Re-Study. If Re-Study of the Interconnection Facilities Study is required due to a higher queued project dropping out of the queue or a modification of a higher queued project pursuant to Section 4.4, Transmission Provider shall so notify Interconnection Customer in writing. Such Re-Study shall take no longer than sixty (60) Calendar Days from the date of notice. Any cost of Re-Study shall be borne by the Interconnection Customer being re-studied.
Appears in 10 contracts
Samples: Standard Large Generator Interconnection Procedures, Standard Large Generator Interconnection Agreement (Lgia), Large Generator Interconnection Agreement (Lgia)
Re-Study. If Re-Study of the Interconnection Facilities Feasibility Study is required due to a higher queued project dropping out of the queue queue, or a modification of a higher queued project pursuant subject to Section 4.4, or re-designation of the Point of Interconnection pursuant to Section 6.1, Transmission Provider shall so notify Interconnection Customer in writing. Such Transmission Provider shall use Reasonable Efforts to complete such Re-Study shall take no longer than sixty within forty-five (6045) Calendar Days from the date of the notice. Any cost of Re-Study shall be borne by the Interconnection Customer being re-studied.
Appears in 6 contracts
Samples: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)
Re-Study. If Re-Study of the Interconnection Facilities Study is required due to a higher queued project dropping out of the queue or a modification of a higher queued project pursuant to Section 4.4, Transmission Provider shall so notify Interconnection Customer in writing. Such Transmission Provider shall use Reasonable Efforts to complete such Re-Study shall take no longer than within sixty (60) Calendar Days from the date of notice. Any cost of Re-Study shall be borne by the Interconnection Customer being re-studied.
Appears in 6 contracts
Samples: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)
Re-Study. If Re-Study of the Interconnection Facilities Feasibility Study is required due to a higher queued project dropping out of the queue queue, or a modification of a higher queued project pursuant subject to Section 4.4, or re-designation of the Point of Interconnection pursuant to Section 6.1 Transmission Provider shall so notify Interconnection Customer in writing. Such Re-Study shall take no not longer than sixty forty-five (6045) Calendar Days from the date of the notice. Any cost of Re-Study shall be borne by the Interconnection Customer being re-re- studied.
Appears in 6 contracts
Samples: Standard Large Generator Interconnection Procedures, Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Procedures (Lgip)
Re-Study. If Rere-Study study of the Interconnection Facilities Study is required due to a higher queued project dropping out of the queue or a modification of a higher queued project pursuant material change relating to Section 4.4prior study assumptions, Transmission Provider shall so notify Interconnection Customer in writing. Such Rere-Study study shall take no longer than sixty (60) Calendar Days from the date of notice. Any In accordance with Section 8.1, Interconnection Customer shall pay the estimated cost of Re-Study shall be borne by the Interconnection Customer being re-studiedstudy in advance and shall pay for the actual cost of the re-study.
Appears in 4 contracts
Samples: Generator Interconnection Agreement (Gia), Generator Interconnection Agreement (Gia), Generator Interconnection Agreement (Gia)
Re-Study. If a Re-Study of the Interconnection Facilities Study is required due to a higher queued project dropping out of the queue or a modification of a higher queued project pursuant to Section 4.4, Transmission Provider shall so notify Interconnection Customer in writing. Such Transmission Provider shall use Reasonable Efforts to complete the Re-Study shall take no longer than sixty within ninety (6090) Calendar Days from the date of notice. Any cost of Re-Study shall be borne by the Interconnection Customer being re-studied.
Appears in 3 contracts
Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement
Re-Study. If Re-Study of the Interconnection Facilities Feasibility Study is required due to a higher queued project dropping out of the queue queue, or a modification of a higher queued project pursuant subject to Section 4.4, or re-designation of the Point of Interconnection pursuant to Section 6.1 Transmission Provider shall so notify Interconnection Customer in writing. Such Re-Study shall take no not longer than sixty forty-five (6045) Calendar Days from the date of the notice. Any cost of Re-Study shall be borne by the Interconnection Customer being re-studied.
