Physical Completion. The deadline for Physical Completion is 90 Calendar Days from the date Substantial Completion is achieved. Refer to General Provisions Section 1-08.5(2) for the requirements to be met in order to achieve Physical Completion.
Physical Completion. (i) Physical Completion has occurred.
Physical Completion. Physical Completion shall have occurred.
Physical Completion. Upon Physical Completion, at the request of the Borrower, provided that no Potential Default or Event of Default then exists, any remaining balance in the Base Equity Account and the Overrun Equity Account not otherwise used to fund Total Project Costs may be disbursed to the Borrower for distribution to the Equity Owners of the Borrower, without regard to the limitations set forth in Section 7.10 hereof (except for Section 7.10(a)(ii) hereof).
Physical Completion. Construction of the Project is physically complete and all Contract Services pertaining to the Project, except the items on the Punch List, is complete and in all respects is in compliance with this Comprehensive Agreement;
Physical Completion. All facilities and equipment necessary for the Project to operate as contemplated under the Project Plans:
(i) shall have been completely constructed, installed, completed, tested, and commissioned, all utilizing first-class standards of workmanship and materials and in accordance with the Project Plans and the terms of applicable construction agreements, subject to Punch List Items for which adequate reserves have been established, as verified by the Independent Engineer;
(ii) shall be operating in accordance with applicable guidelines;
(iii) shall have been accepted and paid for, as evidenced by the Borrower having issued acceptance certificates relating to each of the major engineering, procurement and construction contracts, subject to Punch List Items for which adequate reserves have been established, as verified by the Independent Engineer; and
(A) are being properly operated and maintained in all respects.
Physical Completion. All pipelines, facilities, materials and equipment for the Project have been installed in accordance with the requirements of the Contract Documents and inspected (tv’d), (each joint isolated and air tested, Mandrel test for flexible pipes), tested in accordance with Appendix 4 and the Project has been cleaned out as necessary and required by the City and Applicable Law;
Physical Completion. All the Work is physically completed on the Project and is Accepted by the District Coordinator. All documentation required by the Contract and by law shall be furnished by this date.
Physical Completion. At this stage the Work is fully and finally completed in accordance with the Contract Documents.
Physical Completion. Design-Build Work of the applicable School, including any associated parking, is in all respects physically complete and in compliance with this Agreement, except for (a) the Commissioning Tests; (b) Punch List Items; (c) at Developer’s election, the Athletic Fields; and (d) if applicable, the Demolition Work associated with the school existing on the Effective Date on the Xxxxxx Mill Middle School Land;