Connecting Transmission Owner’s Scope of Work and Responsibilities The Connecting Transmission Owner will design, construct, own, operate, and maintain all Connecting Transmission Owner’s Interconnection Facilities, except as otherwise stated above and in the Project Specific Specifications. The Connecting Transmission Owner will complete all engineering reviews, field verifications and witness testing, etc. in accordance with the ESBs and the Project Specific Specifications. Connecting Transmission Owner shall provide the revenue metering CT/PT units and meter check socket enclosure. The Connecting Transmission Owner shall: provide, run, and wire both ends of the color-coded cable for the revenue metering instrument transformer secondary wiring; perform all terminations; and supply and install the meter. The revenue meter may require a communications link to the RTU. The Connecting Transmission Owner will specify and run those communications cables. The Connecting Transmission Owner shall complete all wiring, testing and commissioning of the RTU.
Network Resource Interconnection Service (check if selected)
Developer and Connecting Transmission Owner Notice Developer and Connecting Transmission Owner shall each notify the other Party, first orally and then in writing, of the release of any Hazardous Substances, any asbestos or lead abatement activities, or any type of remediation activities related to the Large Generating Facility or the Attachment Facilities, each of which may reasonably be expected to affect the other Party. The notifying Party shall: (i) provide the notice as soon as practicable, provided such Party makes a good faith effort to provide the notice no later than twenty-four hours after such Party becomes aware of the occurrence; and (ii) promptly furnish to the other Party copies of any publicly available reports filed with any Governmental Authorities addressing such events.