Surrender or Removal of Transmission Facilities Sample Clauses

Surrender or Removal of Transmission Facilities. Upon expiration of the Term or any other termination of this Agreement (whether such termination is under Article 19, Section 21.3 or otherwise), in its entirety or with respect to less than all of the Premises, METC shall surrender to Consumers all Transmission Facilities then on, under or over the Premises (or applicable portion of the Premises, if the termination is as to less than all of the Premises) and title thereto shall vest in Consumers unless Consumers notifies METC in writing that some or all of the Transmission Facilities are to be removed therefrom. Notwithstanding the foregoing, in the event of termination under Article 19, METC shall have one hundred eighty (180) days after the date of such termination to remove Transmission Facilities, and the immediately preceding sentence shall in the case of a termination under Article 19 apply to all Transmission Facilities as are on, under or over the Premises at the expiration of one hundred eighty (180) days after the date of such termination. If Consumers notifies METC that some or all of the Transmission Facilities are to be so removed, METC shall, at its own expense, remove same with all reasonable diligence thereafter, restore the surface of the Premises affected thereby, and otherwise leave such Premises in good and proper condition. If and to the extent that Transmission Facilities are not to be so removed, METC shall leave same in such condition as would apply with same having been fully and properly kept, maintained and repaired by METC in compliance with the terms and conditions of this Agreement. METC shall coordinate removal activities with Consumers and Authorized Users as and to the extent necessary to protect or relocate Distribution Facilities or other uses of Transmission Facilities then being made of Transmission Facilities by Consumers and/or Authorized Users. METC shall continue to have access to the Premises after such expiration or termination for such purpose and shall not be deemed to be continuing to occupy Leased Property pursuant to Section 21.3. Until completion of such removal, Section 9.1, Articles 12, 14, 15, 16, 17 and 18 shall continue in effect notwithstanding expiration or termination of this Agreement. In the event title to some or all of the Transmission Facilities vests in Consumers pursuant to this Section 21.4, METC shall execute and deliver to Consumers from time to time such bills of sale or other conveyance as Consumers may reasonably request for the purpose...
AutoNDA by SimpleDocs

Related to Surrender or Removal of Transmission Facilities

  • Connecting Transmission Owner’s Attachment Facilities Construction The Connecting Transmission Owner’s Attachment Facilities shall be designed and constructed in accordance with Good Utility Practice. Upon request, within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Connecting Transmission Owner and Developer agree on another mutually acceptable deadline, the Connecting Transmission Owner shall deliver to the Developer “as-built” drawings, relay diagrams, information and documents for the Connecting Transmission Owner’s Attachment Facilities set forth in Appendix A. The Connecting Transmission Owner [shall/shall not] transfer operational control of the Connecting Transmission Owner’s Attachment Facilities and Stand Alone System Upgrade Facilities to the NYISO upon completion of such facilities.

  • DISCONNECTION OF SUPPLY 14.1 When can we arrange for disconnection? (a) you do not pay your bill by the pay-by date and, if you are a residential customer, you: (i) fail to comply with the terms of an agreed payment plan; or (ii) do not agree to an offer to pay the bill by instalments, or having agreed, you fail to comply with the instalment arrangement; (b) you do not provide a security deposit we are entitled to require from you; or (c) you do not give access to your premises to read a meter (where relevant) for 3 consecutive meter reads; or (d) you fail to give us safe and unhindered access to the premises as required by clause 11 or any requirements under the energy laws; or (e) there has been illegal or fraudulent use of energy at your premises in breach of clause 16 of this contract; or (f) we are otherwise entitled or required to do so under the Rules or by law.

  • Connecting Transmission Owner Obligations Connecting Transmission Owner shall maintain its transmission facilities and Attachment Facilities in a safe and reliable manner and in accordance with this Agreement.

  • Use of Interconnection Facilities by Third Parties 6551 Error! Hyperlink reference not valid.9.9.1 Purpose of Interconnection Facilities. 6551

  • System Upgrade Facilities and System Deliverability Upgrades Connecting Transmission Owner shall design, procure, construct, install, and own the System Upgrade Facilities and System Deliverability Upgrades described in Appendix A hereto. The responsibility of the Developer for costs related to System Upgrade Facilities and System Deliverability Upgrades shall be determined in accordance with the provisions of Attachment S to the NYISO OATT.

  • Information Submission by Connecting Transmission Owner The initial information submission by Connecting Transmission Owner shall occur no later than one hundred eighty (180) Calendar Days prior to Trial Operation and shall include New York State Transmission System information necessary to allow the Developer to select equipment and meet any system protection and stability requirements, unless otherwise mutually agreed to by the Developer and Connecting Transmission Owner. On a monthly basis Connecting Transmission Owner shall provide Developer and NYISO a status report on the construction and installation of Connecting Transmission Owner’s Attachment Facilities and System Upgrade Facilities and System Deliverability Upgrades, including, but not limited to, the following information: (1) progress to date; (2) a description of the activities since the last report; (3) a description of the action items for the next period; and (4) the delivery status of equipment ordered.

  • Connecting Transmission Owner’s Attachment Facilities Connecting Transmission Owner shall design, procure, construct, install, own and/or control the Connecting Transmission Owner’s Attachment Facilities described in Appendix A hereto, at the sole expense of the Developer.

  • Cancellation and Destruction of Surrendered ADRs; Maintenance of Records All ADRs surrendered to the Depositary shall be canceled by the Depositary. Canceled ADRs shall not be entitled to any benefits under the Deposit Agreement or be valid or enforceable against the Depositary for any purpose. The Depositary is authorized to destroy ADRs so canceled, provided the Depositary maintains a record of all destroyed ADRs. Any ADSs held in book-entry form (e.g., through accounts at DTC) shall be deemed canceled when the Depositary causes the number of ADSs evidenced by the Balance Certificate to be reduced by the number of ADSs surrendered (without the need to physically destroy the Balance Certificate).

  • Cost Responsibility for Interconnection Facilities and Distribution Upgrades 4.1 Interconnection Facilities 4.2 Distribution Upgrades

  • Purpose of Interconnection Facilities Except as may be required by Applicable Laws and Regulations, or as otherwise agreed to among the Parties, the Interconnection Facilities shall be constructed for the sole purpose of interconnecting the Large Generating Facility to the Participating TO’s Transmission System and shall be used for no other purpose.