FIRST AMENDMENT TO LEASE
Exhibit 10.10
FIRST AMENDMENT TO LEASE
THIS FIRST AMENDMENT TO LEASE (this “Amendment”) is entered into as of this 25th day of October, 2006, by and between BMR-7 GRAPHICS DRIVE LLC, a Delaware limited liability company (“Landlord”), and LINGUAGEN CORPORATION, a Delaware corporation (“Tenant”).
RECITALS
A. WHEREAS, Landlord and Tenant entered into that certain Lease dated as of November 28,2005 (the “Lease”), whereby Tenant leases certain premises (the “Premises”) from Landlord at 0 Xxxxxxxx Xxxxx in Ewing, New Jersey (the “Building”);
B. WHEREAS, Landlord and Tenant desire to correct certain language and modify other language appearing in the Lease; and
C. WHEREAS, Landlord and Tenant desire to modify and amend the Lease only in the respects and on the conditions hereinafter stated.
AGREEMENT
NOW, THEREFORE, Landlord and Tenant, in consideration of the mutual promises contained herein and for other good and valuable consideration, the receipt and sufficiency of which are hereby acknowledged, and intending to be legally bound, agree as follows:
1. Definitions. For purposes of this Amendment, capitalized terms shall have the meanings ascribed to them in the Lease unless otherwise defined herein.
2. Square Footage of Building.
a. Section 2.3 of the Lease is hereby replaced in its entirety with the following: “Rentable Area of Building: 72,300 sq. ft., subject to adjustment pursuant to the terms hereof”.
b. Section 2.8 of the Lease is hereby replaced in its entirety with the following: “Tenant’s Pro Rata Share: 25.69% of the Building, subject to adjustment pursuant to the terms hereof”.
3. Estimated Tern Commencement Date. Section 2.9 of the Lease is hereby replaced in its entirety with the following: “Estimated Term Commencement Date: April 1, 2007”
4. Substantial Completion. In Section4.1 of the Lease, the date May 21, 2006, is hereby replaced with April 1, 2007. In the same Section, the date June 18, 2006, is hereby replaced with May 1, 2007.
5. Construction Manager (at-risk). Landlord and Tenant hereby approve ProTecs, Inc., as the Construction Manager (at-risk) (“Construction Manager”) to perform work under the Work Letter. All references in the Lease and the Work Letter to the “Construction Manager” are intended to and for all purposes shall mean and refer to ProTecs, Inc., as such Construction Manager (at-risk).
1
Construction Manager’s compensation shall be the six percent (6%) construction management fee provided for in Section 4.6 of the Lease.
6. Competitive Bidding.
a. The words “general contractor,” and “and Landlord and Tenant shall each participate in the review of the competitive bid process” are hereby deleted from Section 4.7 of the Lease.
b. The word “bidding” in Section 5.1 of the Work Letter is hereby replaced with “negotiating the construction contract documents”.
c. Section 6 of the Work Letter is hereby replaced in its entirety with the following: “Landlord shall, with the assistance of Tenant’s Architect, issue bidding documents to, and assist in contract negotiations with the Construction Manager. Landlord shall assist Tenant’s Architect with respect to questions from the Construction Manager and with the issuance of supplemental project information, and Landlord and the Construction Manager agree to work timely and to cooperate reasonably with Tenant if and when Tenant requests assistance to value engineer Landlord’s Work to reduce expenses. Without limitation of the foregoing, Landlord shall reasonably cooperate with Tenant in revising the scope of Landlord’s Work to the extent necessary to reduce the Construction Costs to a level reasonably acceptable to Tenant, including, without limitation, re- bidding one or more aspects of Landlord’s Work as may be requested by Tenant in an effort to reduce costs; provided, however, that Tenant shall not require that Landlord construct any improvements below the Building Standard as set forth in that document dated September 12, 2005, and entitled “BioMed Realty Trust, Inc. Tenant Standards,” attached hereto as Exhibit A,” Landlord and Tenant acknowledge that Landlord has presented the GMP proposal to Tenant, which proposal is attached as Exhibit B hereto (the “Proposal”). Tenant hereby approves of the GMP contained in the Proposal (such GMP shall hereafter be deemed to be the “GMP” as defined in the Lease).
7. Tenant Improvement Costs. The first (1st) paragraph of Section 4.8 of the Lease is hereby replaced in its entirety with the following: “Landlord shall, upon execution hereof, establish a fund from which Tenant may borrow funds to pay for additional Tenant Improvements in the Premises. Tenant may borrow such funds from Landlord in one or more draws, at Tenant’s discretion, beginning from and after the date hereof until that date which is two (2) years from and after the Term Commencement Date (as provided in Section 4.6) and in two (2) tranches: the first tranche (“Tranche 1”) providing One Hundred Twenty-Five Dollars ($125) per rentable square foot and the second tranche (“Tranche 2”) providing Fifty Dollars ($50) per rentable square foot. Tenant shall pay to Landlord, as Additional Rent (as defined below), any amount funded to Tenant by Landlord from Tranche 1or Tranche 2 amortized over the first (1st) ten (10) years of the Term of the Lease at an annual rate of eleven percent (11%), in the case of Tranche 1, and twelve percent (12%), in the case of Tranche 2.”
8. Property Management Fee. In the first (1st) paragraph of Section 7.1(b) of the Lease, “Building); and costs of management services, which costs of management services shall not exceed three percent (3%) of the Basic Annual Rent due from Tenant” is hereby replaced with “Building). In addition, Tenant shall pay to Landlord on the first day of each calendar month of the Term, as Additional Rent, a property management fee equal to three percent (3%) of such month’s installment
2
of Basic Annual Rent due from Tenant; such property management fee to be payable in lieu of any other property management fee otherwise payable under this Lease.”
9. Broker. Tenant represents and warrants that it has not dealt with any broker or agent in the negotiation for or the obtaining of this Amendment, other than Xxxxxxx & Xxxxxxxxx of New Jersey (“Broker”), to whom Landlord alone shall be obligated to pay a commission in connection with the Lease as provided in a separate written agreement between Landlord and Broker. Tenant agrees to indemnify, defend and hold Landlord harmless from any and all cost or liability for compensation claimed by any other broker or agent employed or engaged by it or claiming to have been employed or engaged by it. Landlord agrees to indemnify, defend and hold Tenant harmless from any and all cost or liability for compensation claimed by any other broker or agent employed or engaged by it or claiming to have been employed or engaged by it.
10. Security Deposit. Upon execution of this Amendment by Landlord and Tenant, (a) Tenant shall deposit with Landlord the Security Deposit (as defined in Section 9 of the Lease), and (b) Landlord shall simultaneously reimburse to Tenant, from the Initial Tenant Improvement Allowance, the fees for Tenant’s Architect as requisitioned by Tenant through March 31, 2006, in the amount of $163,586. Additional sums to reimburse Tenant for fees charged by Tenant’s Architect for the period subsequent to March 31, 2006, shall be requisitioned by Tenant and reimbursed by Landlord as provided in Section 5.6 of the Work Letter.
11. No Default. Tenant represents, warrants and covenants that, to the best of Tenant’s knowledge, neither Landlord nor Tenant are in default of any of their respective obligations under the Lease, and no event has occurred that, with the passage of time or the giving of notice (or both) would constitute a default by either Landlord or Tenant thereunder. Landlord represents, warrants and covenants that, to the best of Landlord’s knowledge, neither Landlord nor Tenant are in default of any of their respective obligations under the Lease and no event has occurred that, with the passage of time or the giving of notice (or both) would constitute a default by either Landlord or Tenant thereunder.
12. Effect of Amendment. Except as modified by this Amendment, the Lease and all the covenants, agreements, terms, provisions and conditions thereof shall remain in full force and effect and are hereby ratified and affirmed. The covenants, agreements, terms, provisions and conditions contained in this Amendment shall bind and inure to the benefit of the parties hereto and their respective successors and, except as otherwise provided in the Lease, their respective assigns. In the event of any conflict between the terms contained in this Amendment and the Lease, the terms herein contained shall supersede and control the obligations and liabilities of the parties. From and after the date hereof, the term “Lease” as used in the Lease shall mean the Lease, as modified by this Amendment.
13. Miscellaneous. This Amendment becomes effective only upon execution and delivery hereof by Landlord and Tenant. The captions of the paragraphs and subparagraphs in this Amendment are inserted and included solely for convenience and shall not be considered or given any effect in construing the provisions hereof. All exhibits hereto are incorporated herein by reference.
3
14. Counterparts. This Amendment may be executed in one or more counterparts that, when taken together, shall constitute one original.
[REMAINDER OF THIS PAGE INTENTIONALLY LEFT BLANK]
4
IN WITNESS WHEREOF, Landlord and Tenant have executed this Amendment to be effective on the date first above written.
LANDLORD:
BMR-7 GRAPHICS DRIVE LLC,
a Delaware limited liability company
By: |
|
/s/ Xxxx X. Xxxxxxxx |
|
Name: |
|
Xxxx X. Xxxxxxxx |
|
Title: |
|
Executive V.P. |
|
TENANT:
LINGUAGEN CORPORATION,
a Delaware corporation
By: |
|
/s/ Xxxxx Xxxxxxx |
|
Name: |
|
Xxxxx Xxxxxxx |
|
Title: |
|
CFO |
|
5
EXHIBIT A
BUILDING STANDARD
BioMed Realty Trust, Inc.
Tenant Standards
Date: September 12, 2005
Revision 1
The following describes items to be included in the tenant standards. This information is organized based on CSI division and/or section numbers.
