Wind Generating Facility Output Reduction. To protect the reliability of the Transmission System, a Generating Facility that is a wind plant shall be capable of reducing its generation output in increments of no more than fifty (50) MW in five (5) minute intervals. The requirements may be met by using: (a) SCADA control of circuit breakers protecting wind farm collector distribution circuits,
Appears in 4 contracts
Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement
Wind Generating Facility Output Reduction. To protect the reliability of the Transmission System, a Generating Facility that is a wind plant shall be capable of reducing its generation output in increments of no more than fifty (50) MW in five (5) minute intervals. The requirements may be met by using: :
(a) SCADA control of circuit breakers protecting wind farm collector distribution circuits,, (b) automatic control of wind turbine power output, or (c) a combination of (a) and (b).
Appears in 2 contracts
Samples: Generator Interconnection Agreement, Interim Generator Interconnection Agreement
Wind Generating Facility Output Reduction. To protect the reliability of the Transmission System, a Generating Facility generating facility that is a wind plant shall be capable of reducing its generation output in increments of no more than fifty (50) MW in five (5) minute intervals. The requirements may be met by using: (a) SCADA control of circuit breakers protecting wind farm collector distribution circuits,