Common use of Special Damages Clause in Contracts

Special Damages. A. In addition to the amount provided for in liquidated damages, the Contractor shall reimburse NBU (1) for any fines or penalties imposed on NBU as a direct result of the Contractor’s failure to attain Substantial Completion according to the Contract Times, and (2) for the actual costs reasonably incurred by NBU for engineering, construction observation, inspection, and administrative services needed after the time specified in Paragraph 4.02 for Substantial Completion (as duly adjusted pursuant to the Contract), until the Work is substantially complete. B. After Contractor achieves Substantial Completion, if the Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times, the Contractor shall reimburse NBU for the actual costs reasonably incurred by NBU for engineering, construction observation, inspection, and administrative services needed after the time specified in Paragraph 4.02 for Work to be completed and ready for final payment (as duly adjusted pursuant to the Contract), until the Work is completed and ready for final payment.

Appears in 6 contracts

Samples: Construction Contract, Construction Contract, Construction Contract

AutoNDA by SimpleDocs

Special Damages. A. In addition to the amount provided damages for delay addressed in liquidated damagesSection 4.03, the Contractor shall reimburse NBU for (1i) for any fines or penalties imposed on NBU as a direct result of the Contractor’s failure to attain Substantial Completion according to the Contract Times, Times and (2ii) for the actual costs reasonably incurred by NBU for engineering, construction observation, inspection, and administrative services needed after the time specified in Paragraph Section 4.02 for Substantial Completion (as duly adjusted pursuant to the Contract), until the Work is substantially complete. B. After the Contractor achieves Substantial Completion, if the Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times, the Contractor shall reimburse NBU for the actual costs reasonably incurred by NBU for engineering, construction observation, inspection, and administrative services needed after the time specified in Paragraph Section 4.02 for Work to be completed and ready for final payment (as duly adjusted pursuant to the Contract), until the Work is completed and ready for final payment. C. The remedies contained in this Article 4 are not exclusive and shall be cumulative to other remedies provided to NBU in the event of default or breach by the Contractor.

Appears in 6 contracts

Samples: Construction Contract, Construction Contract, Construction Contract

Special Damages. A. In addition to the amount provided damages for delay addressed in liquidated damagesParagraph 4.03, the Contractor shall reimburse NBU Owner (1) for any fines or penalties imposed on NBU Owner as a direct result of the Contractor’s failure to attain Substantial Completion according to the Contract Times, and (2) for the actual costs reasonably incurred by NBU Owner for engineering, construction observation, inspection, and administrative services needed after the time specified in Paragraph 4.02 for Substantial Completion (as duly adjusted pursuant to the Contract), until the Work is substantially complete. B. After Contractor achieves Substantial Completion, if the Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times, the Contractor shall reimburse NBU Owner for the actual costs reasonably incurred by NBU Owner for engineering, construction observation, inspection, and administrative services needed after the time specified in Paragraph 4.02 for Work to be completed and ready for final payment (as duly adjusted pursuant to the Contract), until the Work is completed and ready for final payment. C. The remedies contained in this Article 4 are not exclusive and shall be cumulative to other remedies provided to the Owner in the event of default or breach by the Contractor.

Appears in 3 contracts

Samples: Construction Contract, Construction Contract, Construction Contract

Special Damages. A. In addition to the amount provided damages for delay addressed in liquidated damagesSection 4.03, the Contractor shall reimburse NBU for (1i) for any fines or penalties imposed on NBU as a direct result of the Contractor’s failure to attain Substantial Completion according to the Contract Times, Times and (2ii) for the actual costs reasonably incurred by NBU for engineering, construction observation, inspection, and administrative services needed after the time specified in Paragraph Section 4.02 for Substantial Completion (as duly adjusted pursuant to the Contract), until the Work is substantially complete. B. After the Contractor achieves Substantial Completion, if the Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times, the Contractor shall reimburse NBU for the actual costs reasonably incurred by NBU for engineering, construction observation, inspection, and administrative services needed after the time specified in Paragraph Section 4.02 for Work to be completed and ready for final payment (as duly adjusted pursuant to the Contract), until the Work is completed and ready for final payment. C. The remedies contained in this Article 4 are not exclusive and shall be cumulative to other remedies provided to NBU in the event of default or breach by the Contractor.

Appears in 2 contracts

Samples: Construction Contract, Construction Contract

AutoNDA by SimpleDocs

Special Damages. A. In addition to the amount provided damages for delay addressed in liquidated damagesParagraph 4.03, the Contractor shall reimburse NBU the Owner (1) for any fines or penalties imposed on NBU the Owner as a direct result of the Contractor’s failure to attain Substantial Completion according to the Contract Times, and (2) for the actual costs reasonably incurred by NBU the Owner for engineering, construction observation, inspection, and administrative services needed after the time specified in Paragraph 4.02 for Substantial Completion (as duly adjusted pursuant to the Contract), until the Work is substantially complete. B. After the Contractor achieves Substantial Completion, if the Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Times, the Contractor shall reimburse NBU the Owner for the actual costs reasonably incurred by NBU the Owner for engineering, construction observation, inspection, and administrative services needed after the time specified in Paragraph 4.02 for Work to be completed and ready for final payment (as duly adjusted pursuant to the Contract), until the Work is completed and ready for final payment. C. The remedies contained in this Article 4 are not exclusive and shall be cumulative to other remedies provided to the Owner in the event of default or breach by the Contractor.

Appears in 2 contracts

Samples: Construction Contract, Annual Unit Price Contract

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!