SCADA and Telemetry System. All communication, metering, telemetry, and associated generation operation equipment will be centralized into the Generating Facility’s SCADA. Seller shall configure the SCADA so that SCE may access it via the GMS from the GOC. Seller shall link the systems via an approved SCE communication network, utilizing existing industry standard network protocol, as approved by SCE. The connection will be bidirectional in nature and used by the Parties to exchange all data points to and from the GOC. Seller shall be responsible for the costs of installing, configuring, maintaining and operating the SCADA and internal site links for the Generating Facility. Seller shall be responsible for designing, furnishing, installing, operating, maintaining and testing a real time Telemetry System capable of interconnecting to the GMS, the CAISO-Approved Meter(s) and the Generating Facility’s control system with the CAISO’s Energy Communication Network. The Telemetry System shall be designed in accordance with the CAISO monitoring and communication requirements and must be capable of: (i) Reporting data from each CAISO-Approved Meter; (ii) Providing the status of key control points from the Generating Facility’s control system; (iii) Routing generating unit set points to the Generating Facility’s control system; and (iv) Communicating availability of the Generating Facility pursuant to Section 3.08(g). The Telemetry System must include a data processing gateway, internet connection, interconnecting cabling and all service agreements required for accessing the CAISO’s Energy Communications Network. The above mentioned connections and data transfer must be included in the systems engineering tasks as a part of the construction of the Generating Facility, and must be fully functional before Initial Synchronization.
Appears in 9 contracts
Samples: Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement, Renewable Power Purchase and Sale Agreement
SCADA and Telemetry System. All communication, metering, telemetry, and associated generation operation equipment will be centralized into the Generating Facility’s SCADA. Seller shall configure the SCADA so that SCE may access it via the GMS from the GOC. Seller shall link the systems via an approved SCE communication network, utilizing existing industry standard network protocol, as approved by SCE. The connection will be bidirectional in nature and used by the Parties to exchange all data points to and from the GOC. Seller shall be responsible for the costs of installing, configuring, maintaining and operating the SCADA and internal site links for the Generating Facility. Seller shall be responsible for designing, furnishing, installing, operating, maintaining and testing a real time Telemetry System capable of interconnecting to the GMS, the CAISO-CAISO Approved Meter(s) and the Generating Facility’s control system with the CAISO’s Energy Communication Network. The Telemetry System shall be designed in accordance with the CAISO monitoring and communication requirements and must be capable of:
(i) Reporting data from each CAISO-CAISO Approved Meter;
(ii) Providing the status of key control points from the Generating Facility’s control system;
(iii) Routing generating unit set points to the Generating Facility’s control system; and
(iv) Communicating availability of the Generating Facility pursuant to Section 3.08(g). The Telemetry System must include a data processing gateway, internet connection, interconnecting cabling and all service agreements required for accessing the CAISO’s Energy Communications Network. The above mentioned connections and data transfer must be included in the systems engineering tasks as a part of the construction of the Generating Facility, and must be fully functional before Initial SynchronizationCommercial Operation.
Appears in 2 contracts
Samples: Renewable Power Purchase Agreement, Renewable Power Purchase Agreement
SCADA and Telemetry System. All communication, metering, telemetry, and associated generation operation equipment will be centralized into the [Distributed Energy Resource Aggregation’s] {SCE Comment: For DERs} [Generating Facility’s ’s] {SCE: Comment: For non-DER Generating Facilities} SCADA. Seller shall configure the SCADA so that SCE may access it via the GMS from the GOC. Seller shall link the systems via an approved SCE communication network, utilizing existing industry standard network protocol, as approved by SCE. The connection will be bidirectional in nature and used by the Parties to exchange all data points to and from the GOC. Seller shall be responsible for the costs of installing, configuring, maintaining and operating the SCADA and internal site links for the Generating FacilityDistributed Energy Resource Aggregation. Seller shall be responsible for designing, furnishing, installing, operating, maintaining and testing a real time Telemetry System capable of interconnecting to the GMS, the CAISO-CAISO Approved Meter(s) and the Generating FacilityDistributed Energy Resource Aggregation’s control system with the CAISO’s Energy Communication Network. Seller shall be responsible for designing, furnishing, installing, operating, maintaining and testing a real time DER Telemetry System capable of allowing the Distributed Energy Resource Aggregation’s control system to interconnect to and control each Distributed Energy Resource, permitting each Distributed Energy Resource to comply with any CAISO dispatch or curtailment pursuant to Section 3.12(g). The Telemetry System shall be designed in accordance with the CAISO monitoring and communication requirements and must be capable of:
(i) Reporting data from each CAISO-CAISO Approved Meter;
(ii) Providing the status of key control points from the Generating FacilityDistributed Energy Resource Aggregation’s control system;system;
(iii) Routing generating unit set points to the Generating FacilityDistributed Energy Resource Aggregation’s control system; and
(iv) Communicating availability of the Generating Facility pursuant to Section 3.08(g). The Telemetry System must include a data processing gateway, internet connection, interconnecting cabling and all service agreements required for accessing the CAISO’s Energy Communications Network. The above mentioned connections and data transfer must be included in the systems engineering tasks as a part of the construction of the Generating Facility, and must be fully functional before Initial SynchronizationCommercial Operation. The DER Telemetry System shall be designed in accordance with the CAISO monitoring and communication requirements and must be capable of complying with the requirements set forth in CAISO Tariff applicable to a Distributed Energy Resource, a Distributed Energy Resource Provider, a Distributed Energy Resource Aggregation, and any requirement applicable to a Scheduling Coordinator for a Distributed Energy Resource Aggregation.