Attachments:
Partition Details (
Ceiling Details (
Casework Details (
Division 6: Wood & Plastic
Section 06400: Architectural Woodwork
Wood Veneer designated WD- I. Maple wood veneer matching maple plastic laminate and vice versa.
Section 06411: Plastic Laminate Millworks
Office Area
1. All P-Xxx Cabinet Door pulls/hardware to be: Amerock, Esential’Z Open Arch Pull (part # 9363-G10) with concealed hinges, U.O.N. Cut sheet attached. Door pulls/hardware at conference room casework to be: Amerock, Galleria Pull (part # 24016-SS) with touch latch hardware.
2. Copy Room casework: Plastic laminate countertop and base cabinet with drawers and doors.
3. Copy/Mail Room casework: Plastic laminate countertop and base cabinet with drawers and doors. Mail slots design to be reviewed by BioMed Realty Trust, Inc.
4. Coffee Room casework: Plastic laminate countertop and plastic laminate base cabinet with doors and drawer.
5. Conference Room casework: Option A: Wood veneer casework designated WD- I (maple to match maple wood veneer door). Option B: Plastic laminate XXX.
6. Equipment stations: Plastic laminate countertop with 18” drawer unit base cabinet at each end.
000 Xxxxx Xxxxxx, Xxxxxxxx Xxxx, XX 00000 phone 650 943 1660 fax 650 943 I670 xxx.xxxxxxxxxxxx.xxx
1
Lab Area
1. All lab casework to be finished with matching (maple) chemical resistant high pressure plastic laminate and (LabTops or equal) 1” solid black epoxy countertop.
2. All lab bench utility chases to be finish with (3-Form) translucent panel or perforated metal sheet support by aluminum C channels. Detail , sheet A8. .
3. Reagent shelf at bench to be construct with 1” thick plywood core, finish with matching (maple) chemical resistant high pressure plastic laminate and brush aluminum finish stainless steel tubes support. Detail , sheet A8. .
4. Provide Chicago Faucet 1300 series surface mounted electrical boxes where pedestal mounted electrical service is indicated.
2
Division 8: Doors and Xxxxxxx
Xxxxxx Xxxx
Xxxxxxx 00000: Aluminum Frames
Aluminum door and window frames Option A: Advanced Architectural Frame (AFF). Style: Venus. Throat 4-7/8” U.O.N. Finish: Clear Anodized aluminum. Option B: Series 318 by Western Integrated. Throat 4-7/8” U.O.N. Finish: Clear Anodized aluminum.
Section 08210: Wood Doors
I. Typical Interior Wood Door: Solid core wood door (3’-0” x 9’-0”) with maple wood face veneer for transparent finish. Typical door hardware to consist of: (2 pair) butts, latch sets at conference rooms and locksets at offices (Schlage D series), door stop (Xxxxx-Xxxxxxx FB-I3). All hardware finish to be: S626 satin chrome. Doors from the exterior and at the interior, which separate entry points from the office areas, will receive card access (designated CA on sheet PP-2.0).
II. Interior Glass Door when apply: ½” clear-frosted Herculite Glass Doors and glazing. All hardware finish to be: S626 satin chrome. Recessed top and bottom channels for glazing and hardware on doors.
Section 08305: Access Doors
I. Fire-Rated: Fire-resistive rated flush steel panel door & flanged frame, 1-1/2 hour rating, continuous hinge, self-latching & key-operated flush lock & gypsum board installations.
Lab Area
Section 08100: Wood Hollow Metal Doors & Frames:
I. Typical interior Wood Door: Solid core wood door (3’-0” x 9’-0”) with maple wood face veneer for transparent finish. All lab access doors required hardware locksets and vision-lite, U.O.N. Provide 10” S.S. kick plate at push side of all lab door.
-Optional interior Hollow Metal Door in Lab Area when required: 18 gauge face sheets, flush seamless steel, insulated. Prime and finish with epoxy paint. Fill voids with non-combustible, moisture resistant mineral insulation. Close top edge with continuous 16 ga. flush channel filler at All doors. All lab access H/M doors required hardware locksets and vision-lite, U.O.N. Provide 10” S.S. kick plate at push side of door. (Replace kick-plate with 36” armor-plate on lab door when required.)
II. Typical Hollow Metal Fames in all lab area: 16 gauge knock down units. Provide 3 rubber silencers at each door and 3 anchors per jamb and floor anchor each jamb; prime and finish with epoxy paint. Install glass stops on room side of frame.
Section 08800: Glazing
I. Glass types to be used include; ¼” clear tempered glass (office window), ¼” frosted tempered glass (office sidelights), ¼” clear or frosted tempered glass (at conference rooms). Extent and locations of glazing to be determined by tenants/architects.
II. Wired Glass at rated Corridor U.O.N.: ¼” thick, polished face with 24 B&W gauge wire arranged in baroque ‘square’ pattern.
3
Division 9: Finishes
Section 09250: Gypsum Board
Partitions and soffits as follows:
a. One hour partition: Partition Type I. Detail , sheet A8. .
b. Full height partitions (with insulation) at Conference Rooms: Partition Type .
c. Partition 6” Above Ceiling: Partition Type , Detail , sheet A8. Typical U.O.N.
d. Typical partition with 6 metal stud furring where noted on plans.
e. Soffits: 3-5/8” metal studs and 5/8” gyp. Board. Typical.
Section 09300: Toilet Room Ceramic Tile
Floor field tile: 2x2 Daltile D325 (Marble); floor accent tile: 2x2 Daltile Dl56 (Keystones)
Wall field tile: 4x4 Daltile 0140 (Silver Sage); wall accent tile: 4x4 Daltile 1452 (Cypress)
I. All Toilet Room tile: ANSI 317.1 Standard grade.
II. Provide bull-nose shapes at all free edges, corners where shown. Provide cove shapes at base & any other misc. shape needed for a complete installation that may not be shown or specified.
Section 09510: Acoustical Treatment
Acoustical ceilings as follows:
Office Area
a. CL-I: Suspended acoustical ceiling tile and grid in reception, partial hallway and private offices:
I. Tile: Xxxxxxxxx, Cirrus Second Look (white) 24” x 24” x 3/4”
II. Grid: Xxxxxxxxx Prelude Exposed Tee Grid System.
Ill. Remarks: Provide 4” compasso edge trim where specified. Where ceiling is held back from soffit (exposing structure above) Paint all walls, ductwork, piping, conduit, structure, etc., above ceiling.
b. CL-2: Suspended acoustical ceiling tile and grid at open office areas and partial hallway:
I. Tile: Xxxxxxxxx, Tundra (white) 24” x 48” x 5/8”
II. Grid: Xxxxxxxxx Prelude Exposed Tee Grid System.
c. CL-3: 5/8” gyp. Bd. Ceiling (see section 09900 for finishes in various location)
Lab Area
d. CL-4: Suspended acoustical ceiling tile and grid at lab area:
I. Tile: XXXXXX: Envirogard (No substitute) Vinyl Faced Lay-in Tile (white) 24” x 48”
II. Grid: Xxxxxxxxx Prelude Exposed Tee Grid System.
e. CL-5: Suspended acoustical ceiling tile in specialty lab area:
I. Tile: Gridstone: Vinyl Faced Lay-in Tile, Edge sealed, Clean room type low particle count (white) 24” x 48”
II. Grid: Xxxx, 1½” Lay-in Ceiling Grid Dx with gasket sealant around all edges
4
Section 09650: Resilient Flooring
Office Area
1. Lobby/Reception
Field: GenuWood II Vinyl Bonded (Maple)
Accent 1: Plynyl Bamboo (Brick)
Accent 2: Optional Porcelain Ceramic or Slate Tile
2. Break Room/Mail & Copy Room
Field: Forbo Linoleum: Marmoleum Real (3142 Umbra)
Accent 1: Forbo Linoleum: Marmoleum Fresco (3826 Canyon)
Accent 2: Forbo Linoleum: Artoleum Graphic (5311 Signo)
Optional 12”x12” VCT can be provided at Break, Copy/Mail room and Storage Rooms.
Color TBD. (Three color pattern: VCT-1, 2 and 3)
Lab Area
3. Lab Function Area:
Field: Mannington BioSpec Sheet Flooring (15164 New Glacier)
Accent: Mannington BioSpec Sheet Flooring (15161 Flax)
Optional 12”x12” VCT can be used when appropriate.
