Scheduling and Despatch Review. 47.2.1 The Grid Operator shall (after consultation with the Executive Committee) decide upon the appointment from time to time of such firm of accountants of internationally recognised standing as the Executive Committee shall approve (such approval not to be unreasonably withheld or delayed) to carry out reviews ("Scheduling and Despatch Reviews") of the Scheduling and Despatch processes under the Grid Code, such reviews to be carried out, until the first anniversary of the Effective Date, at such time or times as shall be agreed between the Grid Operator and the Executive Committee and, thereafter, annually. The objective and scope of each such review is set out in Schedule 19.
Appears in 3 contracts
Samples: Supplemental Agreement (Southern Investments Uk PLC), Supplemental Agreement (Txu Eastern Holdongs LTD), Calenergy Co Inc
Scheduling and Despatch Review. 47.2.1 The 47.2.1The Grid Operator shall (after consultation with the Executive Committee) decide upon the appointment from time to time of such firm of accountants of internationally recognised standing as the Executive Committee shall approve (such approval not to be unreasonably withheld or delayed) to carry out reviews ("Scheduling UScheduling and Despatch Reviews") of the Scheduling and Despatch processes under the Grid Code, such reviews to be carried out, until the first anniversary of the Effective Date, at such time or times as shall be agreed between the Grid Operator and the Executive Committee and, thereafter, annually. The objective and scope of each such review is set out in Schedule 19.
Appears in 1 contract
Scheduling and Despatch Review. 47.2.1 The the Grid Operator shall (after consultation with the Executive Committee) decide upon the appointment from time to time of such firm of accountants accounts of internationally recognised standing as the Executive Committee shall approve (such approval not to be unreasonably withheld or delayed) to carry out reviews ("Scheduling and Despatch Reviews") " of the Scheduling and Despatch processes under the Grid 148 Code, such reviews to be carried out, until the first anniversary of the Effective Dateeffective date, at such time or times as shall be agreed between the Grid Operator and the Executive Committee and, thereafter, annually. The objective and scope of each such review is set out in Schedule 19.
Appears in 1 contract