Schedule Meetings and Records. After execution of the Contract and prior to commencement of the Work, Owner shall schedule a meeting with Contractor for the purpose of outlining and clarifying the proposed Work, security and use of the Site, potentially difficult aspects of the Work of which Owner is actually aware and responding to questions of those attending. 7.5.1 Contractor shall schedule and conduct pre-construction and construction progress meetings at the Site on a regular basis (at least weekly) at which Owner, Architect, Interior Designer, Contractor and Subcontractors may jointly discuss such matters as Work procedures, progress, scheduling and coordination, and Owner’s Lender may attend. Contractor shall be responsible for securing attendance of its Subcontractors, Vendors, suppliers and other personnel as are required at such meetings. Contractor shall keep and distribute timely in advance of the next meeting minutes of such meetings, including a list of the action items, responsible parties and dates necessary to complete actions to enable the Contractor to maintain the progress of the Work in accordance with the Project Schedule. 7.5.2 Contractor shall regularly monitor and provide to Owner and Owner’s Lenders written reports on a monthly basis describing the status of the actual progress of the Work in relation to the Project Schedule, in accordance with Article 11 below. 7.5.3 For purposes of Schedule Updates and requested changes in the Contract Time, Contractor shall maintain daily logs which shall be available for Owner’s and Owner’s Lenders review at any time during normal working hours, and which shall record the progress of the Work. 7.5.4 Contractor shall also monthly provide to Owner and Owner’s Lenders, on the first day of each month, an Anticipated Cost Report prepared by Contractor and containing detailed information on pending Change Orders, contracts awarded and to be awarded, and similar budget related items.
Appears in 2 contracts
Samples: Guaranteed Maximum Price Construction Services Agreement (Pinnacle Entertainment Inc), Guaranteed Maximum Price Construction Services Agreement (Pinnacle Entertainment Inc)
Schedule Meetings and Records. After execution of the Contract and prior to commencement of the Work, Owner shall schedule a meeting one or more meetings with Contractor for the purpose of outlining and clarifying the proposed Work, security and use of the Site, potentially difficult aspects of the Work of which Owner is actually aware and responding to questions of those attending.
7.5.1 Contractor shall schedule and conduct pre-construction and construction progress meetings at the Site on a regular basis (at least weekly) at which Owner, Architect, Interior Designer/Engineer, Contractor and Subcontractors may jointly discuss such matters as Work procedures, progress, scheduling and coordination. Owner’s Lenders, Owner’s Consultants and Owner’s Lender Contractors may attendattend such meetings. Contractor shall be responsible for securing attendance of its Subcontractors, Vendors, suppliers and other personnel as are required at such meetings. Contractor shall keep and distribute timely in advance of the next meeting minutes of such meetings, including a list of the action items, responsible parties and dates necessary to complete actions to enable the Contractor to maintain the progress of the Work in accordance with the Project Schedule.
7.5.2 Contractor shall regularly monitor and provide to Owner and Owner’s Lenders written reports on a monthly basis describing the status of the actual progress of the Work in relation to the Project Schedule, in accordance with Article 11 below.
7.5.3 For purposes of Schedule Updates and requested changes in the Contract Time, Contractor shall maintain daily logs which shall be available for Owner’s and Owner’s Lenders review at any time during normal working hours, and which shall record the progress of the Work.
7.5.4 Contractor shall also provide monthly provide to Owner and Owner’s Lenders, on the first day of each month, an “Anticipated Cost Report Report” prepared by Contractor in substantial conformance with Owner’s standards and containing detailed information on pending Change Orders, contracts awarded and to be awarded, and similar budget related items.
Appears in 1 contract
Schedule Meetings and Records. After execution of the Contract and prior to commencement of the Work, Owner shall schedule a meeting with Contractor for the purpose of outlining and clarifying the proposed Work, security and use of the Site, potentially difficult aspects of the Work of which Owner is actually aware and responding to questions of those attending.
7.5.1 Contractor shall schedule and conduct pre-construction and construction progress meetings at the Site on a regular basis (at least weekly) at which Owner, Architect, Interior Designer, Contractor and Subcontractors may jointly discuss such matters as Work procedures, progress, scheduling and coordination, and Owner’s 's Lender may attend. Contractor shall be responsible for securing attendance of its Subcontractors, Vendors, suppliers and other personnel as are required at such meetings. Contractor shall keep and distribute timely in advance of the next meeting minutes of such meetings, including a list of the action items, responsible parties and dates necessary to complete actions to enable the Contractor to maintain the progress of the Work in accordance with the Project Schedule.
7.5.2 Contractor shall regularly monitor and provide to Owner and Owner’s 's Lenders written reports on a monthly basis describing the status of the actual progress of the Work in relation to the Project Schedule, in accordance with Article 11 below.
7.5.3 For purposes of Schedule Updates and requested changes in the Contract Time, Contractor shall maintain daily logs which shall be available for Owner’s 's and Owner’s 's Lenders review at any time during normal working hours, and which shall record the progress of the Work.
7.5.4 Contractor shall also monthly provide to Owner and Owner’s 's Lenders, on the first day of each month, an Anticipated Cost Report prepared by Contractor and containing detailed information on pending Change Orders, contracts awarded and to be awarded, and similar budget related items.
Appears in 1 contract
Samples: Guaranteed Maximum Price Construction Services Agreement (Wynn Resorts LTD)
Schedule Meetings and Records. After execution of the Contract Agreement and prior to commencement of the Expansion Project Work, Owner shall schedule a meeting one or more meetings with Contractor for the purpose of outlining and clarifying the proposed Expansion Project Work, security and use of the Site, potentially difficult aspects of the Work of which Owner is actually aware aware, interface and coordination issues between the Original Project and the Expansion Project and responding to questions of those attending.
7.5.1 Contractor shall schedule and conduct pre-construction and construction progress meetings at the Site on a regular basis (at least weekly) at which Owner, Architect, Interior Designer/Engineer, Contractor and Subcontractors may jointly discuss such matters as Work procedures, progress, scheduling and coordination. Owner’s Lenders, Owner’s Consultants and Owner’s Lender Contractors may attendattend such meetings. Contractor shall be responsible for securing attendance of its Subcontractors, Vendors, suppliers and other personnel as are required at such meetings. Contractor shall keep and distribute timely in advance of the next meeting minutes of such meetings, including a list of the action items, responsible parties and dates necessary to complete actions to enable the Contractor to maintain the progress of the Work in accordance with the Original Project Schedule and the Expansion Project Schedule.
7.5.2 Contractor shall regularly monitor and provide to Owner and Owner’s Lenders written reports on a monthly basis describing the status of the actual progress of the Work in relation to the Original Project Schedule and the Expansion Project Schedule, in accordance with Article 11 below.
7.5.3 For purposes of Schedule Updates and requested changes in the Contract TimeTimes, Contractor shall maintain daily logs which shall be available for Owner’s and Owner’s Lenders review at any time during normal working hours, and which shall record the progress of the Work.
7.5.4 Contractor shall also provide monthly provide to Owner and Owner’s Lenders, on or before the first tenth (10th) day of each month, an “Anticipated Cost Report Report” prepared by Contractor in substantial conformance with Owner’s standards and containing detailed information on pending Change Orders, contracts awarded and to be awarded, and similar budget related items.
Appears in 1 contract