Unconditional Obligation to Proceed. Notwithstanding anything herein to the contrary, the Contractor will proceed with the Work so as to complete the Work on or before the Substantial Completion Date even if it has a dispute with the Owner concerning a Construction Contract Amendment, a Construction Change Directive or any extension of time which is or could be due to the Contractor pursuant to a Contract Amendment, a Construction Change Directive or otherwise.
Appears in 5 contracts
Samples: Lump Sum Construction Contract For, Construction Contract, Lump Sum Construction Contract
Unconditional Obligation to Proceed. Notwithstanding anything herein to the contrary, the Contractor will proceed with the Work when so as directed by Owner in writing and attempt in good faith to complete comply with the Work on or before the Substantial Completion Date as amended by Owner’s directed change, even if it has a dispute with the Owner concerning a Construction Contract Amendment, a Construction Change Directive the amount to be paid under Section 8.3 or any extension of time which is or could be due to the Contractor pursuant to a Contract Amendment, a Construction Change Directive or otherwiseOrder.
Appears in 2 contracts
Samples: Construction Agreement—nacsac (LSB Industries Inc), Construction Agreement – Dmw2 (LSB Industries Inc)