Common use of Subcontractor Construction Schedules (Subnetworks) Clause in Contracts

Subcontractor Construction Schedules (Subnetworks). Upon the award of each subcontract, Construction Contractor shall jointly with the subcontractor, develop a schedule which is more detailed than the pre-bid schedule included in the bid packages, taking into account the work schedule of the other subcontractors. The subcontractor’s construction schedule shall include as many activities as necessary to make the schedule an effective tool for construction planning and for monitoring the performance of the subcontractor. The subcontractor’s construction schedule also shall show pertinent activities for material purchase orders, manpower supply, shop drawing schedules and material delivery schedules.

Appears in 19 contracts

Samples: Standard Construction Management Contract, Standard Construction Management Contract, Standard Construction Management Contract

AutoNDA by SimpleDocs

Subcontractor Construction Schedules (Subnetworks). Upon the award of each subcontract, the Construction Contractor Manager shall jointly with the subcontractor, develop a schedule which is more detailed than the pre-bid schedule included in the bid packages, taking into account the work Work schedule of the other subcontractors. The subcontractor’s construction schedule shall include as many activities as necessary to make the schedule an effective tool for construction planning and for monitoring the performance of the subcontractor. The subcontractor’s construction schedule also shall show pertinent activities for material purchase orders, manpower supply, shop drawing schedules and material delivery schedules.

Appears in 4 contracts

Samples: Construction Of, www.naplesgov.com, www.naplesgov.com

Subcontractor Construction Schedules (Subnetworks). Upon the award of each subcontract, the Construction Contractor shall jointly with the subcontractor, develop a schedule which is more detailed than the pre-bid schedule included in the bid packages, taking into account the work Work schedule of the other subcontractors. The subcontractor’s construction schedule shall include as many activities as necessary to make the schedule an effective tool for construction planning and for monitoring the performance of the subcontractor. The subcontractor’s construction schedule also shall show pertinent activities for material purchase orders, manpower supply, shop drawing schedules and material delivery schedules.

Appears in 3 contracts

Samples: Project Construction Management Contract, Project Construction Management Contract, Project Construction Management Contract

Subcontractor Construction Schedules (Subnetworks). Upon the award of each subcontract, the Construction Contractor Manager shall jointly with the subcontractor, develop a schedule which is more detailed than the pre-bid schedule included in the bid packages, taking into account the work Work schedule of the other subcontractors. The subcontractor’s construction schedule shall include as many activities as necessary to make the schedule an effective tool for construction planning and for monitoring the performance of the subcontractor. The subcontractor’s construction schedule also shall show pertinent activities for material purchase orders, manpower supply, shop drawing schedules and material delivery schedules.

Appears in 1 contract

Samples: Construction Management Agreement

AutoNDA by SimpleDocs

Subcontractor Construction Schedules (Subnetworks). Upon the award of each subcontract, Construction Contractor Manager shall jointly with the subcontractor, develop a schedule which is more detailed than the pre-bid schedule included in the bid packages, taking into account the work schedule of the other subcontractors. The subcontractor’s construction schedule shall include as many activities as necessary to make the schedule an effective tool for construction planning and for monitoring the performance of the subcontractor. The subcontractor’s construction schedule also shall show pertinent activities for material purchase orders, manpower supply, shop drawing schedules and material delivery schedules.

Appears in 1 contract

Samples: legistarweb-production.s3.amazonaws.com

Subcontractor Construction Schedules (Subnetworks). Upon the award of each subcontract, Construction the Contractor shall jointly with the subcontractor, develop a schedule which is more detailed than the pre-bid schedule included in the bid packages, taking into account the work schedule of the other subcontractors. The subcontractor’s construction schedule shall include as many activities as necessary to make the schedule an effective tool for construction planning and for monitoring the performance of the subcontractor. The subcontractor’s construction schedule shall also shall show pertinent activities for material purchase orders, manpower supply, shop drawing schedules and material delivery schedules.mater

Appears in 1 contract

Samples: Agreement for Contractor Services