Field: Substitute with Mannington Brushwork (703 Ecru) 12”x12” title
Accent: Substitute with Mannington Brushwork (713 Florentine) 12”x12” title
Section 09685: Carpet
1. Carpet C- I: TBD.
2. Carpet C-2: TBD.
Section 09910: Painting
Note:
Paint finish
shall be:
Semi-gloss at cafeteria, coffee room, restroom, general wet lab and chemistry
lab; Epoxy paint finish to be used in biology lab, tissue-culture lab and
vivarium facility; Desco-Glaze finish to be used in cage-wash and glass-wash
area;
1. All other paint finish to be eggshell finish, U.O.N.
2. Paint P-1 (white) U.0.N:
3. Paint P-2 (accent color): TBD
4. Paint P-3 (accent color): TBD
5. Paint P-4 (accent color): TBD
6. Paint P-5 (accent color): XXX
0
Xxxxxxx 00000: Decorative Finishes
1. To be determined by tenants/architects and review with BioMed Realty Trust, Inc.
Division 10: Specialties
Section 10160 Toilet Partitions
1. Global Steel Products Corp. (or equal): Floor anchored toilet compartments stainless steel #4 satin finish
Section 10800 Toilet Accessories
1. TBD
Section 10999 Miscellaneous Specialties
Lab Area
1. |
Corner Guards: |
Bobrick: B-633, 18 ga. Stainless Steel, 3½” x 3½” x
full wall |
|
|
|
2. |
Projecting Wall Guards: |
Sani-Rail Wall Protection System with 4” wide
aluminum metal |
|
|
|
3. |
Face Mounted Wall Guards: (Optional) |
Construction Specialties: High impact acrylic vinyl,
C/S type |
|
|
|
4. |
Emergency Shower/ |
WaterSaver Faucet: Barrier-free Combination
Emergency |
Division 11: Equipment
Section 11132 (Tenant Options)
1. |
Motorized Front Projection Screens” Da-Lite Automatic Electric Projection Screen or equal |
|
|
Type: |
Director Electrol |
|
Size: |
Vary depend on size of room |
|
|
|
Section 11452: Coffee Room Equipment
1. Dishwasher: Asko #1385 Color/Finish: TBD
2. Garbage Disposal: In Sink Erator, Performance Plus Series, Model #77. Color: TBD
3. Sink: Elkay, GECR-2521-R 25” x 2 1-1/4” x 5-3/8” type 302 stainless steel with American standard “Ceramix” single handle faucet model 200 I . (Quantity 4).
4. Sink: Elkay, double bowl sink, type 302 stainless steel with American standard “Ceramix” single handle faucet model 2001. (Quantity 1). Pantry only.
6
Division 12: Furnishings
Section 12484: Floor Mat and Frames
1. Entry Mat: Pedimat: Xxxxx X0, All aluminum mill finish with SA I Serrated Aluminum Insert and ANG frame.
Section 12491: Window Treatment
1. New treatment at exterior window to match established building standards.
7
Division 15: Plumbing
Section 15000
1 Epoxy sink/faucet at lab benches: Epoxy cup sink to match work surface
(Furnish by lab cabinet vendor)
2. Lab sink accessories: (Furnish by Plumbing Contractor)
-Paper towel dispensers: Bobrick B-2621; locations as shown on drawings
-Drying rack: Epoxy resin with PVC pegs, Detail , sheet A8 .
-Water Saver Faucet TBD
Provide fittings with colored plastic disk identification tags to match existing.
a. Hot and Cold Water
b. Laboratory Water
c. Air, Vac, Gas
d. (and others when necessary)
Division 16: Electrical
Section 16130
1. WireMold: Open Space — Xxxxxx Poke-Thru Systems
Note: Tenants are required to provide Power/Data/Telecom poke-thru devices with flush trim under the center of conference table in each conference room.
Section 16500: Lighting
1. Refer to light fixture specifications for light fixture type.
8
Itemized Light Fixture Schedule
|
Light |
|
Light Fixture Description/Comments
|
|
Office Area |
||||
|
|
|
|
|
A |
|
Type: |
|
2’ x 2’ recessed direct/indirect fluorescent |
|
|
Manufacturer: |
|
Lightolier |
|
|
Model: |
|
Alter High Efficiency QHE2GPFOP224 |
|
|
Location: |
|
Private offices. |
|
|
|
|
|
B |
|
Type: |
|
Suspended Pendant Light |
|
|
Manufacturer: |
|
Lightolier (or equal) |
|
|
Model: |
|
EYP Series 35 Degree Louver with perforated side reflectors |
|
|
Location: |
|
Open Office Areas. |
|
|
|
|
|
C |
|
Type: |
|
2’ x 4’ recessed direct/indirect fluorescent |
|
|
Manufacturer: |
|
Lightolier |
|
|
Model: |
|
Alter High Efficiency QHE2GPFOP4FT |
|
|
Location: |
|
Hallway and corridor. |
|
|
|
|
|
D |
|
Type: |
|
Recessed wall washer fluorescent light fixture |
|
|
Manufacturer: |
|
Prescolite |
|
|
Model: |
|
CFW826EB-ST812 with white trim |
|
|
Location: |
|
At wall washer locations. |
|
|
|
|
|
E |
|
Type: |
|
Surface strip 1 x 4 Fluorescent light fixture. |
|
|
Manufacturer: |
|
Welimade (or equal) |
|
|
Model: |
|
204-248-2T8-SSB |
|
|
Location: |
|
Storage/equipment room |
|
|
|
|
|
F |
|
Type: |
|
Wall Sconces |
|
|
Manufacturer: |
|
Lightolier |
|
|
Model: |
|
Alter Soft Lights QVW8SPFOS2FT |
|
|
Location: |
|
At hallways and stairs locations. |
|
|
|
|
|
G |
|
Type: |
|
Optional Wall Sconces |
|
|
Manufacturer: |
|
Sistemalux |
|
|
Model: |
|
Blitz 2 Windows 180 (S.4063) |
|
|
Location: |
|
At hallways and stairs locations. |
|
|
|
|
|
|
|
Type: |
|
Optional Wall Sconces |
|
|
Manufacturer: |
|
Sistemalux |
|
|
Model: |
|
Fuse Wall (0890-HA-120) |
|
|
Location: |
|
At hallways and stairs locations. |
|
|
|
|
|
H |
|
Exit signage |
|
Edge-lit LED exit sign by Liteforms (DUAL LITE) |
9
Lab Area |
||||
|
||||
I |
|
Type: |
|
1’ x 4’ recessed direct/indirect fluorescent |
|
|
Manufacturer: |
|
Lightolier |
|
|
Model: |
|
Alter High Efficiency QHEIGPFOP232 |
|
|
Location: |
|
In general lab locations |
|
|
|
|
|
J |
|
Type: |
|
Recessed 1’ x 4’ Lay-in Fluorescent light fixture with seal gasket (in area required) |
|
|
Manufacturer: |
|
Kleenseal KTR 100 featherweight series |
|
|
Model: |
|
K-1-142-F32 G6 AP3-1 |
|
|
Location: |
|
In specialty lab locations |
10
Specialty Lab Finishes
1. |
Vivarium Facility: |
|
|
|
|
|
|
|
Floor: |
|
Versacolor aggregate filled polymer floor system, X-5 Series (or equal) (Multi-part epoxy resin/aggregate floor) |
|
Floor (alt. option): |
|
TBD |
|
Wall: |
|
Gyp. Bd. wall with epoxy paint finish |
|
Ceiling: |
|
CL-3: 5/8” gyp. Bd. Ceiling with epoxy paint finish. Service access panels to be located wherever required |
|
Casework: |
|
All caseworks in vivarium are to be metal with (LabTops or equal) 1” solid black epoxy countertop. |
|
Lighting: |
|
Recessed 1’x 4’ Lay-in Fluorescent light fixture with seal gasket (in area required) Manufacturer: Kleenseal KTR 100 featherweight series Model: K-1-142-F32 J6 AP3-1 |
|
|
|
|
2. |
Cage-wash Area |
|
|
|
|
|
|
|
Floor/Wall: |
|
Glass Fiber Reinforced epoxy, Tnemec System 280. |
|
Floor Pit: |
|
Xxxxxx Chemicals, U-Crete, HP-Q or Poly-Spec Flow Crete. |
|
Sewage Sumps: |
|
NovoRez 351: Epoxy wall/floor |
|
Ceiling: |
|
CL-3: 5/8” gyp. Bd. Ceiling with desco-glaze paint finish. Service access panels to be located wherever required |
|
Casework: |
|
All caseworks in cage-wash area are to be metal with (LabTops or equal) 1” solid black epoxy countertop. |
|
Lighting: |
|
Recessed 1’x 4’ Lay-in Fluorescent light fixture with seal gasket (in area required) Manufacturer: Kleenseal KTR 100 featherweight series Model: K-1-142-F32 J6 AP3-1 |
General Notes to all tenants
1. |
All tenants are to provide with new equipments/millwork Lab bench and casework. |
|
|
2. |
All lab equipment which required steam operation shall be self-generated. |
11
EXHIBIT B
GMP PROPOSAL
BMR-7 Graphics Drive LLC
00000 Xxxxxxxx Xxxxxx Xxxxx, Xxxxx 000
Xxx Xxxxx, Xxxxxxxxxx 00000
Phone: (000) 000-0000
Facsimile: (000) 000-0000
Xx. Xxxxx Xxxxxxx
Chief Financial Officer |
|
October 25, 2006 |
Linguagen Corporation
0000 Xxxxxxxx Xxxx.
Xxxxxxxx, XX 00000-0000
RE: 0 Xxxxxxxx Xxxxx, Xxxxx, XX
Dear Xxxxx:
As a follow up on our conversations and pursuant to our Lease Agreement, as amended, attached please find our Guaranteed Maximum Price (GMP) proposal for your review. Please find a summary of the anticipated costs and fees below:
Linguagen’s TI Estimate (per attached Basis of Estimate Summary) |
|
$ |
3,362,015 |
|
Less: Construction Contingency |
|
(146,407 |
) |
|
Subtotal |
|
3,215,608 |
|
|
BioMed Realty Trust Management Fee (3%) |
|
96,468 |
|
|
Guaranteed Maximum Price |
|
3,312,076 |
|
|
Estimated Design fees |
|
175,027 |
* |
|
Total Estimated TI Draw |
|
$ |
3,487,103 |
|
* To date, Linguagen has submitted documentation covering $163,586 of the estimated design fees
The above referenced amounts are subject to change per mutually agreed upon additive and deductive change orders incurred during the construction phase of this project. We look forward to initiating the construction phase of this project. Please call if you have questions or comments (000) 000-0000.