Appears in 1 contract
Samples: Renewable Power Purchase Agreement
SCADA and Telemetry System. All communication, metering, telemetry, and associated generation operation equipment will be centralized into the Generating Facility’s 's SCADA. Seller shall configure the SCADA so that SCE may access it via the GMS from the GOC. Seller shall link the systems via an approved SCE communication network, utilizing existing industry standard network protocol, as approved by SCE. The connection will be bidirectional in nature and used by the Parties to exchange all data points to and from the GOC. Seller shall be responsible for the costs of installing, configuring, maintaining and operating the SCADA and internal site links for the Generating Facility. Seller shall be responsible for designing, furnishing, installing, operating, maintaining and testing a real time Telemetry System capable of interconnecting to the GMS, the CAISO-Approved Meter(s) and the Generating Facility’s 's control system with the CAISO’s 's Energy Communication Network. The Telemetry System shall be designed in accordance with the CAISO monitoring and communication requirements and must be capable of:
(i) Reporting data from each CAISO-Approved Meter;
(ii) Providing the status of key control points from the Generating Facility’s 's control system;
(iii) Routing generating unit set points to the Generating Facility’s 's control system; and
(iv) Communicating availability of the Generating Facility pursuant to Section 3.08(g). The Telemetry System must include a data processing gateway, internet connection, interconnecting cabling and all service agreements required for accessing the CAISO’s 's Energy Communications Network. The above mentioned connections and data transfer must be included in the systems engineering tasks as a part of the construction of the Generating Facility, and must be fully functional before Initial Synchronization.
Appears in 1 contract
SCADA and Telemetry System. All communication, metering, telemetry, and associated generation operation equipment will be centralized into the [Distributed Energy Resource Aggregation’s] {SCE Comment: For DERs} [Generating Facility’s ’s] {SCE: Comment: For non-DER Generating Facilities} SCADA. Seller shall configure the SCADA so that SCE may access it via the GMS from the GOC. Seller shall link the systems via an approved SCE communication network, utilizing existing industry standard network protocol, as approved by SCE. The connection will be bidirectional in nature and used by the Parties to exchange all data points to and from the GOC. Seller shall be responsible for the costs of installing, configuring, maintaining and operating the SCADA and internal site links for the Generating FacilityDistributed Energy Resource Aggregation. Seller shall be responsible for designing, furnishing, installing, operating, maintaining and testing a real time Telemetry System capable of interconnecting to the GMS, the CAISO-CAISO Approved Meter(s) and the Generating FacilityDistributed Energy Resource Aggregation’s control system with the CAISO’s Energy Communication Network. Seller shall be responsible for designing, furnishing, installing, operating, maintaining and testing a real time DER Telemetry System capable of allowing the Distributed Energy Resource Aggregation’s control system to interconnect to and control each Distributed Energy Resource, permitting each Distributed Energy Resource to comply with any CAISO dispatch or curtailment pursuant to Section 3.12(g). The Telemetry System shall be designed in accordance with the CAISO monitoring and communication requirements and must be capable of:
(i) Reporting data from each CAISO-CAISO Approved Meter;
(ii) Providing the status of key control points from the Generating FacilityDistributed Energy Resource Aggregation’s control system;
(iii) Routing generating unit set points to the Generating FacilityDistributed Energy Resource Aggregation’s control system; and
(iv) Communicating availability of the Generating Facility pursuant to Section 3.08(g). The Telemetry System must include a data processing gateway, internet connection, interconnecting cabling and all service agreements required for accessing the CAISO’s Energy Communications Network. The above mentioned connections and data transfer must be included in the systems engineering tasks as a part of the construction of the Generating Facility, and must be fully functional before Initial SynchronizationCommercial Operation. The DER Telemetry System shall be designed in accordance with the CAISO monitoring and communication requirements and must be capable of complying with the requirements set forth in CAISO Tariff applicable to a Distributed Energy Resource, a Distributed Energy Resource Provider, a Distributed Energy Resource Aggregation, and any requirement applicable to a Scheduling Coordinator for a Distributed Energy Resource Aggregation.
Appears in 1 contract
Samples: Renewable Power Purchase Agreement