Summary of Contractor Scope. Except for items and services excluded from Contractor’s Scope of Work as identified in the Agreement to be provided by Owner or others, Contractor’s responsibilities for the design, engineering, procurement, fabrication, manufacture, erection, installation, construction, management, inspection, repair (including Corrective Work), testing (including Performance Tests), training, pre-commissioning, commissioning and placing into service of the Stage 2 Liquefaction Facility and modifications and improvements to the Existing Facility, Stage 1 Liquefaction Facility, and Equipment and systems, and the required related labor and materials, shall generally include: a. Detailed engineering design of the Stage 2 Liquefaction Facility and modifications and improvements to the Existing Facility and Stage 1 Liquefaction Facility; b. Development of Contractor deliverables as described in Attachment B of the Agreement; c. Supply of Equipment; d. Mobilization and Stage 2 Site establishment; e. Management, reporting and supervision of the Work; f. Construction and installation of Stage 2 Liquefaction Facility and modifications and improvement for the Existing Facility and Stage 1 Liquefaction Facility; g. Care, maintenance and preservation of all Equipment; h. Pre-commissioning; i. Mechanical Completion; j. Ready for Start Up; k. Commissioning and Start Up; l. Initial Operation of the each Subproject up to Substantial Completion of such Subproject; m. Performance Tests; n. Substantial Completion of such Subproject; o. Performance of Corrective Work in accordance with Article 12 of the Agreement; and p. Final Completion.
Appears in 3 contracts
Samples: Lump Sum Turnkey Agreement (Sabine Pass Liquefaction, LLC), Lump Sum Turnkey Agreement (Cheniere Energy Partners LP Holdings, LLC), Lump Sum Turnkey Agreement (Cheniere Energy Partners, L.P.)
Summary of Contractor Scope. Except for items and services excluded from Contractor’s Scope of Work as identified in the Agreement to be provided by Owner or others, Contractor’s responsibilities for the design, engineering, procurement, fabrication, manufacture, erection, installation, construction, management, inspection, repair (including Corrective Work), testing (including Performance Tests), training, pre-commissioning, commissioning and placing into service of the Stage 2 Liquefaction Facility and modifications and improvements to the Existing Facility, Stage 1 Liquefaction Facility, and Equipment and systems, and the required related labor and materials, shall generally include:
a. Detailed engineering design of the Stage 2 Liquefaction Facility and modifications and improvements to the Existing Facility and Stage 1 Liquefaction Facility;
b. Development of Contractor deliverables as described in Attachment B of the Agreement;
c. Supply of Equipment;
d. Mobilization and Stage 2 Site establishment;
e. Management, reporting and supervision of the Work;
f. Construction and installation of Stage 2 Liquefaction Facility and modifications and improvement for the Existing Facility and Stage 1 Liquefaction Facility;
g. Care, maintenance and preservation of all Equipment;
h. Pre-commissioning;
i. Mechanical Completion;
j. Ready for Start Up;
k. Commissioning and Start Up;
l. Initial Operation of the each Subproject up to Substantial Completion of such Subproject;
m. Performance Tests;
n. Substantial Completion of such Subproject;
o. Performance of Corrective Work in accordance with Article 12 of the Agreement; and
p. Final Completion.
Appears in 1 contract
Samples: Lump Sum Turnkey Agreement