Sincerely,
/s/ Xxxxxxx X. Xxxxxx
Xxxxxxx X. Xxxxxx
Attachments:
· 1st Amendment to Linguagen Lease
· BioMed Standards & Finishes (Exhibit A)
· Guaranteed Maximum Price Proposal for BMR-Linguagen Protecs Proposal Number: 1297PAC06.1 Date of last modification 10/25/06 (Exhibit B)
Guaranteed Maximum
Price
Professional Turnkey |
|
Proposal for BMR - |
Engineering |
|
Linguagen |
and Construction |
|
Ewing, New Jersey |
Services |
|
|
ProTecs Proposal Number:
1297PAC06.I
Date of Issue: May 23, 2006
Revised: July 12, 2006
Revised: August 11, 2006
Modified: August 18, 2006
Revised: September 22, 2006
Modified: October 2, 2006
Modified: October 25, 2006
TABLE OF CONTENTS
1.0 |
|
EXECUTIVE SUMMARY |
|||
|
|
|
|
|
|
|
|
1.1 |
|
Overview |
|
|
|
1.2 |
|
Key Issues for Project Success |
|
|
|
1.3 |
|
Delivery Strategy |
|
|
|
|
|
|
|
2.0 |
|
PROJECT SCOPE |
|||
|
|
|
|
|
|
|
|
2.1 |
|
Architectural / Structural |
|
|
|
2.2 |
|
HVAC & Plumbing |
|
|
|
2.3 |
|
Electrical |
|
|
|
|
|
|
|
3.0 |
|
CLARlFICATIONS AND ASSUMPTIONS |
|||
|
|
|
|
|
|
4.0 |
|
COMMERCIAL TERMS |
|||
|
|
|
|
|
|
|
|
4.1 |
|
Guaranteed Maximum Price |
|
|
|
|
|
|
|
5.0 |
|
MILESTONE SCHEDULE |
|||
|
|
|
|
|
|
6.0 |
|
APPENDIX |
|||
|
|
|
|
|
|
|
|
6.1 |
|
Drawing / Document List |
|
|
|
6.2 |
|
ProTecs Project Team |
|
0000 Xxxxxx Xxxx Xxxx Xxxx XX. 00000
P: (000) 000-0000 F: (000) 000-0000
xxx.xxxxxxxxxx.xxx
2
BioMed Realty Trust has requested that ProTecs develop the Guaranteed Maximum Price ($GMP) proposal for the renovation project located at 0 Xxxxxxxx Xxxxx in Ewing, New Jersey, in order to accommodate their new tenant, Linguagen. This proposal was generated based on the Revision 2 drawings as prepared by Architecture Plus dated July 26, 2006 and Xxxxx Engineering drawings Revision 3 dated August 1, 2006. As part of this presentation, ProTecs has developed the following $GMP proposal for the described construction scope of work.
This project is based upon the fitout of approximately 17,500 square foot of new tenant space, within the existing shell area. This includes all structural, architectural, mechanical and electrical upgrades as denoted on the design documents for the new lab and office space to be occupied by Linguagen. A detailed description of the various systems upgrades follows. This project is to commence immediately, and will require an accelerated submittal and shop drawing review period, with construction activities starting in the middle of October 2006, with an anticipated completion by mid March 2007. ProTecs has included a preliminary construction schedule with this document.
This GMP proposal includes all management, supervision, equipment, labor, and materials for all construction field activities required to furnish and install systems as depicted on the bid documents identified above and noted in this document.
Following is a detailed description of our proposal including delivery strategy, component summary, proposed commercial terms, and a preliminary schedule.
1.2 Key Issues for Project Success
The successful delivery of a technically driven project is a complex endeavor. ProTecs is up to the challenge since this is our chosen area of expertise and daily practice. This project has multiple critical issues, which must be clearly addressed in order to achieve the programs objectives. The discussion, which follows, offers insights on a proposed project approach.
3
1.2.1 Quality
This project requires exceptional attention to detail in order to deliver a facility, which meets performance requirements and the necessary conformance and compliance requirements imposed on the project from federal, state, and local authorities. Our team is extensively skilled and knowledgeable of laboratory and related technologies and is capable of translating BioMed Realty Trust and Linguagen requirements into effective facility solutions.
ProTecs has successfully completed several hundred million dollars of pharmaceutical and laboratory facilities over the past few years; all of which have been successful in their achievement of business and technical objectives.
1.2.2 Speed
This project’s objectives must be accomplished within a fixed budget while being cognizant of calendar time. We have confidence in our abilities to successfully meet these objectives. This project is well within our capabilities to totally support, not only from a technical standpoint, but also from in-house resources. We believe having the right talent is essential to meeting this project’s need for timely achievement of deadlines. Since we are design/builders, we are routinely involved with speed critical projects and our entire team routinely works quickly and efficiently toward our clients’ objectives. This project is a good fit for our team. As ProTecs construction team is poised to support this challenging construction schedule.
1.2.3 Technology
Implementing sophisticated processing technologies within a challenging building environment for laboratory and safety compliance is a considerable design challenge. Only firms with extensive practical experience can achieve these technical objectives. ProTecs is up to the challenge. Our practice is specifically focused on pharmaceutical manufacturing and laboratory projects. During the last fourteen years we have been involved with many multiple product manufacturing facilities and pilot plants, as well as a full range of design, build, and validation assignments of laboratory facilities. Our
4
staff is deeply skilled and experienced in these endeavors and we have truly relevant experience and knowledge to bring to this project.
Our team of in-house expert staff will review the existing design documents for constructability, cost effectiveness and commissioning aspects throughout the bidding and construction process. This project is a great opportunity for ProTecs to demonstrate our skills and commitment.
1.2.4 Leadership
Achieving technical and business objectives for this project requires teamwork. Tight coordination, clear responsibilities, and excellent communication are essential on this project if we are to achieve its goals and meet the challenges ahead. ProTecs understands these dynamics and has demonstrated success in becoming a vital part of owner’s teams under these demanding circumstances. We are leaders in our field and have an excellent grasp of our role and responsibilities on this project. We pledge our total corporate commitment on this project. Decisions will be streamlined and support will be solid and timely. We will share all decisions with a strong sense of professionalism and purpose, and are prepared to work with Architecture Plus and Xxxxx Engineering to streamline and expedite the submittal review process.
Based on the information provided and the pre-bid walk through of the site, ProTecs recommends that BMR / Linguagen use the methodology below to deliver this project. ProTecs believes that a three phase approach will work best. We believe proceeding in the fashion outlined below will lead to the most cost effective and timely delivery of this project.
Phase 1 Consists of procuring all long lead equipment, and expediting all submittals and shop drawings in order to allow for timely deliveries.
5
Phase 2 ProTecs will execute construction activities in an expeditious manner. This includes all underground piping, exterior wall modifications, structural modifications, MEP and HVAC rough-in, architectural finishes, installation of equipment and casework, and modifications to existing systems.
Phase 3 This phase consists of ProTecs performing system start-up and commissioning, final punchlist, inspections, and allowing BMR / Linguagen to move furniture and equipment into the newly renovated areas. System start up and commissioning will be completed prior to CO being issued.
6
· Remainder of demolition not completed by THG Builders.
· Sawcutting of floor and restoration to accommodate underground piping and new footing installation for new mezzanine.
· Sawcut and restoration of parking lot for new emergency generator utility trench. New pads/supports for new generator and relocated, existing chiller.
· Modifications to existing exterior wall for new windows and glazing, including needle beam and supports. New storefront doors as shown.
· Relocation of existing stairs to existing mezzanine area.
· New structural mezzanine as depicted.
· Structural framing and reinforcing for new HVAC equipment and penetrations.
· New walls including framing and drywall, and new doors, frames and hardware.
· New ceiling systems (GWB & Acoustical) and supports as depicted.
· New flooring, including vinyl, ceramic tile, carpet and epoxy flooring as shown.
· New laboratory casework and hoods.
· New millwork, accessories and partitions for bathroom and galley areas.
· All interior painting and finishes.
· Roofing cutting and patching for new work, including sealing of penetrations.
· Sanitary and vent piping as depicted in design documents.
· New piping systems including cold water, hot water, natural gas, lab compressed air.
· New plumbing fixtures as shown, including laboratory sinks.
· Chilled water and hot water piping systems as depicted, including pumps and tanks.
· New HVAC duct systems, including all dampers and diffusers.
· Furnish and install of new boiler, pumps, coils, fans, rooftop units and air handling units.
· Demolition of existing and supply / install of new chiller.
· Automatic Temperature Controls and balancing of the air and hydronic systems is included in this scope.
7
· Installation and calculations for new sprinkler system, including modifications to existing system.
· Power feeders, wiring and conduit to new and relocated HVAC equipment.
· Power feeders, wiring and conduit for new receptacles and devices.
· Electrical wiring and fixtures as depicted on lighting plans.
· Fire devices and a working system as shown on drawings and specifications.
· Furnish and install new panel boards and distribution panels.
· Furnish and install new emergency generator, including underground feeds.
8
3.0 CLARIFICATIONS AND ASSUMPTIONS
The following represents a list of assumptions and clarifications used in preparation of the estimate. It is noted that there may be adjustments to the Estimate required based on the scope increase or decrease by the revised documents and/or any changes to the following assumptions and clarifications:
· This proposal and all contents expressed herein are confidential and privileged, and cannot be disclosed to parties outside of ProTecs and BioMed Realty Trust without the specific written permission of ProTecs. Dissemination, distribution, or copying of this document, or any portion thereof by any party other than ProTecs is strictly prohibited.
