Substantial Completion Date Substantial Completion of the Work as defined in Article 6.1.2 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by July 31, 2022.
Substantial Completion 9.8.1 When the Contractor considers that the Work, or a designated portion thereof which has been accepted in writing to by the State, is substantially complete as defined in Subparagraph
Final Completion Date Final Completion for the Work as defined in Article 6.1.3 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by October 31, 2024.
Final Completion The full and final completion of all Work in accordance with the Contract Documents.
Completion Date The Work under this Contract shall be completed by midnight of the date required in the Contract as the Material Completion and Occupancy Date unless extended by approved requests for extension of time.
Project Completion Date It is agreed between the Parties that the Project Completion Date is <END DATE, YEAR>. If the Project is not completed by such date then, subject to an amendment agreed to between the Parties, Alberta Innovates may elect to terminate this Investment Agreement. In such event, Alberta Innovates will notify the Applicant of its decision to terminate as soon as reasonably practical and shall advise the Applicant of the effective date of termination. Alberta Innovates will have no liability or obligation to reimburse the Applicant for any Project Costs incurred after the effective date of termination and may require the Applicant to return any portions of the Investment which were spent on Ineligible Expenses. Additionally, any portion of the Investment not used and accounted for in accordance with this Agreement as of the Project Completion Date or earlier termination is repayable by the Applicant to AI at AI’s request.
Upon Substantial Completion of the Work or designated portion thereof and upon application by the Contractor and certification by the Architect, the State shall make payment, reflecting adjustment in retainage, if any, for such Work or portion thereof, as provided in the Contract Documents.
ADDITIONAL SPECIAL CONTRACT CONDITIONS Special Contract Conditions revisions: the corresponding subsections of the Special Contract Conditions referenced below are replaced in their entirety with the following:
Termination Conditions Such license shall not be terminated or its exploitation enjoined, until and unless: (i) Hitachi has committed a material breach of its obligations under this IP License Agreement, Opto-Device has given written notice of such breach to Hitachi and such breach remains uncured after the Cure Period, or, in the case of a breach, which cannot be cured within such Cure Period, Hitachi has not instituted within such Cure Period steps necessary to remedy the default and/or thereafter has not diligently pursued the same to completion; or (ii) such a material breach is incurable. In the event the breach is a curable breach that cannot be cured within the Cure Period but with respect to which Hitachi has instituted steps necessary to remedy the default and is thereafter diligently pursuing such cure, both parties shall negotiate to determine whether further pursuit of such cure is reasonable. If the parties cannot agree on a resolution in such negotiations, then this issue shall be referred to arbitration pursuant to the arbitration procedures set forth in Exhibit B hereto to decide whether such breach can be cured or any other alternative remedy should be adopted. In the event the breach is an incurable breach, the parties agree that the matter shall be referred to arbitration pursuant to the arbitration procedures set forth in Exhibit B hereto to determine the appropriate remedy. In the event that either party submits the dispute to arbitration, both parties shall cooperate in such binding arbitration in accordance with Exhibit B.
Completion of Concrete Pours and Emergency Work (a) Except as provided in this sub-clause an Employee shall nor work or be required to work in the rain. (b) Employees shall not be required to start a concrete pour in Inclement Weather. (c) Where a concrete pour has been commenced prior to the commencement of a period of Inclement Weather Employees may be required to complete such concrete pour to a practical stage and for such work shall be paid at the rate of double time calculated to the next hour, and in the case of wet weather shall be provided with adequate wet weather gear. (d) If an Employee’s clothes become wet as a result of working in the rain during a concrete pour the Employee shall, unless the Employee has a change of dry working clothes available, be allowed to go home without loss of pay. (e) The provisions of clauses 32.7(c) and 32.7(d) hereof shall also apply in the case of emergency work where the Employees concerned and their delegates agree that the work is of an emergency nature and can start and/or proceed.