Time and Material. If Owner and Contractor are unable to agree on the basis of pricing a Change Order pursuant to Sections 19.4.1 or 19.4.2 above, then Contractor shall be paid on a time and material basis in accordance with Section 19.4.4, provided that: (1) such costs are reasonably and properly incurred by Contractor; (2) such costs are documented as required in this Section 19.4.3; (3) such costs would not have been incurred but for the change in the Work; and, for those Requests for Change Orders under Section 19.3, (4) Contractor is entitled to relief for such Request for Change Order in accordance with the terms of this Contract. To be considered eligible for reimbursement, Contractor shall strictly comply with the following requirements:
Appears in 5 contracts
Samples: Design Build Contract, www.mwaa.com, metwashairports.com