Common use of Reporting of Non-Force Majeure Events Clause in Contracts

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”) shall notify the other Parties when the Notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.

Appears in 265 contracts

Samples: Engineering, Procurement, and Construction Agreement, Service Agreement, Service Agreement

AutoNDA by SimpleDocs

Reporting of Non-Force Majeure Events. Each Party (the “Notifying notifying Party”) shall notify the other Parties when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this AgreementLGIA.

Appears in 137 contracts

Samples: Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Reporting of Non-Force Majeure Events. Each A Party (the “Notifying notifying Party”) shall notify the other Parties when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement GIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the any Party receiving such notification to allege a cause for anticipatory breach of this AgreementGIA.

Appears in 54 contracts

Samples: Generator Interconnection Agreement (Gia), Generator Interconnection Agreement (Gia), Generator Interconnection Agreement (Gia)

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”) shall notify the other Parties when the Notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.

Appears in 52 contracts

Samples: Standard Large Generator Interconnection Agreement, Interconnection Agreement, Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”) shall notify the other Parties Party when the Notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.

Appears in 30 contracts

Samples: Interconnection Agreement, Lgia (Large Generator Interconnection Agreement), Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying "notifying Party") shall notify the other Parties Party when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this AgreementLGIA.

Appears in 23 contracts

Samples: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)

Reporting of Non-Force Majeure Events. Each Party (the "Notifying Party") shall notify the other Parties when the Notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.

Appears in 23 contracts

Samples: Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying "notifying Party") shall notify the other Parties when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this AgreementLGIA.

Appears in 18 contracts

Samples: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying notifying Party”) shall notify the other Parties Party(ies) when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach Breach of this AgreementLGIA.

Appears in 13 contracts

Samples: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”) shall notify the other Parties when the Notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.Agreement.‌

Appears in 13 contracts

Samples: Interconnection Agreement, Engineering, Procurement, and Construction Agreement, Transmission Project Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying "notifying Party") shall notify the other Parties when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement GIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article article shall not entitle the Party Parties receiving such notification to allege a cause for anticipatory breach of this AgreementGIA.

Appears in 11 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”) shall notify the other Parties Party when the Notifying Party it becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure eventMajeure. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including including, but not limited to, the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article Section 12.1 shall not entitle the receiving Party receiving such notification to allege a cause of action for anticipatory breach Breach of this Agreement.

Appears in 8 contracts

Samples: Designated Entity Agreement, Designated Entity Agreement, Designated Entity Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”) shall notify the other Parties PartiesParty when the Notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.

Appears in 6 contracts

Samples: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying notifying Party”) shall notify the other Parties Party when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this AgreementLGIA.

Appears in 6 contracts

Samples: Standard Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”) shall notify the other Parties Party when the Notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.

Appears in 6 contracts

Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying notifying Party) shall notify the other Parties Party when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement SGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this AgreementSGIA.

Appears in 5 contracts

Samples: Standard Generator Interconnection Agreement (Sgia), Standard Generator Interconnection Agreement (Sgia), Standard Generator Interconnection Agreement (Sgia)

Reporting of Non-Force Majeure Events. Each Party (the “Notifying notifying Party”) shall notify the other Parties Party when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation cooperation, or information provided under this Article Section shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.

Appears in 5 contracts

Samples: Approved Project Sponsor Agreement (Apsa), Approved Project Sponsor Agreement (Apsa), Approved Project Sponsor Agreement (Apsa)

Reporting of Non-Force Majeure Events. Each Party (the “Notifying "notifying Party") shall notify the other Parties when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article article shall not entitle the Party Parties receiving such notification to allege a cause for anticipatory breach of this AgreementLGIA.

Appears in 4 contracts

Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying notifying Party”) shall notify the other Parties Party(ies) when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this AgreementLGIA.

Appears in 4 contracts

Samples: Large Generator Interconnection Agreement, Service Agreements, Service Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying "notifying Party") shall notify the other Parties Party when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement GIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this AgreementGIA.

Appears in 4 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”) shall notify the other Parties when the Notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.. 56

Appears in 3 contracts

Samples: Lgia, Lgia, Lgia

Reporting of Non-Force Majeure Events. Each A Party (the “Notifying notifying Party”) shall notify the other Parties when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the any Party receiving such notification to allege a cause for anticipatory breach of this Agreement.

Appears in 3 contracts

Samples: Transmission Connection Agreement, Transmission Connection Agreement, Transmission Connection Agreement

Reporting of Non-Force Majeure Events. Each A Party (the “Notifying notifying Party”) shall notify the other Parties when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the any Party receiving such notification to allege a cause for anticipatory breach of this AgreementLGIA.

Appears in 2 contracts

Samples: Large Generator Interconnection Agreement (ITC Holdings Corp.), Large Generator Interconnection Agreement (ITC Holdings Corp.)

Reporting of Non-Force Majeure Events. Each Party (the “Notifying notifying Party”) shall notify the other Parties when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.LGIA.‌

Appears in 2 contracts

Samples: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”) shall notify the other Parties when the Notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other 29 SERVICE AGREEMENT NO. 2476 than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.

Appears in 2 contracts

Samples: Epc Agreement, Epc Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”) shall notify the other Parties Party when the Notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the datedate and duration of, duration, and reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article Section shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.

Appears in 2 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the "Notifying Party") shall notify the other Parties when the Notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide 47 SERVICE AGREEMENT NO. 2599 necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.

