Common use of Variation to Scope of Works due to Scope Change Event Clause in Contracts

Variation to Scope of Works due to Scope Change Event. (a) If Aurizon Network considers, acting reasonably, that it is necessary to vary the Scope of Works as a result of a Scope Change Event, then Aurizon Network must provide reasonable details of the proposed variation to the Study Funder Committee who must advise Aurizon Network within [X] days whether they accept or reject Aurizon Network’s proposed variation. (b) If the Study Funder Committee accepts Aurizon Network’s proposed variation, then Aurizon Network: (i) may, by notice to All Study Funders (also a Variation Notice), vary the Scope of Works as a result of the Scope Change Event as specified in the Variation Notice; and (ii) must, if Aurizon Network gives a Variation Notice under (c) If the Study Funder Committee rejects Aurizon Network’s proposed variation provided under clause 9.2(a), then Aurizon Network may submit a revised proposal to vary the Scope of Works to the Study Funder Committee for approval.

Appears in 2 contracts

Samples: Studies Funding Agreement, Studies Funding Agreement

AutoNDA by SimpleDocs

Variation to Scope of Works due to Scope Change Event. (a) If Aurizon Network considers, acting reasonably, that it is necessary to vary the Scope of Works as a result of a Scope Change Event, then Aurizon Network Network: must provide reasonable details of the proposed variation to the Study Funder Committee who must advise Aurizon Network within [X] days whether they accept or reject Aurizon Network’s proposed variation. (b) If the Study Funder Committee accepts Aurizon Network’s proposed variation, then Aurizon Network: (a) (i) may, by notice to All Study Funders (also a Variation Notice), vary the Scope of Works as a result of the Scope Change Event as specified in the Variation Notice; and (b) (ii) must, if Aurizon Network gives a Variation Notice underunder clause 8.2(a)9.2(b)(i), provide in that Variation Notice reasonable details of the Scope Change Event and the effect of the Scope Change Event on the Scope of Works. (c) If the Study Funder Committee rejects Aurizon Network’s proposed variation provided under clause 9.2(a), then Aurizon Network may submit a revised proposal to vary the Scope of Works to the Study Funder Committee for approval.

Appears in 1 contract

Samples: Funding Agreement

AutoNDA by SimpleDocs

Variation to Scope of Works due to Scope Change Event. (a) If Aurizon Network considers, acting reasonably, that it is necessary to vary the Scope of Works as a result of a Scope Change Event, then Aurizon Network must provide reasonable details of the proposed variation to the Study Funder Committee who must advise Aurizon Network within [X] days whether they accept or reject Aurizon Network’s proposed variation. (b) If the Study Funder Committee accepts Aurizon Network’s proposed variation, then Aurizon Network: (i) may, by notice to All Study Funders (also a Variation Notice), vary the Scope of Works as a result of the Scope Change Event as specified in the Variation Notice; and (ii) must, if Aurizon Network gives a Variation Notice underunder clause 9.2(b)(i), provide in that Variation Notice reasonable details of the Scope Change Event and the effect of the Scope Change Event on the Scope of Works. (c) If the Study Funder Committee rejects Aurizon Network’s proposed variation provided under clause 9.2(a), then Aurizon Network may submit a revised proposal to vary the Scope of Works to the Study Funder Committee for approval.

Appears in 1 contract

Samples: Studies Funding Agreement

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!