Rate of Progress. 15.1 If for any reason, which does not entitle the Contractor to an extension of time as provided by Article 16.1 of this Contract, the rate of progress of the Works or any section of the Works is at anytime considered by UNICEF to be too slow to comply with the time for completion, the Contractor shall immediately take such steps as are necessary to expedite progress so as to be able to complete the Works on time. The Contractor shall not be entitled to any additional payment for taking such steps.