Repeated failure. Without limiting any other rights or remedies Spark may have, if a Stage fails its Acceptance Tests a second time after being resubmitted under clause 27.4(b), Supplier will be deemed to have missed a Contract Milestone and failed to remedy the delay within the Milestone Remedy Period, and Spark will be entitled to terminate under clause 26.4 accordingly.
Appears in 5 contracts
Samples: Purchase Agreement, Purchase Agreement, Purchase Agreement
Repeated failure. Without limiting any other rights or remedies Spark may have, if a Stage fails its Acceptance Tests a second time after being resubmitted under clause 27.4(b26.4(b), Supplier will be deemed to have missed a Contract Milestone and failed to remedy the delay within the Milestone Remedy Period, and Spark will be entitled to terminate under clause 26.4 25.4 accordingly.
Appears in 1 contract
Samples: Purchase Agreement