Termination due to Force Majeure Events. 37.2.1 The Owner shall have a right to forthwith terminate this Contract if the performance of this Contract is prevented, hindered or delayed due to a Force Majeure event for a continuous period of 90 (ninety) days from the beginning of a Force Majeure event. 37.3
Appears in 3 contracts
Samples: At Palatana Power, otpcindia.in, otpcindia.in
Termination due to Force Majeure Events. 37.2.1 32.3.1 The Owner shall have a right to forthwith terminate this Contract if the performance of this Contract is prevented, hindered or delayed due to a Force Majeure event for a continuous period of 90 (ninety) days from the beginning of a Force Majeure event. 37.3.
Appears in 2 contracts
Samples: At Palatana Power Plant, otpcindia.in
Termination due to Force Majeure Events. 37.2.1 44.3.1 The Owner shall have a right to forthwith terminate this Contract if the performance of this Contract is prevented, hindered or delayed due to a Force Majeure event for a continuous period of 90 (ninety) days from the beginning of a Force Majeure event. 37.3.
Appears in 2 contracts
Samples: Maintenance Contract, Maintenance Contract
Termination due to Force Majeure Events. 37.2.1 41.3.1 The Owner shall have a right to forthwith terminate this Contract if the performance of this Contract is prevented, hindered or delayed due to a Force Majeure event for a continuous period of 90 (ninety) days from the beginning of a Force Majeure event. 37.3.
Appears in 1 contract
Samples: Office and Palatana
Termination due to Force Majeure Events. 37.2.1 33.2.1 The Owner shall have a right to forthwith terminate this Contract if the performance of this Contract is prevented, hindered or delayed due to a Force Majeure event for a continuous period of 90 (ninety) days from the beginning of a Force Majeure event. 37.333.3
Appears in 1 contract
Samples: otpcindia.in
Termination due to Force Majeure Events. 37.2.1 43.3.1 The Owner shall have a right to forthwith terminate this Contract if the performance of this Contract is prevented, hindered or delayed due to a Force Majeure event for a continuous period of 90 (ninety) days from the beginning of a Force Majeure event. 37.3.
Appears in 1 contract
Samples: Office and Palatana
Termination due to Force Majeure Events. 37.2.1 33.2.1 The Owner shall have a right to forthwith terminate this Contract if the performance of this Contract is prevented, hindered or delayed due to a Force Majeure event for a continuous period of 90 (ninety) days from the beginning of a Force Majeure event. 37.3.
Appears in 1 contract
Samples: otpcindia.in
Termination due to Force Majeure Events. 37.2.1 38.3.1 The Owner shall have a right to forthwith terminate this Contract if the performance of this Contract is prevented, hindered or delayed due to a Force Majeure event for a continuous period of 90 (ninety) days from the beginning of a Force Majeure event. 37.3.
Appears in 1 contract
Samples: Office and Palatana
Termination due to Force Majeure Events. 37.2.1 41.2.1 The Owner shall have a right to forthwith terminate this Contract if the performance of this Contract is prevented, hindered or delayed due to a Force Majeure event for a continuous period of 90 (ninety) days from the beginning of a Force Majeure event. 37.341.3
Appears in 1 contract
Samples: www.otpcindia.in
Termination due to Force Majeure Events. 37.2.1 45.3.1 The Owner shall have a right to forthwith terminate this Contract if the performance of this Contract is prevented, hindered or delayed due to a Force Majeure event for a continuous period of 90 (ninety) days from the beginning of a Force Majeure event. 37.3.
Appears in 1 contract
Samples: otpcindia.in