STATEMENT OF THE WORK. 2.01 Subject to paragraph 3.02 below, Contractor shall prosecute and complete the Work in accordance with the schedule and as more fully described in Section 01100, paragraphs 1.13 and 1.14. 2.02 Owner will occupy premises during the entire construction period for conduct of normal operations. Cooperate with Owner in scheduling operations to minimize conflict and to facilitate Owner’s usage on the basis of the completion dates on the indicated schedule based on the Owner’s occupancy of areas. See Section 01100. 2.03 The Contractor specifically acknowledges that it has read and understands the requirements of the General Conditions, Section 00700, Parts 7 and 8 relating to Changes, including the requirements to provide timely notice, keep daily records, and submit documentation. Contractor further acknowledges that failure to comply with any of these requirements will result in rejection of claims as set forth in paragraph 7.01 B.5. General Contractor’s Initials _
Appears in 3 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
STATEMENT OF THE WORK. 2.01 Subject to paragraph 3.02 below, Contractor shall prosecute and complete the Work in accordance with the schedule and as more fully described in Section 01100, paragraphs 1.13 and 1.14.
2.02 Owner will occupy premises during the entire construction period for conduct of normal operations. Cooperate with Owner in scheduling operations to minimize conflict and to facilitate Owner’s usage on the basis of the completion dates on the indicated schedule based on the Owner’s occupancy of areas. See Section 01100.
2.03 The Contractor specifically acknowledges that it has read and understands the requirements of the General Conditions, Section 00700, Parts 7 and 8 relating to Changes, including the requirements to provide timely notice, keep daily records, and submit documentation. Contractor further acknowledges that failure to comply with any of these requirements will result in rejection of claims as set forth in paragraph 7.01 B.5B. 5. General Contractor’s Initials _Initials
Appears in 2 contracts
Samples: Construction Contract, Construction Contract
STATEMENT OF THE WORK. 2.01 Subject to paragraph 3.02 below, Contractor shall prosecute and complete the Work in accordance with the schedule and as more fully described in Section 01100, paragraphs 1.13 and 1.14.
2.02 Owner will occupy premises during the entire construction period for conduct of normal operations. Cooperate with Owner in scheduling operations to minimize conflict and to facilitate Owner’s Owner‟s usage on the basis of the completion dates on the indicated schedule based on the Owner’s Owner‟s occupancy of areas. See Section 01100.
2.03 The Contractor specifically acknowledges that it has read and understands the requirements of the General Conditions, Section 00700, Parts 7 and 8 relating to Changes, including the requirements to provide timely notice, keep daily records, and submit documentation. Contractor further acknowledges that failure to comply with any of these requirements will result in rejection of claims as set forth in paragraph 7.01 B.5B. 5. General Contractor’s Initials _Contractor‟s Initials
Appears in 1 contract
Samples: Construction Contract
STATEMENT OF THE WORK. 2.01 Subject to paragraph 3.02 below, Contractor shall prosecute and complete the Work in accordance with the schedule and as more fully described in Section 01100, paragraphs 1.13 and 1.14.
2.02 Owner will occupy premises during the entire construction period for conduct of normal operations. Cooperate with Owner in scheduling operations to minimize conflict and to facilitate Owner’s usage on the basis of the completion dates on the indicated schedule based on the Owner’s occupancy of areas. See Section 01100.
2.03 The Contractor specifically acknowledges that it has read and understands the requirements of the General Conditions, Section 00700, Parts 7 and 8 relating to Changes, including the requirements to provide timely notice, keep daily records, and submit documentation. Contractor further acknowledges that failure to comply with any of these requirements will result in rejection of claims as set forth in paragraph 7.01 B.5. General Contractor’s Initials _Initials
Appears in 1 contract
Samples: Construction Contract