Schedule Corrections. 6.5.4.1. Each month, in accordance with the Specification, the Contractor shall address corrections to the schedule that were identified by the Construction Manager during the review of the last Monthly Schedule Update. If the submittal is rejected, the Contractor must individually respond to every correction and review comment received from both the Construction Manager and/or Architect via the schedule narrative of the resubmittal. If the submittal is conditionally accepted with noted exceptions, the Contractor must individually respond to every correction and review comment via the schedule narrative of the next monthly update. Failure of the Contractor to specifically respond to each of the Construction Manager’s previous review comments may result in rejection of the following submittal and a monthly payment portion withheld.