Uncorrected Deficiencies. If the standards set forth for performance in this Exhibit are not met per notification by the Authority, the Contractor will be required to execute a Corrective Action Plan, as drafted by the Authority, no later than five (5) business days from the date of notice by the Authority’s Chief Housing Solutions Officer. The Contractor will have ninety (90) calendar days to successfully implement the action plan, correct all deficiencies, and maintain at least a Standard Performance rating in both Monthly Performance and Quarterly Field Audits for at least the ninety (90) days following the execution of the Corrective Action Plan. No more than one Corrective Action Plan will be executed during a twelve (12) month period during the term of this Agreement. Failure to meet the terms outlined in the Corrective Action Plan may result in a material breach of this agreement.