Common use of Submittal Schedule Clause in Contracts

Submittal Schedule. Within seven (7) days after execution of this Contract, the Contractor shall provide the Owner and the Engineer with a preliminary submittal schedule of the dates that each shop drawing or sample will be submitted for approval. Within thirty (30) days after execution of this Contract, the Contractor shall provide the Engineer and the Owner with a final schedule of the dates that each shop drawing or sample will be submitted for approval. The sequence of the submittals of the Contractor shall be scheduled so as to permit an orderly review by the Engineer. The schedule shall allow reasonable added time according to the number or complexity of shop drawings or samples in each submittal for the checking, correction and rechecking of corrections, as well as for return of approved or rejected shop drawings and samples to the Contractor. The submittal schedules shall allow not less than fourteen (14) calendar days for the Engineer to review any shop drawing or sample.

Appears in 4 contracts

Samples: Lump Sum Construction Contract, Construction Contract, Construction Contract

AutoNDA by SimpleDocs

Submittal Schedule. Within seven (7) days after execution of this Contract, the Contractor shall provide the Owner and the Engineer with a preliminary submittal schedule of the dates that each shop drawing or sample will be submitted for approval. Within thirty (30) days after execution of this Contract, the Contractor shall provide the Engineer and the Owner with a final schedule of the dates that each shop drawing or sample will be submitted for approval. The sequence of the submittals of the Contractor shall be scheduled so as to permit an orderly review by the Engineer. The schedule shall allow reasonable added time according to the number or complexity of shop drawings or samples in each submittal for the checking, correction correction, and rechecking of corrections, as well as for return of approved or rejected shop drawings and samples to the Contractor. The submittal schedules shall allow not less than fourteen (14) calendar days for the Engineer to review any shop drawing or sample.

Appears in 1 contract

Samples: Lump Sum Construction Contract

AutoNDA by SimpleDocs

Submittal Schedule. Within seven (7) days after execution of this ContractAgreement, the Contractor shall provide the Architect and Owner and the Engineer with a preliminary submittal schedule of the dates that each shop drawing or sample will be submitted for approval. Within thirty (30) days after execution of this ContractAgreement, the Contractor shall provide the Engineer Architect and the Owner with a final schedule of the dates that each shop drawing or sample will be submitted for approval. The sequence of the submittals of the Contractor shall be scheduled so as to permit an orderly review by the EngineerOwner and the Architect. The schedule shall allow reasonable added time according to the number or complexity of shop drawings or samples in each submittal for the checking, correction and rechecking of corrections, as well as for return of approved or rejected shop drawings and samples to the Contractor. The submittal schedules shall allow not less than fourteen (14) calendar days for the Engineer Owner and Architect to review any shop drawing or sample. Material Testing.

Appears in 1 contract

Samples: Lump Sum Construction Agreement