Representations and warranties of the Contractor. 5.1 The Contractor represents and warrants that he has visited the Area, that the same is suitable for the System’s construction in a world class manufacturing way and in compliance with the Technical Specifications and the Applicable Law and has already checked the absence of obstacles of a technical and/or geological and/or hydraulic and/or legal and/or administrative nature with reference to the commencement of the Works. Any and all designs, engineering and project specifications produced and delivered by the Contractor shall be prepared and signed by a duly certified engineer and are appropriate to fully accomplish the purpose of this Contract. Therefore, any approval or acknowledgement by the Principal of the technical designs and documentation shall not release the Contractor from its duties, warranties and liabilities as to the exact delivery of the System and performance of the Works. 5.2 The Contractor represents and warrants that at the time of execution hereof he, also through the Developer, holds a valid Building Permit, accepted STMC and Enel’s comunicazione di conclusione iter autorizzativo in relation to the System and that it is unaware of any facts or circumstances, of any kind whatsoever that might prejudice the formation or validity of any System’s Applicable Permits, or the transfer or registration thereof in favour of the Principal. The Area, object of the final building right agreement regarding the Land Use Rights, are free from any encumbrances or burden and there are no third parties (apart from the lawful owners) who can claim any right in relation to such lands, nor prevent the acquisition by the Principal of the Area free from any encumbrances or burden. 5.3 The Contractor also represents and warrants to the Principal, with reference to the “turn key” nature of this Contract, to be the only Party liable to the Principal concerning the Works’ complete construction in a world class manufacturing way, undertaking, thus, all liability towards the Principal with reference to all the activities whose performance is entrusted to sub-contractors, pursuant to this Contract. 5.4 The Contractor expresses his consent, as of the date hereof, to the assignment and/or pledge in favour of the Financing Entity (or any third parties appointed by the latter) by the Principal of his receivables deriving from this Contract and shall provide his cooperation in the performance of all the formalities and shall provide any further consent, necessary or expedient, required as to the assignment and/or pledge's formation. 5.5 The Contractor guarantees to dedicate to the System, at all times, the adequate number of workers and to timely and completely pay all wages, insurance fees and public charges, social securities, etc. for the workers on the sites. 5.6 There are no impediments, to Contractor's knowledge that could compromise in some way the obtaining of the authorizations for the construction of the grid infrastructure necessary to connect the System to the grid.

Appears in 2 contracts

Samples: Engineering Procurement & Construction Contract (Ellomay Capital Ltd.), Engineering Procurement & Construction Contract (Ellomay Capital Ltd.)

AutoNDA by SimpleDocs

Representations and warranties of the Contractor. 5.1 The Contractor represents and warrants that he has visited the Area, that the same is suitable for the System’s construction realization in a world class manufacturing way and in compliance with the Technical Specifications and the Applicable Law and has already checked the absence of obstacles of a technical and/or geological and/or hydraulic and/or legal and/or administrative nature with reference to the commencement of the Works. Any and all designs, engineering and project specifications produced and delivered by the Contractor shall be prepared and signed by a duly certified engineer and are appropriate to fully accomplish the purpose of this Contract. Therefore, any approval or acknowledgement by the Principal of the technical designs and documentation shall not release the Contractor from its duties, warranties and liabilities as to the exact delivery of the System and performance of the Works. 5.2 The Contractor represents and warrants that at the time of execution hereof he, also through the Developer, holds a valid Building Permit, Permit and accepted STMC and Enel’s comunicazione di conclusione iter autorizzativo in relation to the System and that it he is unaware of any facts or circumstances, of any kind whatsoever that might prejudice the formation or validity of any System’s Applicable Permits, or the transfer or registration thereof in favour of the Principal. The Area, object of the final building right agreement regarding the Land Use Rights, are free from any encumbrances or burden and there are no third parties (apart from the lawful owners) who can claim any right in relation to such lands, nor prevent the acquisition by the Principal of the Area free from any encumbrances or burden. 5.3 The Contractor also represents and warrants to the Principal, with reference to the “turn key” nature of this Contract, to be the only Party liable to the Principal concerning the Works’ complete construction realization in a world class manufacturing way, undertaking, thus, all liability towards the Principal with reference to all the activities whose performance is entrusted to sub-contractors, pursuant to this Contract. 5.4 The Contractor expresses his consent, as of the date hereof, to the assignment and/or pledge in favour of the Financing Entity (or any third parties appointed by the latter) by the Principal of his receivables deriving from this Contract and shall provide his cooperation in the performance of all the formalities and shall provide any further consent, necessary or expedient, required as to the assignment and/or pledge's formation. 5.5 The Contractor guarantees to dedicate to the System, at all times, the adequate number of workers and to timely and completely pay all wages, insurance fees and public charges, social securities, etc. for the workers on the sites. 5.6 There are no impediments, to Contractor's knowledge that could compromise in some way the obtaining of the authorizations for the construction of the grid infrastructure necessary to connect the System to the grid.

