Schedule Updates. Contractor shall update the schedule each month to address actual start dates and durations, the percent complete on activities, actual completion dates, estimated remaining duration for the Work in progress, estimated start dates for Work scheduled to start at future times and changes in duration of Work items
Appears in 8 contracts
Samples: Construction Services Agreement, Construction Services Agreement, Pre Construction Services Agreement
Schedule Updates. Contractor shall update the schedule (including a narrative) each month to address actual start dates and durations, the percent complete on activities, actual completion dates, estimated remaining duration for the Work in progress, areas of progress, logic and durations, overall assessment of schedule achievement, estimated start dates for Work scheduled to start at future times and changes in duration of Work items.
Appears in 8 contracts
Samples: Construction Services Agreement, Construction Services Agreement, Construction Services Agreement
Schedule Updates. Contractor shall update the schedule each month to address actual start dates and durations, the percent complete on activities, actual completion dates, estimated remaining duration for the Work in progress, estimated start dates for Work scheduled to start at future times and changes in duration of Work items.
Appears in 3 contracts
Samples: Construction Services Agreement, Construction Services Agreement, Construction Services Agreement
Schedule Updates. Contractor shall update the schedule (including a narrative) each month to address actual start dates and durations, the percent complete on activities, actual completion dates, estimated remaining duration for the Work in progress, areas of progress, logic and durations, overall assessment of schedule achievement, estimated start dates for Work scheduled to start at future times and changes in duration of Work itemsitems.β
Appears in 1 contract
Samples: Construction Services Agreement
Schedule Updates. Contractor shall update the schedule (including a narrative) each month to address actual start dates and durations, the percent complete on activities, actual completion dates, estimated remaining duration for the Work in progress, areas of progress, logic and durations, overall assessment of achieving the approved schedule, estimated start dates for Work scheduled to start at future times and changes in duration of Work items
Appears in 1 contract
Samples: Construction Services Agreement
Schedule Updates. Contractor shall update the schedule each month to address actual start dates and durations, the percent complete on activities, actual completion dates, estimated remaining duration for the Work in progress, estimated start dates for Work scheduled to start at future times and changes in duration of Work items. The Schedule shall be maintained throughout the Work for the Project and is both a prerequisite to the issuance of a Pay Application and Contract Closeout.
Appears in 1 contract