Section closure. 17.7.1 The Concessionaire shall not close any section of the Bus Terminal for undertaking maintenance or repair works except with the prior written approval of the Independent Engineer. Such approval shall be sought by the Concessionaire through a written request to be made to the Independent Engineer, and a copy thereof furnished to the Authority, at least 7 (seven) days before the proposed closure of such section and shall be accompanied by particulars thereof. Within 3 (three) days of receiving such request, the Independent Engineer shall grant permission with such modifications as it may deem necessary and a copy of such permission shall be sent to the Authority. 17.7.2 Upon receiving the permission pursuant to Clause 17.7.1, the Concessionaire shall be entitled to close the designated section for the period specified therein, and in the event of any delay in re-opening such section, the Concessionaire shall pay Damages to the Authority calculated at the rate of 0.1% (zero point one per cent) of the Performance Guarantee for that section, for each day of delay until the section has been re-opened for traffic.
Appears in 32 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement
Section closure. 17.7.1 The Concessionaire shall not close any section of the Bus Terminal for undertaking maintenance or repair works except with the prior written approval of the Independent Engineer. Such approval shall be sought by the Concessionaire through a written request to be made to the Independent Engineer, and a copy thereof furnished to the Authority, at least 7 (seven) days before the proposed closure of such section and shall be accompanied by particulars thereof. Within 3 (three) days of receiving such request, the Independent Engineer shall grant permission with such modifications as it may deem necessary and a copy of such permission shall be sent to the Authority.. xxx.xxxxxx.xxx Downloaded
17.7.2 Upon receiving the permission pursuant to Clause 17.7.1, the Concessionaire shall be entitled to close the designated section for the period specified therein, and in the event of any delay in re-opening such section, the Concessionaire shall pay Damages to the Authority calculated at the rate of 0.1% (zero point one per cent) of the Performance Guarantee for that section, for each day of delay until the section has been re-opened for traffic.
Appears in 10 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement
Section closure. Downloaded from
17.7.1 The Concessionaire shall not close any section of the Bus Terminal for undertaking maintenance or repair works except with the prior written approval of the Independent Engineer. Such approval shall be sought by the Concessionaire through a written request to be made to the Independent Engineer, and a copy thereof furnished to the Authority, at least 7 (seven) days before the proposed closure of such section and shall be accompanied by particulars thereof. Within 3 (three) days of receiving such request, the Independent Engineer shall grant permission with such modifications as it may deem necessary and a copy of such permission shall be sent to the Authority.. xxx.xxxxxx.xxx
17.7.2 Upon receiving the permission pursuant to Clause 17.7.1, the Concessionaire shall be entitled to close the designated section for the period specified therein, and in the event of any delay in re-opening such section, the Concessionaire shall pay Damages to the Authority calculated at the rate of 0.1% (zero point one per cent) of the Performance Guarantee for that section, for each day of delay until the section has been re-opened for traffic.
Appears in 2 contracts
Samples: Concession Agreement, Concession Agreement