Utility-Related Claims. Developer shall have no Claim to a Relief Event or Change Order on account of: 5.5.10.1 Any difference in the cost or time to complete Utility Adjustment Work from that anticipated by Developer, except to the extent set forth in Article 15 with respect to a Utility Owner delay under clause (l) of the definition of Relief Event; 5.5.10.2 Any inaccuracies in the Utility Information (including information as to the existence or nature of any rights or interests relating to the occupancy of any real property by any Utility), in any other Reference Information Documents or in public and private records with respect to any Utilities, whether the inaccuracies are as to the existence, location (horizontal or vertical), length, activity or inactivity, ownership, type, and/or any other characteristic of Utilities, except to the extent set forth in Article 15 with respect to clause (u) of the definition of Relief Event; 5.5.10.3 Any change in the proposed type or method of Utility Adjustment or any other change in the Utility Adjustment work from that described in the Utility Information or otherwise anticipated by Developer; 5.5.10.4 Any inaccuracy in any information included in the Reference Information Documents as to the existence or nature of any rights or interests relating to the occupancy of any real property by any Utility; and 5.5.10.5 Costs incurred or paid by Developer for the Adjustment of any Service Line or any Utility on or above the surface of the ground.
Appears in 6 contracts
Samples: Public Private Agreement, Public Private Agreement, Public Private Agreement
Utility-Related Claims. Developer shall have no Claim to a Relief Event or Change Order on account of:
5.5.10.1 Any difference in the cost or time to complete Utility Adjustment Work from that anticipated by Developer, except to the extent set forth in Article 15 with respect to a Utility Owner delay under clause (l) of the definition of Relief Event;
5.5.10.2 Any inaccuracies in the Utility Information (including information as to the existence or nature of any rights or interests relating to the occupancy of any real property by any Utility), in any other Reference Information Documents or in public and private records with respect to any Utilities, whether the inaccuracies are as to the existence, location (horizontal or vertical), length, activity or inactivity, ownership, type, and/or any other characteristic of Utilities, except to the extent set forth in Article 15 with respect to clause (u) of the definition of Relief Event;
5.5.10.3 Any change in the proposed type or method of Utility Adjustment or any other change in the Utility Adjustment work from that described in the Utility Information or otherwise anticipated by Developer;
5.5.10.4 Any inaccuracy in any information included in the Reference Information Documents as to the existence or nature of any rights or interests relating to the occupancy of any real property by any Utility; and
5.5.10.5 Costs incurred or paid by Developer for the Adjustment of any Service Line or any Utility on or above the surface of the ground.ground.
Appears in 1 contract
Samples: Public Private Agreement
Utility-Related Claims. Developer shall have no Claim to a Relief Event or Change Order on account of:
5.5.10.1 Any difference in the cost or time to complete Utility Adjustment Work from that anticipated by Developer, except to the extent set forth in Article 15 with respect to a Utility Owner delay under clause (l) of the definition of Relief Event;
5.5.10.2 Any inaccuracies in the Utility Information (including information as to the existence or nature of any rights or interests relating to the occupancy of any real property by any Utility), in any other Reference Information Documents or in public and private records with respect to any Utilities, whether the inaccuracies are as to the existence, location (horizontal or vertical), length, activity or inactivity, ownership, type, and/or any other characteristic of Utilities, except to the extent set forth in Article 15 with respect to clause (u) of the definition of Relief Event;
5.5.10.3 Any change in the proposed type or method of Utility Adjustment or any other change in the Utility Adjustment work from that described in the Utility Information or otherwise anticipated by Developer;
5.5.10.4 Any inaccuracy in any information included in the Reference Information Documents as to the existence or nature of any rights or interests relating to the occupancy of any real property by any Utility; and
5.5.10.5 Costs incurred or paid by Developer for the Adjustment of any Service Line or any Utility on or above the surface of the ground.ground.
Appears in 1 contract
Samples: Public Private Agreement
Utility-Related Claims. Developer shall have no Claim to a Relief Event or Change Order on account of:
5.5.10.1 Any difference in the cost or time to complete Utility Adjustment Work from that anticipated by DeveloperXxxxxxxxx, except to the extent set forth in Article 15 with respect to a Utility Owner delay under clause (l) of the definition of Relief Event;
5.5.10.2 Any inaccuracies in the Utility Information (including information as to the existence or nature of any rights or interests relating to the occupancy of any real property by any Utility), in any other Reference Information Documents or in public and private records with respect to any Utilities, whether the inaccuracies are as to the existence, location (horizontal or vertical), length, activity or inactivity, ownership, type, and/or any other characteristic of Utilities, except to the extent set forth in Article 15 with respect to clause (u) of the definition of Relief Event;
5.5.10.3 Any change in the proposed type or method of Utility Adjustment or any other change in the Utility Adjustment work from that described in the Utility Information or otherwise anticipated by Developer;
5.5.10.4 Any inaccuracy in any information included in the Reference Information Documents as to the existence or nature of any rights or interests relating to the occupancy of any real property by any Utility; and
5.5.10.5 Costs incurred or paid by Developer for the Adjustment of any Service Line or any Utility on or above the surface of the ground.
Appears in 1 contract