Utilities / Hookups. Contractor shall provide the following utilities, hookups, and services by the end of the first business day upon the vessel’s arrival through the duration the vessel is in the Contractor’s possession: 1. Air – Provide 100 psig of air pressure through a 1-1/2” hose to the vessel’s air system. Air supplied shall be dried through a portable air dryer. 2. Internet – Provide high speed internet (DSL) to three (3) separate locations on the vessel. Minimum download / upload speeds shall be 25 Mbps/5 Mbps. 3. Sanitation – Garbage removal onboard the vessel shall occur on a daily basis Provide two (2) leak-proof skips and empty on a daily basis. Furnish a receiving tank for the vessel’s sewage plant effluent. Connect to the vessel’s overboard discharge. Empty the receiving tank as required to prevent overflowing. Furnish a receiving tank for the vessel’s oily bilge waste/slops. Connect to the vessel’s discharge. Empty the receiving tank as required to prevent overflowing.
Appears in 2 contracts
Utilities / Hookups. Contractor shall provide the following utilities, hookups, and services by the end of the first business day upon the vessel’s arrival through the duration the vessel is in the Contractor’s possession:
1. Air – Provide 100 psig of air pressure through a 1-1/2” hose to the vessel’s air system. Air supplied shall be dried through a portable air dryer.
2. Internet – Provide high speed internet (DSL) to three (3) separate locations on the vessel. Minimum download / upload speeds shall be 25 Mbps/5 Mbps.
3. Sanitation – Garbage removal onboard the vessel shall occur on a daily basis basis
a. Provide two (2) leak-proof skips and empty on a daily basis. .
b. Furnish a receiving tank for the vessel’s sewage plant effluent. Connect to the vessel’s overboard discharge. .
c. Empty the receiving tank as required to prevent overflowing. .
d. Furnish a receiving tank for the vessel’s oily bilge waste/slops. Connect to the vessel’s discharge. Empty the receiving tank as required to prevent overflowing.
Appears in 1 contract
Samples: Contract
Utilities / Hookups. Contractor shall provide the following utilities, hookups, and services by the end of the first business day upon the vessel’s arrival through the duration the vessel is in the Contractor’s possession:
1. Air – Provide 100 psig of air pressure through a 1-1/2” hose to the vessel’s air system. Air supplied shall be dried through a portable air dryer.
2. Internet – Provide high speed internet (DSL) to three (3) separate locations on the vessel. Minimum download / upload speeds shall be 25 Mbps/5 Mbps.
3. Sanitation – Garbage removal onboard the vessel shall occur on a daily basis Provide two (2) leak-proof skips and empty on a daily basis. Furnish a receiving tank for the vessel’s sewage plant effluent. Connect to the vessel’s overboard discharge. Empty the receiving tank as required to prevent overflowing. .
Furnish a receiving tank for the vessel’s oily bilge waste/slops. Connect to the vessel’s discharge. Empty the receiving tank as required to prevent overflowing.
Appears in 1 contract