Warranties by Contractor. 7.1 The Contractor warrants that the Works will: 7.1.1 be of good merchantable quality and fit for their purpose; 7.1.2 be performed using new materials, unless otherwise notified in writing by the Contractor; 7.1.3 conform with the description and the Specifications in the Purchase Order; and 7.1.4 throughout the Warranty Period, operate in accordance with the Specifications, and otherwise in accordance with the operation of similar products. 7.2 If any Works are found to be defective or do not comply with clause 7.1.1 to 7.1.4 and the Council notifies the Contractor of the defect during the Warranty Period, the Contractor must, at its own cost, promptly rectify any defects in the Works within the Warranty Response Time. 7.3 Failing rectification by the Contractor during the Warranty Response Time, the Council may rectify defects at the cost of the Contractor.
Appears in 5 contracts
Samples: Purchase Order for Works, Purchase Order for Services, Terms and Conditions for Purchase of Works
Warranties by Contractor. 7.1 The Contractor warrants that the Works will:
7.1.1 10.1 be of good merchantable quality and fit for their purpose;
7.1.2 10.1.1 be performed using new materials, unless otherwise notified in writing by the Contractor;
7.1.3 10.1.2 conform with the description and the Specifications in the Purchase Order; and
7.1.4 10.1.3 throughout the Warranty Period, operate in accordance with the Specifications, and otherwise in accordance with the operation of similar products.
7.2 10.1.4 If any Works are found to be defective or do not comply with clause 7.1.1 10.1.1 to 7.1.4 10.1.2 and the Council notifies the Contractor of the defect during the Warranty Period, the Contractor must, at its own cost, promptly rectify any defects in the Works within the Warranty Response Time.
7.3 10.1.5 Failing rectification by the Contractor during the Warranty Response Time, the Council may rectify defects at the cost of the Contractor.
Appears in 3 contracts
Samples: Terms & Conditions of Purchase, Terms & Conditions of Purchase, Terms & Conditions of Purchase
Warranties by Contractor. 7.1 The Contractor warrants that the Works will:
7.1.1 be of good merchantable quality and fit for their purpose;
7.1.2 be performed using new materials, unless otherwise notified in writing by the Contractor;
7.1.3 conform with the description and the Specifications in the Purchase Order; and
7.1.4 throughout the Warranty Period, operate in accordance with the Specifications, and otherwise in accordance with the operation of similar products.
7.2 If any Works are found to be defective or do not comply with clause 7.1.1 7.1 .1 to 7.1.4 and the Council notifies the Contractor of the defect during the Warranty Period, the Contractor must, at its own cost, promptly rectify any defects in the Works within the Warranty Response Time.
7.3 Failing rectification by the Contractor during the Warranty Response Time, the Council may rectify defects at the cost of the Contractor.
Appears in 1 contract
Samples: Terms and Conditions of Purchase
Warranties by Contractor. 7.1 9.1 The Contractor warrants that the Works will:
7.1.1 9.1.1 be of good merchantable quality and fit for their purpose;
7.1.2 9.1.2 be performed using new materials, unless otherwise notified in writing by the Contractor;
7.1.3 9.1.3 conform with the description and the Specifications in the Purchase Order; and
7.1.4 9.1.4 throughout the Warranty Period, operate in accordance with the Specifications, and otherwise in accordance with the operation of similar products.
7.2 9.2 If any Works are found to be defective or do not comply with clause 7.1.1 9.1.1 to 7.1.4 9.1.4 and the Council notifies the Contractor of the defect during the Warranty Period, the Contractor must, at its own cost, promptly rectify any defects in the Works within the Warranty Response Time.
7.3 9.3 Failing rectification by the Contractor during the Warranty Response Time, the Council may rectify defects at the cost of the Contractor.