Scheduling and Despatch Review. 47.2.1 The Grid Operator shall (after consultation with the Executive Committee) decide upon the appointment from time to time of such firm of accountants of internationally recognised standing as the Executive Committee shall approve (such approval not to be unreasonably withheld or delayed) to carry out reviews ("Scheduling and Despatch Reviews") of the Scheduling and Despatch processes under the Grid Code, such reviews to be carried out, until the first anniversary of the Effective Date, at such time or times as shall be agreed between the Grid Operator and the Executive Committee and, thereafter, annually. The objective and scope of each such review is set out in Schedule 19. 47.2.2 The Grid Operator shall have the right at any time and from time to time (after consultation with the Executive Committee) to decide upon the removal from office of the firm of accountants so appointed by it with the consent of the Executive Committee (such consent not to be unreasonably withheld or delayed). 47.2.3 The auditor carrying out the Scheduling and Despatch Review shall report to the Grid Operator.
Appears in 3 contracts
Samples: Settlement Agreement (Southern Investments Uk PLC), Pooling and Settlement Agreement (Calenergy Co Inc), Pooling and Settlement Agreement (Txu Eastern Holdongs LTD)
Scheduling and Despatch Review. 47.2.1 The the Grid Operator shall (after consultation with the Executive Committee) decide upon the appointment from time to time of such firm of accountants accounts of internationally recognised standing as the Executive Committee shall approve (such approval not to be unreasonably withheld or delayed) to carry out reviews ("Scheduling and Despatch Reviews") " of the Scheduling and Despatch processes under the Grid 148 Code, such reviews to be carried out, until the first anniversary of the Effective Dateeffective date, at such time or times as shall be agreed between the Grid Operator and the Executive Committee and, thereafter, annually. The objective and scope of each such review is set out in Schedule 19.
47.2.2 The Grid Operator shall have the right at any time and from time to time (after consultation with the Executive Committee) to decide upon the removal from office of the firm of accountants so appointed by it with the consent of the Executive Committee (such consent not to be unreasonably withheld or delayed).
47.2.3 The auditor carrying out the Scheduling and Despatch Review shall report to the Grid Operator.
Appears in 1 contract
Samples: Pooling and Settlement Agreement (Yorkshire Power Group LTD)