Start Up Test Sample Clauses

Start Up Test. The tests will be performed separately on each inverter and progressively throughout the plant. > Checking the connection of the inverter for each phase > Verification of the level of input voltage to the inverter > Start Up of inverters and check out the settings of the control system and protection devices > Checking the insulation on the DC side and the setting of the protection devices > Test inverter in different operating conditions provided by the control system (power on, power off, no Grid, etc.). > Verifying the proper operation of the interface device and associated organs of disconnection from the Grid > Verifying the correct operation of the photovoltaic plant Protection devices calibration > Verifying the compliance with the requirements and standards > Verifying and regulation of action levels of equipment and protection devices
AutoNDA by SimpleDocs
Start Up Test. The Contractor shall demonstrate the capability of each Unit and its equipment to meet the following requirements during start-ups:

Related to Start Up Test

  • Performance Tests Contractor shall perform Performance Tests in accordance with Section 11.2 of the Agreement and Attachment S.

  • Acceptance Testing The MCP must have the capability to report all elements in the Minimum Data Set as set forth in the ODJFS Encounter Data Specifications and must submit a test file in the ODJFS-specified medium in the required formats prior to contracting or prior to an information systems replacement or update. Acceptance testing of encounter data is required as specified in Section 29(a)(v) of this Appendix.

  • Stability Testing Patheon may be requested to conduct stability testing on the Products in accordance with the protocols set out in the Specifications for the separate fees and during the time periods set out in Schedule C to a Product Agreement. Patheon will not make any changes to these testing protocols without prior written approval from Client. If a confirmed stability test failure occurs, Patheon will notify Client within one Business Day, after which Patheon and Client will jointly determine the proceedings and methods to be undertaken to investigate the cause of the failure, including which party will bear the cost of the investigation. Patheon will not be liable for these costs unless it has failed to perform the Manufacturing Services in accordance with the Specifications, cGMPs, and Applicable Laws. Patheon will give Client ail stability test data and results at Client’s request.

  • Construction Period The term “Construction Period” shall mean the period from the date of this Lease to the date that Landlord completes construction of the Landlord’s Work (including any “Additional Base Building Items”, as defined in Section 3(f) of the Tenant Work Letter), and Common Areas, regardless of the occurrence of any Tenant Delay and without regard to the effect of any provision of this Lease pursuant to which the Premises are deemed to be Ready for Occupancy in advance of its actual occurrence. Notwithstanding any provision of this Lease to the contrary (including Exhibit B), during the Construction Period only, the following provisions shall be applicable:

  • Commencement Date Delay Except as otherwise provided in the Lease, Delivery of the Premises shall occur when Landlord’s Work has been Substantially Completed, except to the extent that completion of Landlord’s Work shall have been actually delayed by any one or more of the following causes (“Tenant Delay”):

  • Final Completion 6.5.1 Final Completion of the Work shall be achieved within ninety (90) Days after the earlier of the actual date of Substantial Completion or the Scheduled Substantial Completion Date (the “Final Completion Date”).

  • Duplicative Tests If the same Test is required for more than one representation or warranty listed on Schedule A, the Asset Representations Reviewer will only perform the Test once for each Review Receivable but will report the results of the Test for each applicable representation or warranty on the Review Report.

  • Adjustment of Minimum Quarterly Distribution and Target Distribution Levels (a) The Minimum Quarterly Distribution, First Target Distribution, Second Target Distribution, Third Target Distribution, Common Unit Arrearages and Cumulative Common Unit Arrearages shall be proportionately adjusted in the event of any distribution, combination or subdivision (whether effected by a distribution payable in Units or otherwise) of Units or other Partnership Securities in accordance with Section 5.10. In the event of a distribution of Available Cash that is deemed to be from Capital Surplus, the then applicable Minimum Quarterly Distribution, First Target Distribution, Second Target Distribution and Third Target Distribution, shall be adjusted proportionately downward to equal the product obtained by multiplying the otherwise applicable Minimum Quarterly Distribution, First Target Distribution, Second Target Distribution and Third Target Distribution, as the case may be, by a fraction of which the numerator is the Unrecovered Capital of the Common Units immediately after giving effect to such distribution and of which the denominator is the Unrecovered Capital of the Common Units immediately prior to giving effect to such distribution.

  • Subsequent Recalculation In the event the Internal Revenue Service adjusts the computation of the Company under Section 5.2 herein so that the Executive did not receive the greatest net benefit, the Company shall reimburse the Executive for the full amount necessary to make the Executive whole, plus a market rate of interest, as determined by the Committee, within 30 days after such adjustment.

  • Punchlist Upon completion of the Performance Tests and prior to Substantial Completion of a Subproject, Owner and Contractor shall inspect the Subproject, and Contractor shall prepare a proposed Punchlist of items identified as needing to be completed or corrected as a result of such inspection. Contractor shall promptly provide the proposed Punchlist to Owner for its review, together with an estimate of the time and cost necessary to complete or correct each Punchlist item. Contractor shall add to the proposed Punchlist any Punchlist items that are identified by Owner within ten (10) Days after Owner’s receipt of the proposed Punchlist from Contractor, and Contractor shall immediately initiate measures to complete or correct, as appropriate, any item on Contractor’s proposed Punchlist (including those items identified by Owner during Owner’s review) that are not of a Punchlist nature. Notwithstanding anything to the contrary in this Agreement, Contractor and Owner are not required as a condition of Substantial Completion of a Subproject to agree upon and identify every Punchlist item and include it on the Punchlist, but Contractor is required to complete as a condition of Substantial Completion of such Subproject that does not meet the definition of Punchlist as provided in Section 1.1. In the event of a dispute regarding whether a specific item of Work meets the definition of Punchlist under Section 1.1, the Parties shall resolve such dispute in accordance with Section 18.1A. Owner shall provide Contractor with access to the Work after Substantial Completion of a Subproject sufficient to enable Contractor to complete all Punchlist items, so long as such access does not unreasonably interfere with operation of a Subproject after Substantial Completion of the Subproject or the Existing Facility and subject to any reasonable security or safety requirements of Owner. Upon Contractor’s completion or correction of any items necessary to achieve Substantial Completion of a Subproject, as modified by any Owner additions, such Punchlist shall govern Contractor’s performance of the Punchlist items up to Final Completion. All Work on the Punchlist shall be completed by the date required for Final Completion, as specified in Section 5.3C, or Owner may, in addition to any other rights that it may have under this Agreement, complete such Punchlist Work at the expense of Contractor. In the event Owner elects to complete such Punchlist Work, Contractor shall pay Owner, within ten (10) Days after receipt of written notice from Owner, all reasonable costs and expenses incurred by Owner in performing such Punchlist Work, or, at Owner’s sole discretion, Owner may withhold or offset amounts owed to Contractor or collect on the Letter of Credit in accordance with Section 7.8 in the amount of such costs and expenses. Any Defective Work identified after agreement between the Parties of the Punchlist shall be corrected by Contractor as a Warranty item under Article 12.