SUSPENSION BY OWNER FOR CONVENIENCE. 19.4.1 The Owner may, without cause, by written order, direct the Design-Builder to suspend, delay or interrupt all or any part of the Work for such period of time as the Owner may determine to be appropriate for the convenience of the Owner. 19.4.2 If it should become necessary to suspend Work for an indefinite period, the Design- Builder will be granted an appropriate extension to the Contract Time for the period of suspension, which will not exceed the day-for-day period of suspension. The Owner may adjust the GMP Contract Sum for reasonable increases in the direct cost of performance of the Work (excluding profit) necessarily caused by such suspension, delay or interruption. 19.4.3 The Design-Builder will maintain and secure the Project, properly store all materials, provide for suitable drainage and provide any temporary structures that may be required during the suspension period. All established living material will be properly and continuously maintained in an acceptable growing condition throughout the suspension period. 19.4.4 No adjustments will be made for any suspension, delay or interruption to the extent that: 19.4.4.1 Performance is, was or would have been so suspended, delayed or interrupted by another cause for which the Design-Builder is responsible; or 19.4.4.2 An adjustment is made or denied under another provision of this Contract.
Appears in 4 contracts
Samples: Design Build Services Contract, Contract for Design Build Services, Contract for Design Build Services
SUSPENSION BY OWNER FOR CONVENIENCE. 19.4.1 The Owner may, without cause, by written order, direct the Design-Builder to suspend, delay or interrupt all or any part of the Work for such period of time as the Owner may determine to be appropriate for the convenience of the Owner.
19.4.2 If it should become necessary to suspend Work for an indefinite any period, the Design- Design-Builder will be granted an appropriate extension to the Contract Time for the period of suspension, which will not exceed the day-for-day period of suspension. The Owner may adjust the GMP Contract Sum for reasonable increases in the direct cost of performance of the Work (excluding profit) necessarily caused by such suspension, delay or interruption.
19.4.3 The Design-Builder will maintain and secure the Project, properly store all materials, provide for suitable drainage and provide any temporary structures that may be required during the suspension period. All established living material will be properly and continuously maintained in an acceptable growing condition throughout the suspension period.
19.4.4 No adjustments will be made for any suspension, delay or interruption to the extent that:
19.4.4.1 Performance is, was or would have been so suspended, delayed or interrupted by another cause for which the Design-Builder is responsible; or
19.4.4.2 An adjustment is made or denied under another provision of this Contract.
Appears in 1 contract
Samples: Contract for Design Build Services
SUSPENSION BY OWNER FOR CONVENIENCE. 19.4.1 The Owner may, without cause, by written order, direct the Design-Builder to suspend, delay or interrupt all or any part of the Work for such period of time as the Owner may determine to be appropriate for the convenience of the Owner.
19.4.2 If it should become necessary to suspend Work for an indefinite period, the Design- Builder will be granted an appropriate extension to the Contract Time for the period of suspension, which will not exceed the day-for-day period of suspension. The Owner may shall adjust the GMP Contract Sum for reasonable increases in the direct cost of performance of the Work (excluding profit) necessarily caused by such suspension, delay or interruption.
19.4.3 The Design-Builder will maintain and secure the Project, properly store all materials, provide for suitable drainage and provide any temporary structures that may be required during the suspension period. All established living material will be properly and continuously maintained in an acceptable growing condition throughout the suspension period.
19.4.4 No adjustments will be made for any suspension, delay or interruption to the extent that:
19.4.4.1 Performance is, was or would have been so suspended, delayed or interrupted by another cause for which the Design-Builder is responsible; or
19.4.4.2 An adjustment is made or denied under another provision of this Contract.
Appears in 1 contract
Samples: Contract for Design Build Services
SUSPENSION BY OWNER FOR CONVENIENCE. 19.4.1 The Owner may, without cause, by written order, direct the Design-Builder Contractor to suspend, delay or interrupt all or any part of the Work for such period of time as the Owner may determine to be appropriate for the convenience of the Owner.
19.4.2 If it should become necessary to suspend Work for an indefinite period, the Design- Builder Contractor will be granted an appropriate extension to the Contract Time for the period of suspension, which will not exceed the day-for-day period of suspension. The Owner may shall adjust the GMP Contract Sum for reasonable increases in the direct cost of performance of the Work (excluding profit) including a negotiated profit necessarily caused by such suspension, delay or interruption.
19.4.3 The Design-Builder Contractor will maintain and secure the Project, properly store all materials, provide for suitable drainage and provide any temporary structures that may be required during the suspension period. All established living material will be properly and continuously maintained in an acceptable growing condition throughout the suspension period.
19.4.4 No adjustments will be made for any suspension, delay or interruption to the extent that:
19.4.4.1 Performance is, was or would have been so suspended, delayed or interrupted by another cause for which the Design-Builder Contractor is solely responsible; or
19.4.4.2 An adjustment is made or denied under another provision of this Contract.
Appears in 1 contract
Samples: Contract for Services
SUSPENSION BY OWNER FOR CONVENIENCE. 19.4.1 The Owner may, without cause, by written order, direct the Design-Builder to suspend, delay or interrupt all or any part of the Work for such period of time as the Owner may determine to be appropriate for the convenience of the Owner.
19.4.2 If it should become necessary to suspend Work for an indefinite period, the Design- Design-Builder will be granted an appropriate extension to the Contract Time for the period of suspension, which will not exceed the day-for-day period of suspension. The Owner may adjust the GMP Contract Sum for reasonable increases in the direct cost of performance of the Work (excluding profit) necessarily caused by such suspension, delay or interruption.
19.4.3 The Design-Builder will maintain and secure the Project, properly store all materials, provide for suitable drainage and provide any temporary structures that may be required during the suspension period. All established living material will be properly and continuously maintained in an acceptable growing condition throughout the suspension period.
19.4.4 No adjustments will be made for any suspension, delay or interruption to the extent that:
19.4.4.1 Performance is, was or would have been so suspended, delayed or interrupted by another cause for which the Design-Builder is responsible; or
19.4.4.2 An adjustment is made or denied under another provision of this Contract.
Appears in 1 contract
Samples: Design Build Contract
SUSPENSION BY OWNER FOR CONVENIENCE. 19.4.1 The Owner may, without cause, by written order, direct the Design-Builder to suspend, delay or interrupt all or any part of the Work for such period of time as the Owner may determine to be appropriate for the convenience of the Owner.
19.4.2 If it should become necessary to suspend Work for an indefinite period, the Design- Builder will be granted an appropriate extension to the Contract Time for the period impact of suspension, which will not exceed the day-for-day period of such suspension. The Owner may adjust the GMP Contract Sum for reasonable increases in the direct cost of performance of the Work (excluding profit) necessarily caused by such suspension, delay or interruption.
19.4.3 The Design-Builder will maintain and secure the Project, properly store all materials, provide for suitable drainage and provide any temporary structures that may be required during the suspension period. All established living material will be properly and continuously maintained in an acceptable growing condition throughout the suspension period.
19.4.4 No adjustments will be made for any suspension, delay or interruption to the extent that:
19.4.4.1 Performance is, was or would have been so suspended, delayed or interrupted by another cause for which the Design-Builder is responsible; or
19.4.4.2 An adjustment is made or denied under another provision of this Contract.
Appears in 1 contract
Samples: Contract for Design Build Services