Appears in 3 contracts
Samples: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Procedures (Lgip) and Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Procedures (Lgip)
Re-Study. If Re-Study of the Interconnection Facilities Study is required due to a higher queued project dropping out of the queue or a modification of a higher queued project pursuant to Section 4.4, Transmission Provider shall so notify Interconnection Customer in writing. Such Re-Study shall take no longer than sixty (60) Calendar Days from the date of notice. Any cost of Re-Study shall be borne by the Interconnection Customer being re-studied.
Appears in 2 contracts
Samples: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)
Re-Study. If Re-Study of the Interconnection Facilities Feasibility Study is required due to a higher queued project dropping out of the queue queue, or a modification of a higher queued project subject to Section 5.4, or re-designation of the Point of Interconnection pursuant to Section 4.4, 8.1 Transmission Provider shall so notify Interconnection Customer in writing. Such Re-Study shall take no longer than sixty forty-five (6045) Calendar Days from the date of the notice. Any cost of Re-Study shall be borne by the Interconnection Customer being re-studied.
Appears in 2 contracts
Samples: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)
Re-Study. If Re-Study of the Interconnection Facilities Feasibility Study is required due to a higher queued project dropping out of the queue queue, or a modification of a higher queued project pursuant subject to Section 4.4, or re-designation of the Point of Interconnection pursuant to Section 6.1 Transmission Provider shall so notify Interconnection Customer in writing. Such Re-Study shall take no not longer than sixty forty-five (6045) Calendar Days from the date of the notice. Any cost of Re-Study shall be borne by the Interconnection Customer being re-studied.
Appears in 2 contracts
Samples: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)
Re-Study. If Re-Study of the Interconnection Facilities Feasibility Study is required due to a higher queued project dropping out of the queue queue, or a modification of a higher queued project pursuant subject to Section 4.4, or re-designation of the Point of Interconnection pursuant to Section
6.1 Transmission Provider shall so notify Interconnection Customer in writing. Such Re-Study shall take no not longer than sixty forty-five (6045) Calendar Days from the date of the notice. Any cost of Re-Study shall be borne by the Interconnection Customer being re-studied.
Appears in 1 contract
Samples: Standard Large Generator Interconnection Agreement (Lgia)
Re-Study. If Rere-Study study of the Interconnection Facilities Study is required due to a higher queued project dropping out of the queue or a modification of a higher queued project pursuant to Section 4.4, Transmission Provider shall so notify Interconnection Customer in writing. Such Rere-Study study shall take no longer than sixty (60) Calendar Days from the date of notice. Any cost of Rere-Study study shall be borne by the Interconnection Customer being re-studied.
Appears in 1 contract
Samples: Standard Generator Interconnection Agreement (Sgia)
Re-Study. If Re-Study of the Interconnection Facilities Study is required due to a higher queued project dropping out of the queue or a modification of a higher queued project pursuant to Section 4.4, or as a result of Section 9.2, Transmission Provider shall so notify Interconnection Customer in writing. Such Re-Study shall take no longer than sixty (60) Calendar Days from the date of notice. Any cost of Re-Study shall be borne by the Interconnection Customer being re-studied.
Appears in 1 contract
Samples: Standard Large Generator Interconnection Procedures (Lgip)
Re-Study. If Rere-Study study of the Interconnection Facilities Feasibility Study is required due to a higher queued project dropping out of the queue queue, or a modification of a higher queued project pursuant subject to Section 4.4, or re-designation of the Point of Interconnection pursuant to Section 6.1 Transmission Provider shall so notify Interconnection Customer in writing. Such ReTransmission Provider shall use Reasonable Efforts to complete such re-Study shall take study no longer later than sixty forty-five (6045) Calendar Days from the date of the notice. Any cost of Re-Study re- study shall be borne by the Interconnection Customer being re-studied.
Appears in 1 contract
Samples: Standard Generator Interconnection Agreement (Sgia)
Re-Study. If Re-Study of the Interconnection Facilities Feasibility Study is required due to a higher queued project dropping out of the queue queue, or a modification of a higher queued project subject to Section 45.4, or re-designation of the Point of Interconnection pursuant to Section 4.4, 68.1 Transmission Provider shall so notify Interconnection Customer in writing. Such Re-Study shall take no not longer than sixty forty-five (6045) Calendar Days from the date of the notice. Any cost of Re-Study shall be borne by the Interconnection Customer being re-studied.
Appears in 1 contract
Samples: Standard Large Generator Interconnection Agreement (Lgia)