Common use of Scheduling Services Clause in Contracts

Scheduling Services. At the end of the Schematic Design Phase(s) and prior to the start of the Design Development Phase, the CMR shall submit to the DAS PM, A/E and Construction Administrator a detailed written report outlining their recommendations on the Project’s Construction Schedule. It shall include a verification of the overall construction duration and conceptual Construction Schedule submitted in a bar chart format.

Appears in 1 contract

Samples: Standard Form of Agreement Between Owner and Construction Manager at Risk (Cmr) for Guaranteed Maximum Price (Gmp)

Scheduling Services. At the end of the Schematic Design Phase(s) and prior to the start of the Design Development Phase, the CMR shall submit to the DAS PM, A/E and Construction Administrator a detailed written report outlining their recommendations on the Project’s 's Construction Schedule. It shall include a verification of the overall construction duration and conceptual Construction Schedule submitted in a bar chart format.

Appears in 1 contract

Samples: Standard Form of Agreement Between Owner and Construction Manager at Risk (Cmr) for Guaranteed Maximum Price (Gmp)

Scheduling Services. At the end of the Schematic Pre-Design Phase(s) Phase and prior to the start of the Schematic Design Development Phase, the CMR shall submit to the DAS PM, A/E and Construction Administrator a detailed written report outlining their recommendations on the Project’s 's Construction ScheduleSchedule for the three conceptual alternative designs. It The report shall include a verification of the overall construction duration and conceptual Construction Schedule submitted in a bar chart formatformat for each of the three conceptual alternative designs.

Appears in 1 contract

Samples: Standard Form of Agreement Between Owner and Construction Manager at Risk (Cmr) for Guaranteed Maximum Price (Gmp)

Scheduling Services. At the end of the Schematic Pre-Design Phase(s) Phase and prior to the start of the Schematic Design Development Phase, the CMR shall submit to the DAS PM, A/E and Construction Administrator a detailed written report outlining their recommendations on the Project’s Construction ScheduleSchedule for the three conceptual alternative designs. It The report shall include a verification of the overall construction duration and conceptual Construction Schedule submitted in a bar chart formatformat for each of the three conceptual alternative designs.

Appears in 1 contract

Samples: Standard Form of Agreement Between Owner and Construction Manager at Risk (Cmr) for Guaranteed Maximum Price (Gmp)