Appears in 2 contracts

Samples: Service Agreement, Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”) shall notify the other Parties when the Notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.Agreement.‌

Appears in 2 contracts

Samples: Engineering, Procurement, and Construction Agreement, Engineering, Procurement, Construction, Operation, and Maintenance Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying "notifying Party") shall notify the other Parties Party when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement QF-LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this AgreementQF-LGIA.

Appears in 2 contracts

Samples: Qualifying Facility Large Generator Interconnection Agreement, Qualifying Facility Large Generator Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”) shall notify the other Parties when the Notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.. 56 SERVICE AGREEMENT NO. 2341

Appears in 1 contract

Samples: Service Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”) shall notify the other Parties when the Notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.. 56 SERVICE AGREEMENT NO. 1774

Appears in 1 contract

Samples: Lgia

Reporting of Non-Force Majeure Events. Each Party (the “Notifying "notifying Party") shall notify the other Parties Party when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement Provisional LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this AgreementProvisional LGIA.

Appears in 1 contract

Samples: Provisional Large Generator Interconnection Agreement

AutoNDA by SimpleDocs

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”) shall notify the other Parties when the Notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.. 38 SERVICE AGREEMENT NO. 2772

Appears in 1 contract

Samples: Transmission Facility Interconnection Agreement

Reporting of Non-Force Majeure Events. Each A Party (the “Notifying "notifying Party") shall notify the other Parties when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the any Party receiving such notification to allege a cause for anticipatory breach of this AgreementLGIA.

Appears in 1 contract

Samples: Asset Sale Agreement (CMS Energy Corp)

Reporting of Non-Force Majeure Events. Each Party (the “Notifying notifying Party”) shall notify the other Parties when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement UFA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this AgreementUFA.

Appears in 1 contract

Samples: Affected Participating Transmission Owner Upgrade Facilities Agreement (Ufa)

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”) shall notify the other Parties when the Notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability inability‌ to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.

Appears in 1 contract

Samples: Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”) shall notify the each other Parties Party when the Notifying Party it becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure eventan event of force majeure as defined in this Agreement. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including including, but not limited to, the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the receiving Party receiving such notification to allege a cause of action for anticipatory breach of this Agreement.

Appears in 1 contract

Samples: Construction Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying notifying Party”) shall notify the other Parties when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement a material term or provision ofthis IA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, and reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article article shall not entitle the Party Parties receiving such notification to allege a cause for anticipatory breach of this Agreement.ofthis IA,

Appears in 1 contract

Samples: Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”) shall notify the other Parties when the Notifying Party it becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure eventMajeure. The Parties agree to shall cooperate with each other and provide necessary information regarding such inability to comply, including including, but not limited to, the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article Section 9.1 shall not entitle the receiving Party receiving such notification to allege a cause of action for anticipatory breach of this Agreement.

Appears in 1 contract

Samples: Interconnection Coordination Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”) shall notify the other Parties when the Notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide 47 SERVICE AGREEMENT NO. 2605 necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.

Appears in 1 contract

Samples: Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”notifying Party ) shall notify the other Parties when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this AgreementLGIA.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying "notifying Party") shall notify the other Parties when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement Interim GIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article article shall not entitle the Party Parties receiving such notification to allege a cause for anticipatory breach of this AgreementInterim GIA.

Appears in 1 contract

Samples: Interim Generator Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying notifying Party”) shall notify the other Parties Party when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement GIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this AgreementGIA.

Appears in 1 contract

Samples: Generator Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”) shall notify the other Parties Party when the Notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure eventevent (notice of which shall be governed by Section 16.1). The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.

Appears in 1 contract

Samples: Transmission Facility Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”) shall notify the other Parties PartiesParty when the Notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. (notice of which shall be governed by Section 16.1). The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.

Appears in 1 contract

Samples: Transmission Facility Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”) shall notify the other Parties when the Notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information 66 SERVICE AGREEMENT NO. 2232 provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.

Appears in 1 contract

Samples: Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying notifying Party”) shall notify the other Parties Party when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement QFTIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, and reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.QFTIA.‌

Appears in 1 contract

Samples: Qualifying Facility Transmission Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying "notifying Party") shall notify the other Parties Party when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement JAGITS for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this AgreementJAGITS.

Appears in 1 contract

Samples: Jea Agreement for Generator Interconnection to Transmission System (Jagits)

Reporting of Non-Force Majeure Events. Each Party (the “Notifying notifying Party”) shall notify the other Parties Party when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, and reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this AgreementLGIA.

Appears in 1 contract

Samples: Standard Large Generator Interconnection Agreement (Lgia)

Reporting of Non-Force Majeure Events. Each Party (the “Notifying Party”) shall notify the other Parties when the Notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for SERVICE AGREEMENT NO. 2604 the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.

Appears in 1 contract

Samples: Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying "notifying Party") shall notify the other Parties when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

Reporting of Non-Force Majeure Events. Each Party (the “Notifying "notifying Party") shall notify the other Parties Party when the Notifying notifying Party becomes aware of its inability to comply with the provisions of this Agreement LGIA for a reason other than a Force Majeure event. The Parties agree to cooperate with each other and provide necessary information regarding such inability to comply, including the date, duration, reason for the inability to comply, and corrective actions taken or planned to be taken with respect to such inability to comply. Notwithstanding the foregoing, notification, cooperation or information provided under this Article article shall not entitle the Party receiving such notification to allege a cause for anticipatory breach of this Agreement.LGIA.‌

Appears in 1 contract

Samples: Large Generator Interconnection Agreement (Lgia)