· ProTecs general conditions include costs associated with the Supervision and Management of procurement and construction activities through out the duration of the project. The proposal is based on the work schedule attached hereto and milestone dates identified therein. Any work associated with General Conditions extending beyond the schedule indicated due to revisions directed by the owner are not included.
· Fee is shown as a percentage of costs only for the overall presentation of the costs. It remains to be a fixed amount for the given scope whether there are cost savings on the project or otherwise. The fee for Owner requested additional work will be calculated at the same percentage basis. If the project scope increases, the fee and overhead also increase either at the same percentage rate as the shown in the estimate breakdown or on the basis of requirements dictated by the project schedule and job conditions–whichever is applicable.
· ProTec services will be provided with a standard of care similar to other professional service firms providing these services within the region.
· There are neither Design nor Validation Scopes of Work included in the attached $GMP Estimate.
· The state and local sales taxes are excluded for the project and equipment (ProTecs or Owner furnished) item (all assumed to be non-taxable — the owner is to provide required exemption forms).
· The building permit was submitted by others but will be paid for by ProTecs. The cost has been included in the $GMP.
· Builders risk insurance is by BioMed Realty Trust. The deductible limited for ProTecs will be $5,000.
· Payment and performance bonds costs are not included. These can be added to the overall budget if requested by the Owner.
9
· The estimate is based on working during normal hours, between 7:00 AM and 3:30 PM, during the week, Monday through Friday with the exception of utility tie-into existing systems. Tie-in work is anticipated to be done during off hours. No additional shift work or overtime has been included.
· The construction is based on the known code requirements. Any requirements above and beyond these standards that may be required by the Owner’s insurance provider are not included as part of this work. ProTecs has included costs only for those items clearly designed and depicted/defined on the contract drawings. Additional code requirements by the insurance carrier, township, etc. are not included. ProTecs expects the design to reflect and show all code requirements, and “implied” code items are not included.
· All unit costs identified as “ALLOW’ or “ALLOWANCE ITEM” represent an allowance for that particular line item that is the maximum financial responsibility of ProTecs within the estimate. Any costs for any line item with unit cost of in excess of the indicated amount is not included.
· A dedicated fire watch service during the construction process is not included.
· ProTecs has included rigging, handling and freight costs only for those items, which are listed to be furnished by ProTecs and their subcontractors.
· Factory/Shop Inspections and tests by ProTecs are not included.
· Site security, temporary site lighting other than for emergency egress and construction activities, etc. during the course of construction, is not included.
· Utilities:
· ProTecs assumes that all the existing utilities to which we are tying into are functioning properly and will remain fully functional, and not be clogged, blocked or require modification beyond what is indicated on the Owner furnished documents.
· It is assumed that the size/capacity/pressure of the existing utilities are adequate, are in acceptable condition, and working properly.
· The estimate does not include any remedial work to existing systems, unless otherwise shown.
· Landscaping is not included.
· Subsurface investigation is excluded. It is assumed that any unknown underground utilities, tanks, structures etc. that need to be removed or modified will be the responsibility of the Owner. Electronic scanning of the building slab is included.
· Removal of hazardous material such as asbestos, lead paint, PCB, radio active material, potent dust laden equipment, devices and utilities, underground tanks, etc. is not included. These materials have to be addressed if and when encountered during the course of the work. Unless otherwise indicated, ProTecs has not included any special construction to house hazardous, solvent, or flammable substances.
· Temporary fencing for “lay-down” areas or site storage areas is not included in this estimate unless required by ProTecs.
10
· Temporary lay down areas are assumed within the building and in the parking space in the back of the building
· Environmental services including permitting and monitoring/addressing of air and waste discharges are not included unless stated otherwise in the estimate. Any wastewater treatment systems are excluded and have been discounted from the $GMP. ProTecs is carrying a lime item for air and waste water assessment to be done by Xxx Xxxxx. This is a place holder for the sum of money and the service will be contracted by the owner directly.
· Trade remobilization other than what is required by the project schedule and associated staging and phasing is not included. Unscheduled Project Shutdowns (other than the ones spelled out in the project schedule) are not included from this estimate. ProTecs assumes all work will occur simultaneously.
· ProTecs has included fire extinguisher cabinets and fire extinguishers as shown.
· Room signage is included, where shown.
· ProTecs has included $2,500 for window treatments and blinds. None have been specified yet, but will comply with building standards.
· Supply, install and utility hook-up of office furniture and cubicles are excluded from this estimate. The power wire has been included to a junction box as specified on the drawings. The actual furniture hook up from the box to the furniture is by others.
· Enclosure/screen wall to conceal the exterior mechanical/electrica1 equipment from the view is not included.
· Painting of exterior gas piping per specification has been included. No other exposed utilities will be painted.
· Steel testing, e.g. visual field welding and bolt torquing is included in accordance with the structural drawings. Any testing of metals for strength including x-ray testing for welds is not included.
· Spray fireproofing of the steel structure is not included.
· Room Particulate and Pressure Monitoring systems are not included.
· Temporary heating may be needed and would be billed on a cost plus basis. 3 months of temporary heating has been included in the $GMP. Utilities will be paid by the owner.
· Intercom system is excluded.
· Telecommunication system is excluded. Raceway conduit from a wall back box to the ceiling plenum is included. All other raceway systems have been excluded. It is understood that the owner will be contracting with the same contractor as the apparent low bidder for the electric and the work will be conducted at the same time as the general construction. ProTecs will coordinate the installation of the telecommunications wire.
· New neutralization pit installation and associated concrete is excluded and has been credited to the $GMP.
· Sprinkler system is assumed to have adequate capacity. Replacement of standpipes,
11
sprinkler mains, and main fire protection components are not included. No sprinkler work in the Warehouse Space is included. Sprinkler coverage is provided in the labs, office and cleanroom areas (as indicated on the drawings). Sprinklers will be installed in a symmetrical pattern but not necessarily in the center of all ceiling tiles. New hydraulic calculations are included. (add $9500 for center of tile installation)
· Adequate and approved water supply to support the demand of the potable water system is available and furnished by others.
· CCTV is not included
· ProTecs has included cost for the Ar and N2 lab gas piping as shown on the fax from architecture plus dated May 12, 2006, and now included in the revised contract drawings. ProTecs excludes CO2 piping from this scope.
· The space currently has lighting high in the space. This lighting is assumed to remain. Where the lighting is over unfinished areas like the warehouse, the existing lighting will remain and be used to light the area. Where lighting is installed over a finished area the lighting will be recircuited so that they can be turned off.
· The $GMP clarifications and assumptions are to be used in conjunction with the plans and specifications. They are meant to fill in gaps in the scope documents and clarify “Catch All Phrases”.
· Compressed air filter certifications are not included. Fume hoods and HEPA filter certifications are excluded.
· ProTecs included the RO/DI water systems but not the Millipore units or final polishing units. This is based upon the HYDRO quote 405S11-0 dated Aug. 10, 2006 provided to us by owner.
· The proposal is based on the work schedule attached hereto and milestone dates identified therein. Schedule will be provided in Primavera format after contract is awarded.
· The contingency is exclusively meant to pay for all the cost associated with estimating variances. The purpose of the contingency, however, is not to pay for additional work requests or scope adjustments by the Owner or cost associated with force majeure (i.e. Acts of God, labor strife, strikes, etc.). Linguagen will have the right to view all cost associated with the contingency line item. No funds identified as contingency will be expended without authorization of the owner. In an effort to maintain schedule both verbal and written forms of authorization via phone, fax and e-mails will be acceptable. All approvals will be followed up in writing.
· ProTecs’ standard one-year warranty on labor and materials are provided. Any standard manufacturers extended warranties and guarantees will be passed along to either/or both BMR and Linguagen. Any additional warranty requirements beyond these terms have not been included in this $GMP and could be purchased direct by either BMR or Liguagen. Any equipment/system failure due to lack of proper maintenance is excluded
12
from ProTecs responsibility.
· Our proposal is based on mutually agreed terms and contract documents. ProTecs assumes terms similar to our previous construction project would be enforced.
· We have not included any allowance for cost impacts or escalation in regard to the current issues with shortages of steel and related products, materials, and equipment (steel, reinforcing bar, conduit, piping, chiller, boiler, electrical gear, etc.). Any cost impacts related to this issue past the $GMP guarantee date of 10/09/2006 will be addressed as an adjustment to the project scope, as necessary.
· Construction schedule is based on no delays due to weather, municipal permits, or inspections.
· Installation of the telephone/data and PA systems are not included. ProTecs has carried $26,000.00 for security and card reader systems based upon quote received from the preferred vendor.
· ProTecs assumes vacuum pumps are by tenant, and are not included.
· ProTecs has excluded laboratory equipment noted in table on drawings CW-1 and CW-2, with exception to the fumehoods (F4-1, F4-2, F4-3) and Jamestown safety cabinet (PL- 5) which are included.
· ProTecs has included $47,000 for one (1) Getinge steam sterilizer Model 422LS based upon a quote PH0306-010 dated March 1, 2006 supplied by the owner. ProTecs has not included interconnect of components and installation of factory supplied loose components due to limited information. Setting of the steam sterilizer is included.
· ProTecs has included $26,883 plus $1200 for install by factory rep. for one (1) Lancer 1400 UP glasswasher with Basic Basket based on a quote 1403-06-03 dated March 1, 2006 provided by the owner. ProTecs has not included interconnect of components and installation of factory supplied loose components due to limited information. Setting of the glasswasher is included. No Jet Racks have been included in this $GMP.
· It is understood the existing building shell will be of adequate construction to support the mechanical. electrical and architectural systems to be fumished under this scope of work and that no supplemental steel, other than that shown on the current plans, will be required.
