Scope of Studies. In conducting the enhancement and expansion studies, the Office of the Interconnection shall not limit its analyses to bright line tests to identify and evaluate potential Transmission System limitations, violations of planning criteria, or transmission needs. In addition to the bright line tests, the Office of the Interconnection shall employ sensitivity studies, modeling assumption variations, and scenario analyses, and shall also consider Public Policy Objectives in the studies and analyses, so as to mitigate the possibility that bright line metrics may inappropriately include or exclude transmission projects from the transmission plan. Sensitivity studies, modeling assumption variations, and scenario analyses shall take account of potential changes in expected future system conditions, including, but not limited to, load levels, transfer levels, fuel costs, the level and type of generation, generation patterns (including, but not limited to, the effects of assumptions regarding generation that is at risk for retirement and new generation to satisfy Public Policy Objectives), demand response, and uncertainties arising from estimated times to construct transmission upgrades. The Office of the Interconnection shall use the sensitivity studies, modeling assumption variations and scenario analyses in evaluating and choosing among alternative solutions to reliability, market efficiency and operational performance needs. The Office of the Interconnection shall provide the results of its studies and analyses to the Transmission Expansion Advisory Committee to consider the impact that sensitivities, assumptions, and scenarios may have on Transmission System needs and the need for transmission enhancements or expansions. Enhancement and expansion studies shall be completed by the Office of the Interconnection in collaboration with the affected Transmission Owners, as required. In general, enhancement and expansion studies shall include: (a) An identification of existing and projected limitations on the Transmission System’s physical, economic and/or operational capability or performance, with accompanying simulations to identify the costs of controlling those limitations. Potential enhancements and expansions will be proposed to mitigate limitations controlled by non-economic means. (b) Evaluation and analysis of potential enhancements and expansions, including alternatives thereto, needed to mitigate such limitations. (c) Identification, evaluation and analysis of potential transmission expansions and enhancements, demand response programs, and other alternative technologies as appropriate to maintain system reliability. (d) Identification, evaluation and analysis of potential enhancements and expansions for the purposes of supporting competition, market efficiency, operational performance, and Public Policy Requirements in the PJM Region. (e) Identification, evaluation and analysis of upgrades to support Incremental Auction Revenue Rights requested pursuant to the Operating Agreement, Schedule 1, section 7.8. (f) Identification, evaluation and analysis of upgrades to support all transmission customers, including native load and network service customers. (g) Engineering studies needed to determine the effectiveness and compliance of recommended enhancements and expansions, with the following PJM criteria: system reliability, operational performance, and market efficiency. (h) Identification, evaluation and analysis of potential enhancements and expansions designed to ensure that the Transmission System’s capability can support the simultaneous feasibility of all stage 1A Auction Revenue Rights allocated pursuant to the Operating Agreement, Schedule 1, section 7.4.2(b). Enhancements and expansions related to stage 1A Auction Revenue Rights identified pursuant to this Section shall be recommended for inclusion in the Regional Transmission Expansion Plan together with a recommended in-service date based on the results of the ten (10) year stage 1A simultaneous feasibility analysis. Any such recommended enhancement or expansion under this Operating Agreement, Schedule 6, section 1.5.3(h) shall include, but shall not be limited to, the reason for the upgrade, the cost of the upgrade, the cost allocation identified pursuant to the Operating Agreement, Schedule 6, section 1.5.6(m) and an analysis of the benefits of the enhancement or expansion, provided that any such upgrades will not be subject to a market efficiency cost/benefit analysis. (i) Identification, evaluation and analysis of potential enhancements and expansions that mitigate the violation of the Substation Contingency Resilience Criteria or avoid Resiliency Failure.
Appears in 2 contracts
Samples: Operating Agreement Definitions Revisions, Operating Agreement
Scope of Studies. In conducting the enhancement and expansion studies, the Office of the Interconnection shall not limit its analyses to bright line tests to identify and evaluate potential Transmission System limitations, violations of planning criteria, or transmission needs. In addition to the bright line tests, the Office of the Interconnection shall employ sensitivity studies, modeling assumption variations, and scenario analyses, and shall also consider Public Policy Objectives in the studies and analyses, so as to mitigate the possibility that bright line metrics may inappropriately include or exclude transmission projects from the transmission plan. Sensitivity studies, modeling assumption variations, and scenario analyses shall take account of potential changes in expected future system conditions, including, but not limited to, load levels, transfer levels, fuel costs, the level and type of generation, generation patterns (including, but not limited to, the effects of assumptions regarding generation that is at risk for retirement and new generation to satisfy Public Policy Objectives), demand response, and uncertainties arising from estimated times to construct transmission upgrades. The Office of the Interconnection shall use the sensitivity studies, modeling assumption variations and scenario analyses in evaluating and choosing among alternative solutions to reliability, market efficiency and operational performance needs. The Office of the Interconnection shall provide the results of its studies and analyses to the Transmission Expansion Advisory Committee to consider the impact that sensitivities, assumptions, and scenarios may have on Transmission System needs and the need for transmission enhancements or expansions. Enhancement and expansion studies shall be completed by the Office of the Interconnection in collaboration with the affected Transmission Owners, as required. In general, enhancement and expansion studies shall include:
(a) An identification of existing and projected limitations on the Transmission System’s physical, economic and/or operational capability or performance, with accompanying simulations to identify the costs of controlling those limitations. Potential enhancements and expansions will be proposed to mitigate limitations controlled by non-economic means.
(b) Evaluation and analysis of potential enhancements and expansions, including alternatives thereto, needed to mitigate such limitations.
(c) Identification, evaluation and analysis of potential transmission expansions and enhancements, demand response programs, and other alternative technologies as appropriate to maintain system reliability.
(d) Identification, evaluation and analysis of potential enhancements and expansions for the purposes of supporting competition, market efficiency, operational performance, and Public Policy Requirements in the PJM Region.
(e) Identification, evaluation and analysis of upgrades to support Incremental Auction Revenue Rights requested pursuant to the Operating Section 7.8 of Schedule 1 of this Agreement, Schedule 1, section 7.8.
(f) Identification, evaluation and analysis of upgrades to support all transmission customers, including native load and network service customers.
(g) Engineering studies needed to determine the effectiveness and compliance of recommended enhancements and expansions, with the following PJM criteria: system reliability, operational performance, and market efficiency.
(h) Identification, evaluation and analysis of potential enhancements and expansions designed to ensure that the Transmission System’s capability can support the simultaneous feasibility of all stage 1A Auction Revenue Rights allocated pursuant to the Operating Section 7.4.2(b) of Schedule 1 of this Agreement, Schedule 1, section 7.4.2(b). Enhancements and expansions related to stage 1A Auction Revenue Rights identified pursuant to this Section shall be recommended for inclusion in the Regional Transmission Expansion Plan together with a recommended in-service date based on the results of the ten (10) year stage 1A simultaneous feasibility analysis. Any such recommended enhancement or expansion under this Operating Agreement, Schedule 6, section Section 1.5.3(h) shall include, but shall not be limited to, the reason for the upgrade, the cost of the upgrade, the cost allocation identified pursuant to the Operating Agreement, Section 1.5.6(l) of Schedule 6, section 1.5.6(m) 6 of this Agreement and an analysis of the benefits of the enhancement or expansion, provided that any such upgrades will not be subject to a market efficiency cost/benefit analysis.
(i) Identification, evaluation and analysis of potential enhancements and expansions that mitigate the violation of the Substation Contingency Resilience Criteria or avoid Resiliency Failure.
Appears in 1 contract
Samples: Operating Agreement