Appears in 2 contracts

Samples: Engineering Procurement & Construction Contract (Ellomay Capital Ltd.), Engineering Procurement & Construction Contract (Ellomay Capital Ltd.)

AutoNDA by SimpleDocs

Representations and warranties of the Contractor. 5.1 The Contractor represents and warrants that he has visited the Area, that the same is suitable for the SystemPlant’s construction in a world class manufacturing way and in compliance with the Technical Specifications and the Applicable Law and has already checked the absence of obstacles of a technical and/or geological and/or hydraulic and/or legal and/or administrative nature with reference to the commencement of the Works. Any and all designs, engineering and project specifications produced and delivered by the Contractor shall be prepared and signed by a duly certified engineer and are appropriate to fully accomplish the purpose of this Contract. Therefore, any approval or acknowledgement by the Principal of the technical designs and documentation shall not release the Contractor from its duties, warranties and liabilities as to the exact delivery of the System Plant and performance of the Works. 5.2 The Contractor represents and warrants that at the time of execution hereof he, also through the Developer, holds Principal has been transferred a valid Building PermitAU, an accepted STMC STMD and Enel’s comunicazione Enel’scomunicazione di conclusione iter autorizzativo in relation to the System Plant and that it is unaware of any facts or circumstances, of any kind whatsoever that might prejudice the formation or validity of any SystemPlant’s Applicable Permits, or the transfer or registration thereof in favour of the Principal. The Area, object of the final building right agreement regarding the Land Use Rights, are Area is free from any encumbrances or burden burdens and there are no third parties (apart from the lawful owners) who can raise any claim any right in relation to such lands, nor prevent the Area and/or hinder the acquisition by the Principal of the Area free from any encumbrances or burdenburdens. 5.3 The Contractor also represents and warrants to the Principal, with reference to the “turn key” nature of this Contract, to be the only Party liable to the Principal concerning the Works’ complete construction in a world class manufacturing way, undertaking, thus, all liability towards the Principal with reference to all the activities whose performance is entrusted to sub-contractors, pursuant to this Contract. 5.4 The Contractor expresses his consentagrees, as of the date hereof, to the assignment and/or pledge in favour of the Financing Entity (or any third parties appointed by the latter) by the Principal of his receivables deriving from this Contract and shall provide his cooperation in the performance of all the formalities and shall provide any further consent, necessary or expedient, required as to the assignment and/or pledge's formation. 5.5 The Contractor guarantees to dedicate to the SystemPlant, at all times, the adequate number of workers and to timely and completely pay all wages, insurance fees and public charges, social securities, etc. for the workers on the sites. 5.6 There are no impediments, to the Contractor's knowledge knowledge, that could compromise in some way the obtaining of the authorizations for the construction of the grid infrastructure necessary to connect the System Plant to the grid.

Appears in 1 contract

Samples: Engineering Procurement & Construction Contract (Ellomay Capital Ltd.)