· Millwork is fabricated in open-shop environment.
· No paint above ceiling; firetape only.
· ProTecs has not included exterior signage. ProTecs has only included interior signage for bathrooms. Interior room signs are not included.
· ProTecs does not include repair to existing MEP insulation.
· ProTecs will patch existing vapor barrier and install new where disturbed. ProTecs does not include welding new barrier to existing.
· No warranty of guarantee of existing MEP systems is implied or given.
· Balancing of HVAC systems is included however; ProTecs excludes any specific
13
fumehood testing (ASHRAE 100 etc.,).
· ProTecs has not included sprinkler coverage in ductwork or within fumehoods.
· Any escalation due to market conditions from our proposal expiration date has not been included in this $GMP.
· Revised structural drawings were not provided. This proposal is based upon ProTecs using conventional means and methods to shore the outside wall in lieu of the depicted shoring system on the drawings. In addition, as previously stated the waste neutralization pit will not be installed.
· ProTecs will coordinate pressure requirements with the subcontractor for the gas meter upgrade to ensure proper pressure is supplied.
· The (5) year compressor, parts only warranty is included.
· Removal of existing chiller pier foundations is included. Patching of paving is also included.
· Supply and install of new 105 ton chiller (carrier) has been included in the $GMP. Removal and disposal of existing chiller by others.
· Setting of gas meters is by PSEG contracted by owner or payee of service.
14
4.0 COMMERCIAL TERMS
ProTecs proposes to provide the above-described professional construction services for a guaranteed maximum price of Three Million Seven Hundred Ninety Six Thousand and Thirty Eight Dollars ($3,796,038.00).
Work can commence immediately upon receiving written authorization to proceed or a purchase order. Our services will be invoiced monthly based on the percent of completion and are payable upon receipt. A division breakdown for these costs is provided within the attached estimate.
This proposal is valid until October 3lst, 2006. If the services of ProTecs do not commence, or are stopped for a period of thirty (30) days through no act or fault of ProTecs, ProTecs may elect to renegotiate the terms of this agreement to reflect changes in project scope, schedule and fee schedules.
Any changes made to this proposal do not constitute an agreement. Both parties in writing must approve all changes. If you accept this proposal, please sign one copy and return it to ProTecs.
PROTECS, INC. |
|
|
ACCEPTED BY: |
|||
PROTECS PROPOSAL NO.: 1297PAC06.1rev.4c BioMed Realty Trust |
|
|
||||
|
|
|
||||
/s/ Xxxxxxxxxxx X. XxXxxxx |
|
|
||||
Xxxxxxxxxxx X. XxXxxxx |
|
|
||||
Principal |
|
Date: |
|
|||
15
BIOMED
REALTY TRUST - LINGUAGEN
EWING, NJ
BASIS OF ESTIMATE
SUMMARY
|
|
|
|
TOTAL |
|
|
|
|
|
|||
|
|
|
|
ESTIMATED |
|
TOTAL COST |
|
TOTAL COST |
|
|||
DIVISION |
|
DESCRIPTION |
|
COSTS |
|
(LINGUAGEN) |
|
(BMR) |
|
|||
01 |
|
GENERAL CONDITIONS |
|
$ |
231,151 |
|
$ |
195,478 |
|
$ |
34,673 |
|
02 |
|
SITE WORK |
|
$ |
141,350 |
|
$ |
118,050 |
|
$ |
23,300 |
|
03 |
|
CONCRETE |
|
$ |
84,200 |
|
$ |
78,700 |
|
$ |
5,500 |
|
04 |
|
MASONRY |
|
$ |
34,800 |
|
$ |
0 |
|
$ |
34,800 |
|
05 |
|
METALS |
|
$ |
407,600 |
|
$ |
172,300 |
|
$ |
235,300 |
|
|
|
Alternate #1 Provide Alternate Steel Shoring |
|
$ |
(139,000 |
) |
|
|
$ |
(139,000 |
) |
|
06 |
|
CARPENTRY |
|
$ |
43,710 |
|
$ |
36,954 |
|
$ |
6,756 |
|
07 |
|
THERMAL & MOISTURE PROTECTION |
|
$ |
42,070 |
|
$ |
38,570 |
|
$ |
3,500 |
|
08 |
|
DOORS AND WINDOWS |
|
$ |
110,025 |
|
$ |
52,430 |
|
$ |
57,595 |
|
09 |
|
FINISHES |
|
$ |
498,223 |
|
$ |
498,223 |
|
$ |
0 |
|
10 |
|
SPECIALTIES |
|
$ |
1,000 |
|
$ |
1,000 |
|
$ |
0 |
|
11 |
|
EQUIPMENT |
|
$ |
0 |
|
$ |
0 |
|
$ |
0 |
|
12 |
|
FURNISHINGS |
|
$ |
224,346 |
|
$ |
224,346 |
|
$ |
0 |
|
13 |
|
SPECIAL CONSTRUCTION |
|
$ |
0 |
|
$ |
0 |
|
$ |
0 |
|
14 |
|
CONVEYING SYSTEMS |
|
$ |
0 |
|
$ |
0 |
|
$ |
0 |
|
15 |
|
MECHANICAL |
|
$ |
1,139,463 |
|
$ |
1,129,963 |
|
$ |
9,500 |
|
|
|
Alternate #1 - Add for Underground Sanitary Line |
|
$ |
12,000 |
|
$ |
0 |
|
$ |
12,000 |
|
|
|
Alternate #2 - Add or 3 months of Temp, Heat |
|
$ |
16,000 |
|
$ |
16,000 |
|
$ |
0 |
|
16 |
|
ELECTRICAL |
|
$ |
486,935 |
|
$ |
410,485 |
|
$ |
76,450 |
|
17 |
|
PROCESS |
|
$ |
0 |
|
$ |
0 |
|
$ |
0 |
|
|
|
|
|
|
|
|
|
|
|
|||
81 |
|
INSURANCE & WARRANTY |
|
$ |
36,171 |
|
$ |
30,745 |
|
$ |
5,426 |
|
81 |
|
PERMITS |
|
$ |
27,100 |
|
$ |
23,035 |
|
$ |
4,065 |
|
|
|
Alternate #1 - Add for Wastewater Permits |
|
$ |
4,500 |
|
$ |
0 |
|
$ |
4,500 |
|
82 |
|
COMMISSIONING |
|
$ |
10,000 |
|
$ |
8,000 |
|
$ |
2,000 |
|
83 |
|
ENGINEERING AND DESIGN |
|
$ |
0 |
|
$ |
0 |
|
$ |
0 |
|
84 |
|
OVERHEAD/FEE |
|
$ |
212,150 |
|
$ |
180,328 |
|
$ |
31,823 |
|
85 |
|
VALIDATION |
|
$ |
0 |
|
$ |
0 |
|
$ |
0 |
|
|
|
CURRENT TOTAL |
|
$ |
3,623,794 |
|
$ |
3,215,608 |
|
$ |
408,187 |
|
|
|
|
|
|
|
|
|
|
|
|||
80 |
|
CONTINGENCY |
|
$ |
172,244 |
|
$ |
146,407 |
|
$ |
25,837 |
|
|
|
|
|
|
|
|
|
|
|
|||
|
|
GMP Total w/ Contingency |
|
$ |
3,796,038 |
|
$ |
3,362,015 |
|
$ |
434,023 |
|
PROTEC, INC. |
|
BIOMED REALTY TRUST - LINGUAGEN |
ESTIMATING |
|
EWING, NJ |
|
|
DETAILED ESTIMATE |
COST CODE |
|
DESCRIPTION |
|
QUANTITY |
|
UNIT |
|
UNIT COST |
|
SUBTOTAL |
|
TOTAL COST |
|
TOTAL COST |
|
|
|
||||
01-000000 |
|
GENERAL CONDITIONS |
|
|
|
|
|
|
|
$ |
0 |
|
|
|
|
|
|
|
|||
00-000000 |
|
Telephone - Toll Calls |
|
5 |
|
MO |
|
$ |
250.00 |
|
