The Progress Schedule Sample Clauses

The Progress Schedule. Contractor shall fully comply with the requirements for scheduling the Work as set forth in Section 01100 and Section 01320 of the Specifications. The Owner reserves the right to reschedule the Work, or the sequence of the activities of the Contractor, for no additional compensation should Owner deem such rescheduling to be in its best interest. At least fifteen (15) days prior to the due date of the first payment to be made hereunder by the Owner and thereafter on a monthly basis, the Contractor shall submit to the Owner a cash flow projection depicting the projected monthly cash flow for the entire Project.
AutoNDA by SimpleDocs

Related to The Progress Schedule

  • PROGRESS SCHEDULE The Contractor, within ten (10) working days of receiving notice of the award of the contract, shall prepare and submit for the State's and Architect's information an estimated progress schedule for the Work. The progress schedule shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

  • Construction Progress Schedule A schedule indicating proposed activity sequences and durations, milestone dates for receipt and approval of pertinent information, preparation, submittal, and processing of Shop Drawings and Samples, delivery of materials or equipment requiring long-lead time procurement, and proposed date(s) of Material Completion and Occupancy and Final Completion. The schedule will be developed to represent the sixteen or seventeen CSI Specification Divisions. It shall have a minimum number of activities as required to adequately represent to Owner the complete scope of work and define the Project’s critical path and associated activities. If the Project is to be phased, then each individual Phase should be identified from start through completion of the overall Project and should be individually scheduled and described, including any Owner’s occupancy requirements and showing portions of the Project having occupancy priority. The format of the schedule will have dependencies indicated on a monthly grid identifying milestone dates such as construction start, phase construction, structural top out, dry-in, rough-in completion, metal stud and drywall completion, equipment installation, systems operational, Material Completion and Occupancy Date, final inspection dates, Punchlist, and Final Completion date.

  • Flexible Work Schedule A flexible work schedule is any schedule that is not a regular, alternate, 9/80, or 4/10 work schedule and where the employee is not scheduled to work more than 40 hours in the "workweek" as defined in Subsections F. and H., below.

  • Work Schedule (A) Where an employee has an established schedule, a change in workdays or shifts will be posted no less than 14 calendar days in advance and will reflect at least a two workweek schedule; however, the state will make a good faith effort to reflect a one month schedule. (B) In the event of a declared emergency the notice requirement of this Section may be void. (C) The state will continue to observe the scheduling structures currently in place at each agency and agrees to bargain any change in the overall practice of how schedules are established.

  • Milestone Schedule Please state the status and progress of each Milestone and identify any completed Milestone(s) for the previous calendar quarter.

  • Time Schedule 4.1. A project schedule is included in Appendix A. 4.2. Any delay of services or change in sequence of tasks must be approved in writing by Delaware. 4.3. In the event that Vendor fails to complete the project or any phase thereof within the time specified in the Contract, or with such additional time as may be granted in writing by Delaware, or fails to prosecute the work, or any separable part thereof, with such diligence as will insure its completion within the time specified in this Agreement or any extensions thereof, Delaware shall suspend the payments scheduled as set forth in Appendix A.

  • Development Schedule The Project shall substantially comply with the specific timetables and triggers for action set forth in Article 5 of this Agreement. The parties acknowledge that, as provided in G.S. 160A-400.25(b), the failure to meet a commencement or completion date shall not, in and of itself, constitute a material breach of this Agreement pursuant to G.S. 160A-400.27 but must be judged based upon the totality of the circumstances.

  • APPENDIX H Appendix H, Contractor’s Insurance Requirements, attached hereto, is hereby expressly made a part of this Contract as fully as if set forth at length herein. The Contractor shall maintain in force at all times during the terms of the resultant Contract, policies of insurance pursuant to the requirements outlined in Appendix H – Contractor’s Insurance Requirements.

  • Contract Schedule The information set forth in the Contract Schedule is true and correct.

  • Flexible Work Schedules An employee may request a modification of their current work schedule to another schedule. The Employer, or its designees, may approve or deny flexible work schedules and retain the responsibility for determining exemptions from, or terminations of, flexible work schedules which adversely affect the operation of the Minnesota Judicial Branch or the level of service to the public.