Reactions to unplanned outages and curtailment. 4.1 In case of a System Event that is expected to last more than two (2) weeks, the Buyer may, on notice of no more than forty eight (48) hours during the System Event, request the Seller to undertake those activities possible that were planned for the next Scheduled Outage, taking into account the Seller's requirements to mobilize overhaul resources and have spares and equipment available, to be commenced during the time period of System Event but allowing a reasonable period to mobilize following notification. 4.2 The Seller shall use reasonable endeavors to accommodate such rescheduling if it is consistent with the standards of a Reasonable and Prudent Operator and the Seller, acting reasonably, considers it feasible to mobilize necessary resource, spares and equipment to undertake an effective Scheduled Outage. 4.3 The Buyer should compensate the Seller for any additional costs incurred to mobilize resources and spares rapidly during the System Event Outage, and for any power revenue losses resulting from extensions to the duration of the outage which result from difficulties in mobilizing the outage at short notice, or as a result of a future further Scheduled Outage still being required because the resources needed for all the planned maintenance may not have been possible to mobilize at short notice during the System Event. 1. Monthly Facility Unit Forecast Generation Profile Day MWh Available MW DAY SPECIFIC INFORMATION (IF APPLICABLE) Time Hours MWh Available MW
Appears in 5 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Reactions to unplanned outages and curtailment. 4.1 In case of a System Event that is expected to last more than two (2) weeks, the Buyer may, on notice of no more than forty eight (48) hours during the System Event, request the Seller to undertake those activities possible that were planned for the next Scheduled Outage, taking into account the Seller's requirements to mobilize overhaul resources and have spares and equipment available, to be commenced during the time period of System Event but allowing a reasonable period to mobilize following notification.
4.2 The Seller shall use reasonable endeavors to accommodate such rescheduling if it is consistent with the standards of a Reasonable and Prudent Operator and the Seller, acting reasonably, considers it feasible to mobilize necessary resource, spares and equipment to undertake an effective Scheduled Outage.
4.3 The Buyer should compensate the Seller for any additional costs incurred to mobilize resources and spares rapidly during the System Event Outage, and for any power revenue losses resulting from extensions to the duration of the outage which result from difficulties in mobilizing the outage at short notice, or as a result of a future further Scheduled Outage still being required because the resources needed for all the planned maintenance may not have been possible to mobilize at short notice during the System Event.
1. Monthly Facility Unit Forecast Generation Profile Day MWh Available MW DAY SPECIFIC INFORMATION (IF APPLICABLE) Time Hours MWh Available MW
Appears in 1 contract
Samples: Power Purchase Agreement