Transmission Owner Specific Interconnection Requirements Sample Clauses

Transmission Owner Specific Interconnection Requirements. Interconnection Customer must meet all of the Transmission Owner’s facility connection requirements as provided in the Nebraska Public Power District’s “Facility Connections Requirements Document” posted on xxxx.xxx. APPENDIX D TO GIA Security Arrangements Details Infrastructure security of Transmission System equipment and operations and control hardware and software is essential to ensure day-to-day Transmission System reliability and operational security. FERC will expect all Transmission Providers, market participants, and Interconnection Customers interconnected to the Transmission System to comply with the recommendations offered by the President's Critical Infrastructure Protection Board and, eventually, best practice recommendations from the electric reliability authority. All public utilities will be expected to meet basic standards for system infrastructure and operational security, including physical, operational, and cyber-security practices. [Date] Xxxxxx Xxxxxxx Senior Attorney Southwest Power Pool, Inc. 000 Xxxxxxx Xxxxx Little Rock, AR 72223-4936 Xxx Xxxxx, Contracts Manager Nebraska Public Power District X.X. Xxx 000 0000-00xx Xx. Xxxxxxxx, XX 00000-0000 APPENDIX E TO GIA Commercial Operation Date Re: Thunderhead Wind Energy LLC Generating Facility (GEN-2015-023) Dear Xxx. Xxxxxxx and Xx. Xxxxx: On [Date] Thunderhead Wind Energy LLC (“Thunderhead”) has completed Trial Operation of the referenced Generating Facility. This letter confirms that Thunderhead commenced Commercial Operation of the Generating Facility, effective as of [Date plus one day]. Thank you. [Signature] Thunderhead Wind Energy LLC Attn.: General Counsel Xxx Xxxxx Xxxxxx, Suite 1800 Chicago, IL 60606 Phone: 000-000-0000 Email: xxxxxxxxxxxxxxx.xxxxxxx@xxxxxxxxxxxx.xxx Notices: APPENDIX F TO GIA ADDRESSES FOR DELIVERY OF NOTICES AND XXXXXXXX Transmission Provider: Xxxxxx Xxxxxxx Senior Attorney Southwest Power Pool, Inc. 000 Xxxxxxx Xxxxx Little Rock, AR 00000-0000 Phone: 000-000-0000 Email: xxxxxxxx@xxx.xxx Transmission Owner: Xxx Xxxxx, Contracts Manager Nebraska Public Power District X.X. Xxx 000 0000-00xx Xx. Xxxxxxxx, XX 00000-0000 Phone: 000-000-0000 Email: xxxxxxx@xxxx.xxx Interconnection Customer: Thunderhead Wind Energy LLC Attn.: General Counsel Xxx Xxxxx Xxxxxx, Suite 1800 Chicago, IL 60606 Phone: 000-000-0000 Email: xxxxxxxxxxxxxxx.xxxxxxx@xxxxxxxxxxxx.xxx Xxxxxxxx and Payments: [Specify addresses for construction invoices, O&M invoices and settlement of ancillary...
AutoNDA by SimpleDocs
Transmission Owner Specific Interconnection Requirements. The unique requirements of each generation interconnection will dictate the establishment of mutually agreeable interconnection guidelines that further define the requirements of this Agreement. The interconnection guidelines will address, but not be limited to, the following:

Related to Transmission Owner Specific Interconnection Requirements

  • Nyiso and Connecting Transmission Owner Authority General.‌‌ NYISO or Connecting Transmission Owner may take whatever actions with regard to the New York State Transmission System or the Connecting Transmission Owner’s Attachment Facilities it deems necessary during an Emergency State in order to (i) preserve public health and safety, (ii) preserve the reliability of the New York State Transmission System or the Connecting Transmission Owner’s Attachment Facilities, (iii) limit or prevent damage, and (iv) expedite restoration of service. NYISO and Connecting Transmission Owner shall use Reasonable Efforts to minimize the effect of such actions or inactions on the Large Generating Facility or the Developer’s Attachment Facilities. NYISO or Connecting Transmission Owner may, on the basis of technical considerations, require the Large Generating Facility to mitigate an Emergency State by taking actions necessary and limited in scope to remedy the Emergency State, including, but not limited to, directing Developer to shut-down, start-up, increase or decrease the real or reactive power output of the Large Generating Facility; implementing a reduction or disconnection pursuant to Article 13.4.2; directing the Developer to assist with blackstart (if available) or restoration efforts; or altering the outage schedules of the Large Generating Facility and the Developer’s Attachment Facilities. Developer shall comply with all of the NYISO and Connecting Transmission Owner’s operating instructions concerning Large Generating Facility real power and reactive power output within the manufacturer’s design limitations of the Large Generating Facility’s equipment that is in service and physically available for operation at the time, in compliance with Applicable Laws and Regulations.

  • Connecting Transmission Owner’s Attachment Facilities Connecting Transmission Owner shall design, procure, construct, install, own and/or control the Connecting Transmission Owner’s Attachment Facilities described in Appendix A hereto, at the sole expense of the Developer.

  • NYISO and Connecting Transmission Owner Obligations Connecting Transmission Owner and NYISO shall cause the New York State Transmission System and the Connecting Transmission Owner’s Attachment Facilities to be operated, maintained and controlled in a safe and reliable manner in accordance with this Agreement and the NYISO Tariffs. Connecting Transmission Owner and NYISO may provide operating instructions to Developer consistent with this Agreement, NYISO procedures and Connecting Transmission Owner’s operating protocols and procedures as they may change from time to time. Connecting Transmission Owner and NYISO will consider changes to their respective operating protocols and procedures proposed by Developer.

  • Connecting Transmission Owner’s Attachment Facilities Construction The Connecting Transmission Owner’s Attachment Facilities shall be designed and constructed in accordance with Good Utility Practice. Upon request, within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Connecting Transmission Owner and Developer agree on another mutually acceptable deadline, the Connecting Transmission Owner shall deliver to the Developer “as-built” drawings, relay diagrams, information and documents for the Connecting Transmission Owner’s Attachment Facilities set forth in Appendix A. The Connecting Transmission Owner [shall/shall not] transfer operational control of the Connecting Transmission Owner’s Attachment Facilities and Stand Alone System Upgrade Facilities to the NYISO upon completion of such facilities.