Common use of Variations to Project Schedule Clause in Contracts

Variations to Project Schedule. 12.2.1 If in the opinion of the Province’s Representative or the Concessionaire at any time the actual progress of the design, construction, completion, commissioning and testing of the Works or the design and completion of the Decommissioning does not conform with the Project Schedule then, within 21 days of being so required by the Province’s Representative or (if earlier) becoming aware of the same, the Concessionaire will:

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

AutoNDA by SimpleDocs

Variations to Project Schedule. 12.2.1 If in the opinion of the Province’s 's Representative or the Concessionaire at any time the actual progress of the design, construction, completion, commissioning and testing of the Works or the design and completion of the Decommissioning does not conform with the Project Schedule then, within 21 10 days of being so required by the Province’s 's Representative or (if earlier) becoming aware of the same, the Concessionaire will:

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

AutoNDA by SimpleDocs
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!