (30) calendar days advance notice when flagging services will be required so that the Roadmaster can make appropriate arrangements (i.e., bulletin the flagger’s position). If flagging services are scheduled in advance by the Contractor and it is subsequently determined by the parties hereto that such services are no longer necessary, the Contractor must give the Roadmaster five (5) working days advance notice so that appropriate arrangements can be made to abolish the position pursuant to union requirements.
1.05.02 Unless determined otherwise by Railway’s Project Representative, Railway flagger will be required and furnished when Contractor’s work activities are located over, under and/or within twenty-five (25) feet measured horizontally from centerline of the nearest track and when cranes or similar equipment positioned beyond 25-feet from the track centerline could foul the track in the event of tip over or other catastrophic occurrence, but not limited thereto for the following conditions:
Appears in 1 contract
Samples: Contract Proposal
Railway Flagger Services. 1.05.01 The Contractor must give Railway’s Roadmaster Xxxxx Xxxxxxxxxxx at xxxxx.xxxxxxxxxxx@xxxx.xxx (telephone 000-000-0000) and Railway’s contractor (Rail Pros Field Services at xxxxxxxx@xxxxxxxxxx.xxx Pros- xxxxxxxx@xxxxxxxxxx.xxx) a minimum of thirty (30) calendar days advance notice when flagging services will be required so that the Roadmaster can make appropriate arrangements (i.e., bulletin the flagger’s position). If flagging services are scheduled in advance by the Contractor and it is subsequently determined by the parties hereto that such services are no longer necessary, the Contractor must give the Roadmaster five (5) working days advance notice so that appropriate arrangements can be made to abolish the position pursuant to union requirements.
1.05.02 Unless determined otherwise by Railway’s Project Representative, Railway flagger will be required and furnished when Contractor’s work activities are located over, under and/or within twenty-five (25) feet measured horizontally from centerline of the nearest track and when cranes or similar equipment positioned beyond 25-feet from the track centerline could foul the track in the event of tip over or other catastrophic occurrence, but not limited thereto for the following conditions:
Appears in 1 contract
Samples: Contract Proposal