Transmission Owner Specific Interconnection Requirements Sample Clauses

Transmission Owner Specific Interconnection Requirements. The unique requirements of each generation interconnection will dictate the establishment of mutually agreeable interconnection guidelines that further define the requirements of this Agreement. The interconnection guidelines will address, but not be limited to, the following:
AutoNDA by SimpleDocs
Transmission Owner Specific Interconnection Requirements. Interconnection Customer must meet all of the Transmission Owner’s facility connection requirements as provided in the Nebraska Public Power District’s “Facility Connections Requirements Document” posted on xxxx.xxx. Infrastructure security of Transmission System equipment and operations and control hardware and software is essential to ensure day-to-day Transmission System reliability and operational security. FERC will expect all Transmission Providers, market participants, and Interconnection Customers interconnected to the Transmission System to comply with the recommendations offered by the President's Critical Infrastructure Protection Board and, eventually, best practice recommendations from the electric reliability authority. All public utilities will be expected to meet basic standards for system infrastructure and operational security, including physical, operational, and cyber-security practices. Xxxxxx Xxxxxxx Senior Attorney Southwest Power Pool, Inc. 000 Xxxxxxx Xxxxx Little Rock, AR 72223-4936 Xxx Xxxxx, Contracts Manager Nebraska Public Power District X.X. Xxx 000 0000-00xx Xx. Xxxxxxxx, XX 00000-0000 Re: Thunderhead Wind Energy LLC Generating Facility (GEN-2015-023) Dear Xxx. Xxxxxxx and Xx. Xxxxx: On [Date] Thunderhead Wind Energy LLC (“Thunderhead”) has completed Trial Operation of the referenced Generating Facility. This letter confirms that Thunderhead commenced Commercial Operation of the Generating Facility, effective as of [Date plus one day]. Thank you. Thunderhead Wind Energy LLC Attn.: General Counsel Xxx Xxxxx Xxxxxx, Suite 1800 Chicago, IL 60606 Phone: 000-000-0000 Email: xxxxxxxxxxxxxxx.xxxxxxx@xxxxxxxxxxxx.xxx Xxxxxx Xxxxxxx Senior Attorney Southwest Power Pool, Inc. 000 Xxxxxxx Xxxxx Little Rock, AR 00000-0000 Phone: 000-000-0000 Email: xxxxxxxx@xxx.xxx Transmission Owner: Xxx Xxxxx, Contracts Manager Nebraska Public Power District X.X. Xxx 000 0000-00xx Xx. Xxxxxxxx, XX 00000-0000 Phone: 000-000-0000 Email: xxxxxxx@xxxx.xxx Interconnection Customer: Thunderhead Wind Energy LLC Attn.: General Counsel Xxx Xxxxx Xxxxxx, Suite 1800 Chicago, IL 60606 Phone: 000-000-0000 Email: xxxxxxxxxxxxxxx.xxxxxxx@xxxxxxxxxxxx.xxx Supervisor of Transmission Settlements Southwest Power Pool, Inc. 000 Xxxxxxx Xxxxx Little Rock, AR 72223-4936 Transmission Owner: Xxxxxx X. Xxxxxxx, Finance & Cost Manager - Operations Nebraska Public Power District X.X. Xxx 000 0000-00xx Xxxxxx Xxxxxxxx, XX 00000-0000 Phone: 000-000-0000 Thunderhead Wind Energy LL...
Transmission Owner Specific Interconnection Requirements. Transmission Owner also maintains its own Facility Connection Requirements, which may be found at xxxx://xxx.xxxxx.xxxx.xxx/WR/index.html.

Related to Transmission Owner Specific Interconnection Requirements

  • Connecting Transmission Owner’s Attachment Facilities Connecting Transmission Owner shall design, procure, construct, install, own and/or control the Connecting Transmission Owner’s Attachment Facilities described in Appendix A hereto, at the sole expense of the Developer.

  • NYISO and Connecting Transmission Owner Obligations Connecting Transmission Owner and NYISO shall cause the New York State Transmission System and the Connecting Transmission Owner’s Attachment Facilities to be operated, maintained and controlled in a safe and reliable manner in accordance with this Agreement and the NYISO Tariffs. Connecting Transmission Owner and NYISO may provide operating instructions to Developer consistent with this Agreement, NYISO procedures and Connecting Transmission Owner’s operating protocols and procedures as they may change from time to time. Connecting Transmission Owner and NYISO will consider changes to their respective operating protocols and procedures proposed by Developer.

  • Connecting Transmission Owner’s Attachment Facilities Construction The Connecting Transmission Owner’s Attachment Facilities shall be designed and constructed in accordance with Good Utility Practice. Upon request, within one hundred twenty (120) Calendar Days after the Commercial Operation Date, unless the Connecting Transmission Owner and Developer agree on another mutually acceptable deadline, the Connecting Transmission Owner shall deliver to the Developer “as-built” drawings, relay diagrams, information and documents for the Connecting Transmission Owner’s Attachment Facilities set forth in Appendix A. The Connecting Transmission Owner [shall/shall not] transfer operational control of the Connecting Transmission Owner’s Attachment Facilities and Stand Alone System Upgrade Facilities to the NYISO upon completion of such facilities.

  • Connecting Transmission Owner Obligations Connecting Transmission Owner shall maintain its transmission facilities and Attachment Facilities in a safe and reliable manner and in accordance with this Agreement.

  • Interconnection 2.1 This section applies to linking with suppliers providing public telecommunications transport networks or services in order to allow the users of one supplier to communicate with users of another supplier and to access services provided by another supplier, where specific commitments are undertaken.