$ |
1,250 |
|
$ |
1,063 |
|
$ |
185 |
|
Pro-Rated |
|
01-005000 |
|
Computers/Network |
|
5 |
|
MO |
|
$ |
100.00 |
|
$ |
500 |
|
$ |
425 |
|
$ |
75 |
|
Pro-Rated |
|
01-006000 |
|
Reimbursables |
|
5 |
|
MO |
|
$ |
1,600.00 |
|
$ |
8,000 |
|
$ |
6,800 |
|
$ |
1,200 |
|
Pro-Rated |
|
01-025000 |
|
Safety |
|
5 |
|
MO |
|
$ |
650.00 |
|
$ |
3,250 |
|
$ |
2,783 |
|
$ |
488 |
|
Pro-Rated |
|
01-038000 |
|
Pre-Construction Coordination |
|
1 |
|
LS |
|
$ |
12,600.00 |
|
$ |
12,500 |
|
$ |
10,825 |
|
$ |
1,875 |
|
Pro-Rated |
|
01-039000 |
|
Pre-Construction Estimating |
|
1 |
|
LS |
|
$ |
16,101.00 |
|
$ |
16,101 |
|
$ |
13,685 |
|
$ |
2,415 |
|
Pro-Rated |
|
01-041000 |
|
Construction Project Coordination |
|
1 |
|
LS |
|
$ |
7,500.00 |
|
$ |
7,500 |
|
$ |
6,375 |
|
$ |
1,125 |
|
Pro-Rated |
|
01-047000 |
|
Superintendant |
|
21 |
|
WKS |
|
$ |
3,800.00 |
|
$ |
79,800 |
|
$ |
67,830 |
|
$ |
11,970 |
|
Pro-Rated |
|
01-048000 |
|
Project Manager |
|
22 |
|
WKS |
|
$ |
2,060.00 |
|
$ |
45,100 |
|
$ |
38,335 |
|
$ |
8,765 |
|
Pro-Rated |
|
01-049000 |
|
Clerical Support |
|
22 |
|
WKS |
|
$ |
350.00 |
|
$ |
7,700 |
|
$ |
6,545 |
|
$ |
1,155 |
|
Pro-Rated |
|
01-057000 |
|
Project Engineer (Home) |
|
22 |
|
WKS |
|
$ |
2,100.00 |
|
$ |
46,200 |
|
$ |
39,270 |
|
$ |
6,930 |
|
Pro-Rated |
|
01-305000 |
|
Drawings and Prints |
|
5 |
|
MO |
|
$ |
250.00 |
|
$ |
1,250 |
|
$ |
1,063 |
|
$ |
188 |
|
Pro-Rated |
|
01-306100 |
|
Counter and Postage |
|
5 |
|
MO |
|
$ |
200.00 |
|
$ |
1,000 |
|
$ |
850 |
|
$ |
150 |
|
Pro-Rated |
|
01-775000 |
|
Punch Lists |
|
1 |
|
LS |
|
$ |
1,000.00 |
|
$ |
1,000 |
|
$ |
850 |
|
$ |
150 |
|
Pro-Rated |
|
|
|
GENERAL CONDITIONS SUBTOTAL |
|
|
|
|
|
|
|
$ |
231,151 |
|
$ |
196,475 |
|
$ |
34,673 |
|
|
|
|
|
|
DIVISION 2 - SITEWORK |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||
02-000000 |
|
SITE WORK |
|
|
|
|
|
|
|
$ |
0 |
|
|
|
|
|
|
|
|||
02-002000 |
|
Dumpsters General |
|
20 |
|
EA |
|
$ |
650.00 |
|
$ |
13,000 |
|
$ |
13,000 |
|
$ |
0 |
|
|
|
02-002000 |
|
Dumpsters - Concrete and Demolition |
|
3 |
|
EA |
|
$ |
850.00 |
|
$ |
2,550 |
|
$ |
2,550 |
|
$ |
0 |
|
|
|
02-003000 |
|
Cleaning/Laborer |
|
5 |
|
MO |
|
$ |
5,000.00 |
|
$ |
25,000 |
|
$ |
21,250 |
|
$ |
3,750 |
|
Pro-Rated |
|
02-004000 |
|
Temporary Protection |
|
1 |
|
LS |
|
$ |
3,500.00 |
|
$ |
3,500 |
|
$ |
3,500 |
|
$ |
0 |
|
|
|
02-004100 |
|
Temporary Enclosure (outside wall) |
|
1 |
|
LS |
|
$ |
6,800.00 |
|
$ |
5,800 |
|
$ |
0 |
|
$ |
5,800 |
|
|
|
02-004200 |
|
Temporary Floor Protection |
|
1 |
|
LS |
|
$ |
2,500.00 |
|
$ |
2,500 |
|
$ |
2,500 |
|
$ |
0 |
|
|
|
02-006000 |
|
Field Office |
|
5 |
|
MO |
|
$ |
800.00 |
|
$ |
4,000 |
|
$ |
3,400 |
|
$ |
800 |
|
Pro-Rated |
|
02-007000 |
|
Sanitary Facilities |
|
20 |
|
WKS |
|
$ |
150.00 |
|
$ |
3,000 |
|
$ |
2,560 |
|
$ |
450 |
|
Pro-Rated |
|
02-013000 |
|
Final Cleaning |
|
1 |
|
LS |
|
$ |
12,000.00 |
|
$ |
12,000 |
|
$ |
10,200 |
|
$ |
1,500 |
|
Pro-Rated |
|
02-015000 |
|
Small Tools and Equipment |
|
1 |
|
LS |
|
$ |
3,500.00 |
|
$ |
3,500 |
|
$ |
2,975 |
|
$ |
825 |
|
Pro-Rated |
|
02-210000 |
|
Subsurface Investigation of Floor |
|
1 |
|
LS |
|
$ |
3,000.00 |
|
$ |
3,000 |
|
$ |
3,000 |
|
$ |
0 |
|
|
|
02-999000 |
|
Scaffolding and Platforms |
|
1 |
|
LS |
|
$ |
52,500.00 |
|
$ |
82,500 |
|
$ |
53,125 |
|
$ |
9,375 |
|
Pro-Rated |
|
|
|
SITE WORK SUBTOTAL |
|
|
|
|
|
|
|
$ |
141,350 |
|
$ |
118,050 |
|
$ |
23,300 |
|
|
|
|
|
|
DIVISION 3 - CONCRETE |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||
03-000000 |
|
CONCRETE |
|
1 |
|
LS |
|
$ |
89,000.00 |
|
$ |
69,000 |
|
$ |
68,500 |
|
$ |
0 |
|
|
|
03-000001 |
|
Slab cut and replace at 5 Line/D.58 E, and 5 Line/ D.5 and E |
|
|
|
|
|
|
|
|
|
$ |
0 |
|
$ |
500 |
|
|
|
||
03-999999 |
|
Remove Neutralization Pit |
|
1 |
|
LS |
|
$ |
(9,800.00 |
) |
$ |
(9,800 |
) |
$ |
(9,800 |
) |
$ |
0 |
|
|
|
03-999999 |
|
Demolition of Existing Chiller Pad and Foundation |
|
1 |
|
LS |
|
$ |
5,000.00 |
|
$ |
5,000 |
|
$ |
0 |
|
$ |
5,000 |
|
|
|
|
|
CONCRETE SUBTOTAL |
|
|
|
|
|
|
|
$ |
84,2000 |
|
$ |
78,780 |
|
$ |
5,500 |
|
|
|
|
|
|
DIVISION 4 - MASONRY |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||
04-000000 |
|
MASONRY |
|
1 |
|
LS |
|
$ |
34,800.00 |
|
$ |
34,800 |
|
$ |
0 |
|
$ |
34,800 |
|
|
|
04-000001 |
|
Shoring of Outside wall |
|
1 |
|
LS |
|
Included |
|
|
|
$ |
0 |
|
included in Above |
|
|
|
|||
|
|
MASONRY SUBTOTAL |
|
|
|
|
|
|
|
$ |
34,8000 |
|
$ |
0 |
|
$ |
34,800 |
|
|
|
|
|
|
DIVISION 5 - METALS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||
05-000000 |
|
Misc. METALS |
|
1 |
|
LS |
|
$ |
170,600.00 |
|
$ |
170,600 |
|
$ |
170,600 |
|
$ |
0 |
|
|
|
05-000001 |
|
Windbracing and tube lintels along E line |
|
1 |
|
LS |
|
$ |
235,000.00 |
|
$ |
235,000 |
|
$ |
0 |
|
$ |
235,000 |
|
|
|
05-550000 |
|
Stair Treads and Nosings |
|
0 |
|
LS |
|
$ |
9,900.00 |
|
$ |
0 |
|
$ |
0 |
|
$ |
0 |
|
|
|
05-990000 |
|
Structural Submittal/RFI’s |
|
1 |
|
LS |
|
$ |
2,000.00 |
|
$ |
2,000 |
|
$ |
1,700 |
|
$ |
300 |
|
Pro-Rated |
|
|
|
METALS SUBTOTAL |
|
|
|
|
|
|
|
$ |
407,600 |
|
$ |
172,300 |
|
$ |
235,000 |
|
|
|
|
|
|
DIVISON 6 - CARPENTRY |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||
06-000000 |
|
CARPENTRY |
|
0 |
|
LS |
|
$ |
0.00 |
|
$ |
0 |
|
|
|
|
|
|
|
||
06-220000 |
|
Millwork |
|
1 |
|
LS |
|
$ |
36,954.00 |
|
$ |
36,954 |
|
$ |
36,954 |
|
$ |
0 |
|
|
|
06-220001 |
|
Add Corian Tops |
|
1 |
|
LS |
|
$ |
6,758.00 |
|
$ |
8,756 |
|
$ |
0 |
|
$ |
6,756 |
|
|
|
|
|
CARPENTRY SUBTOTAL |
|
|
|
|
|
|
|
$ |
43,710 |
|
$ |
36,954 |
|
$ |
6,758 |
|
|
|
|
|
|
