Schedule Milestones Sample Clauses

Schedule Milestones. The Contractor shall, in conjunction with Princeton University, create and thereafter maintain all schedule activities, including a group of milestone activities that shall be included in and tied to the Project Schedule (the “Schedule Milestones”). Contractor shall prepare its schedule to include, at a minimum, the following Schedule Milestones: Contractual Start (defined by the Effective Date of the Contract), Substantial Completion, Certificate of Occupancy, Princeton University’s “Move-In” process, Early Completion date (if one is proposed). Schedule Milestones shall also specify start date, end date, and duration for Submittals (as defined in Clause F1) and main building system elements of the Work, grouped by building area, and should include, in addition to the previous listed Schedule Milestones herein, as a minimum: Submittals, Site Mobilization, Demolition, Foundation/Excavation, Substructure, Superstructure (frame/bearing walls), Building Enclosure to water-tight condition, MEP Systems (including temporary systems, permanent power, and rough inspections), Conveying Devices, Interior Construction, Finishes, Final Inspections, Punch List, Move-In, Occupancy, and Contract Close Out.
AutoNDA by SimpleDocs
Schedule Milestones. The Contractor shall, in conjunction with Princeton University, create and track a group of milestone activities that shall be tied to the Project Schedule (the “Schedule Milestones”). Contractor shall prepare its schedule to include the following: Contractual Start (defined by contract execution), Substantial Completion, Certificate of Occupancy, Princeton University’s “Move-In” process, Early Completion date (if one is proposed). Schedule Milestones shall also specify start date, end date, and duration for Submittals (as defined in Clause F1) and main building system elements of the Work, grouped by building area and should include, as a minimum: Submittals, Site Mobilization, Demolition, Foundation/Excavation, Substructure, Superstructure (frame/bearing walls), Building Enclosure to water-tight condition, MEP Systems (including temporary systems, permanent power, and rough inspections), Conveying Devices, Interior Construction, Finishes, Final Inspections, Punch List, Move-In, Occupancy, and Contract Close Out.
Schedule Milestones. Key dates and milestones are described in Section xxx of the Statement of Work.
Schedule Milestones. The Contractor shall, in conjunction with Princeton University, create and track a group of milestone activities that shall be tied to the Project Schedule. Schedule Milestones (“Schedule Milestones”) shall include “Contractual Start” (defined by contract execution), “Substantial Completion,” “Certificate of Occupancy”, followed by Princeton University’s “Move-In” process, and an early completion date if one is proposed. Schedule Milestones shall also specify start date, end date, and duration for main building system elements of the Work, should be grouped by building area and should include, as a minimum, “Site Mobilization”, “Demolition”, “Foundation/Excavation”, “Substructure”, “Superstructure” (frame/bearing walls), “Building Enclosure” (building skin, temporary enclosure, windows, doors, roof), “MEP Systems” (temporary systems and rough inspections), “Conveying Devices”, “Interior Construction”, “Finishes”, “Final Inspections”, “Punch List”, “Move-In”, “Occupancy”, and “Close Out”.
Schedule Milestones. The key Schedule Milestones as proposed by the Contractor and agreed upon by the Employer’s Representative will be adopted for periodic review of the progress of various components of the overall Project. These milestones will define the stages when the decisions regarding any delay in the implementation will be assessed with a view towards the application of the provisions of the Conditions of Contract. The successful Bidder/Contractor will be encouraged to complete and commission the system DMAwise, to enable planning for partial commissioning of the project in sections, by availing the water available in the nearest Service Reservoir or Transmission Main.
Schedule Milestones. Proponent to provide additional proposed schedule milestones, in addition to any specified in the Proposed Form of Agreement, which incorporates the schedule milestones for key components of the Services.
Schedule Milestones. Order letter signed October 18, 1999 Agreement Signing November 18, 1999 Begin launch of zap.xxx xxxperties November 18, 1999 100 Xxxxxxxx Xxxxxx - Xxxxx 000 - Xxxxxxxxx, Xxx Xxxx 00000 - 016/242-0000 - XAX 716/242/8677 - www.xxx.xxx 3 [Zap.xxx Xxxterhead] Equipment Available and on-line TBD as evidenced by the on-line functionality of all the equipment defined in the Agreement
AutoNDA by SimpleDocs
Schedule Milestones. Mobilize to Site - 10/31/16 • Compressors Set - 3/17/17 • PCR & Switchgear Buildings Set - 4/3/17 • Large Bore Piping (36” and above) Fabrication and Installation Welding complete - 7/22/17 • Mechanical Completion - 10/1/17 • Final Completion - 12/1/17 ATTACHMENT F INSURANCE REQUIREMENTS
Schedule Milestones. Key dates and milestones are described in Section xxx of the Statement of Work. The Start Date shall be the date this contract is fully executed and received by the Contractor.
Schedule Milestones. Key dates and milestones are described in Section 1.4 of the Statement of Work. REMAINDER OF THIS PAGE INTENTIONALLY LEFT BLANK
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!