DIVISION 7 - THERMAL AND MOISTURE PROTECTION |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||
07-000000 |
|
THERMAL & MOISTURE PROTECTION |
|
0 |
|
LS |
|
$ |
0.00 |
|
$ |
0 |
|
|
|
|
|
|
|
||
07-500200 |
|
Roofing With Flashing |
|
1 |
|
LS |
|
$ |
38,570.00 |
|
$ |
38,570 |
|
$ |
38,570 |
|
$ |
0 |
|
|
|
07-824000 |
|
Sealants for exterior Windows |
|
1 |
|
LS |
|
$ |
3,500.00 |
|
$ |
3,500 |
|
$ |
0 |
|
$ |
3,500 |
|
|
|
|
|
THERMAL AND MOISTURE PROTECTION SUBTOTAL |
|
|
|
|
|
|
|
$ |
42,070, |
|
$ |
38,570 |
|
$ |
3,500 |
|
|
|
|
|
|
DIVISON 8 - DOORS AND WINDOWS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||
08-000000 |
|
DOORS AND WINDOWS |
|
0 |
|
LS |
|
$ |
0.00 |
|
$ |
0 |
|
|
|
|
|
|
|
||
08-100100 |
|
Doors |
|
1 |
|
LS |
|
$ |
42,250.00 |
|
$ |
42,250 |
|
$ |
42,250 |
|
$ |
0 |
|
|
|
08-111000 |
|
H M Steel Doors and Frames |
|
1 |
|
LS |
|
$ |
0.00 |
|
INCLUDED |
|
$ |
0 |
|
$ |
0 |
|
|
|
|
08-800000 |
|
Glazing Interior |
|
1 |
|
LS |
|
$ |
10,180.00 |
|
$ |
10,180 |
|
$ |
10,160 |
|
$ |
0 |
|
|
|
08-800001 |
|
Glazing Exterior |
|
1 |
|
LS |
|
$ |
57,585.00 |
|
$ |
57,595 |
|
$ |
0 |
|
$ |
57,595 |
|
|
|
|
|
DOORS AND WINDOWS SUBTOTAL |
|
|
|
|
|
|
|
$ |
110,025 |
|
$ |
52,430 |
|
$ |
57,595 |
|
|
|
|
|
|
DIVISION 9 - FINISHES |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||
09-000000 |
|
FINISHES |
|
1 |
|
LS |
|
$ |
326,353.00 |
|
$ |
325,353 |
|
$ |
326,353 |
|
$ |
0 |
|
|
|
09-310000 |
|
Ceramic Tile |
|
1 |
|
LS |
|
$ |
25,400.00 |
|
$ |
26,400 |
|
$ |
26,400 |
|
$ |
0 |
|
|
|
09-653100 |
|
VCT |
|
1 |
|
LS |
|
$ |
50,830.00 |
|
$ |
50,830 |
|
$ |
50,830 |
|
$ |
0 |
|
|
|
COST CODE |
|
DESCRIPTION |
|
QUANTITY |
|
UNIT |
|
UNIT COST |
|
SUBTOTAL |
|
TOTAL COST |
|
TOTAL COST |
|
||||
09-653200 |
|
VCT Floor and Vinyl Base |
|
1 |
|
LS |
|
$ |
0.00 |
|
INCLUDED |
|
|
|
|
|
|||
09-675300 |
|
Painted Epoxy Flooring |
|
1 |
|
LS |
|
$ |
36,700.00 |
|
$ |
36,700 |
|
$ |
36,700 |
|
$ |
0 |
|
09-880000 |
|
Carpet |
|
1 |
|
LS |
|
$ |
0.00 |
|
INCLUDED |
|
|
|
|
|
|||
09-770200 |
|
Corner Guards - Install |
|
1 |
|
LS |
|
$ |
4,000.00 |
|
$ |
4,000 |
|
$ |
4,000 |
|
$ |
0 |
|
09-770300 |
|
Corner Guards |
|
1 |
|
LS |
|
$ |
4,030.00 |
|
$ |
4,030 |
|
$ |
4,030 |
|
$ |
0 |
|
09-900000 |
|
Painting |
|
1 |
|
LS |
|
$ |
32,885.00 |
|
$ |
32,885 |
|
$ |
32,885 |
|
$ |
0 |
|
09-995000 |
|
Architectual Submittals/RFI’s |
|
1 |
|
LS |
|
$ |
3,000.00 |
|
$ |
3,000 |
|
$ |
3,000 |
|
$ |
0 |
|
09-999999 |
|
Remove Stair Nosing |
|
0 |
|
LS |
|
$ |
(9,900.00 |
) |
$ |
0 |
|
|
|
$ |
0 |
|
|
09-999999 |
|
Bead Blasting |
|
1 |
|
LS |
|
$ |
14,025.00 |
|
$ |
14,025 |
|
$ |
14,025 |
|
$ |
0 |
|
|
|
FINISHES |
|
|
$ |
498,223 |
|
$ |
498,223 |
|
$ |
0 |
|
||||||
|
|
DIVISION 10 |
|
|
|
|
|
|
|
|
|
|
|||||||
10-000000 |
|
SPECIALTIES |
|
0 |
|
LS |
|
$ |
0.00 |
|
$ |
0 |
|
|
|
|
|
||
10-100000 |
|
Projection Screens |
|
1 |
|
LS |
|
$ |
0.00 |
|
INCLUDED |
|
|
|
|
|
|||
10-522000 |
|
Fire Extinguishers |
|
1 |
|
LS |
|
$ |
1,000.00 |
|
$ |
1,000 |
|
$ |
1,000 |
|
$ |
0 |
|
10-522100 |
|
Fire Exiting Cabinets & Access |
|
1 |
|
LS |
|
$ |
0.00 |
|
INCLUDED |
|
|
|
|
|
|||
|
|
SPECIALTIES |
|
|
$ |
1,000 |
|
$ |
1,000 |
|
$ |
0 |
|
||||||
|
|
DIVISION 11 |
|
|
|
|
|
|
|
|
|
|
|||||||
11-000000 |
|
EQUIPMENT |
|
0 |
|
LS |
|
$ |
0.00 |
|
$ |
0 |
|
|
|
|
|
||
|
|
EQUIPMENT |
|
|
$ |
0 |
|
$ |
0 |
|
$ |
0 |
|
||||||
|
|
DIVISION 12 |
|
|
|
|
|
|
|
|
|
||||||||
12-000000 |
|
FURNISHINGS |
|
0 |
|
LS |
|
$ |
0.00 |
|
$ |
0 |
|
|
|
|
|
||
12-300000 |
|
Casework |
|
1 |
|
LS |
|
$ |
146,763.00 |
|
$ |
146,763 |
|
$ |
146,763 |
|
$ |
0 |
|
12-490000 |
|
Window Treatments |
|
1 |
|
LS |
|
$ |
2,5000.00 |
|
$ |
2,500 |
|
$ |
2,500 |
|
$ |
0 |
|
12-908000 |
|
Sterilizer |
|
1 |
|
LS |
|
$ |
47,000.00 |
|
$ |
47,000 |
|
$ |
47,000 |
|
$ |
0 |
|
12-911000 |
|
Glass Washer - Furnish |
|
1 |
|
LS |
|
$ |
26,883.00 |
|
$ |
26,883 |
|
$ |
26,883 |
|
$ |
0 |
|
12-911000 |
|
Glass Washer - Install |
|
1 |
|
LS |
|
$ |
1,200.00 |
|
$ |
1,200 |
|
$ |
1,200 |
|
$ |
0 |
|
|
|
FURNISHINGS |
|
|
$ |
224,346 |
|
$ |
224,346 |
|
$ |
0 |
|
||||||
|
|
DIVISION 13 |
|
|
|
|
|
|
|
|
|||||||||
13-000000 |
|
SPECIAL |
|
0 |
|
LS |
|
$ |
0.00 |
|
$ |
0 |
|
|
|
|
|
||
|
|
SPECIAL |
$ |
0 |
|
$ |
0 |
|
$ |
0 |
|
||||||||
|
|
DIVISION 14 |
|
|
|
|
|
|
|
|
|||||||||
14-000000 |
|
CONVEYING SYSTEMS |
|
0 |
|
LS |
|
$ |
0.00 |
|
$ |
0 |
|
|
|
|
|
||
|
|
CONVEYING |
$ |
0 |
|
$ |
0 |
|
$ |
0 |
|
||||||||
|
|
DIVISION
15 |
|
|
|
|
|
|
|
|
|
||||||||
15-000000 |
|
MECHANICAL |
|
0 |
|
LS |
|
$ |
0.00 |
|
$ |
0 |
|
|
|
|
|
||
16-100000 |
|
Piping Systems |
|
1 |
|
LS |
|
$ |
439,000.00 |
|
$ |
439,000 |
|
$ |
439,000 |
|
$ |
0 |
|
15-110000 |
|
Valves |
|
1 |
|
LS |
|
$ |
0.00 |
|
INCLUDED |
|
|
|
|
|
|||
15-183300 |
|
HW Reheat Coils |
|
1 |
|
LS |
|
$ |
3,500.00 |
|
$ |
3,500 |
|
$ |
3,500 |
|
$ |
0 |
|
15-184000 |
|
Refrigerant Piping |
|
1 |
|
LS |
|
$ |
0.00 |
|
INCLUDED |
|
|
|
|
|
|||
15-211000 |
|
Air Compressors |
|
1 |
|
LS |
|
$ |
7,500.00 |
|
$ |
7,500 |
|
$ |
7,500 |
|
$ |
0 |
|
15-214100 |
|
Lab Gas Piping Systems (Ar & N2) |
|
1 |
|
LS |
|
$ |
15,000.00 |
|
INCLUDED |
|
|
|
|
|
|||
15-214200 |
|
Lab Gas Manifolds & Regulators |
|
1 |
|
LS |
|
$ |
3,500.00 |
|
$ |
3,500 |
|
$ |
3,500 |
|
$ |
0 |
|
15-300000 |
|
Fire Protection |
|
1 |
|
LS |
|
$ |
48,800.00 |
|
$ |
48,800 |
|
$ |
48,800 |
|
$ |
0 |
|
15-500000 |
|
Boilers |
|
1 |
|
LS |
|
$ |
22,300.00 |
|
$ |
22,300 |
|
$ |
22,300 |
|
$ |
0 |
|
15-600100 |
|
Chiller Test |
|
1 |
|
LS |
|
$ |
0.00 |
|
$ |
0 |
|
|
|
|
|
||
15-720000 |
|
Air Handling Units |
|
1 |
|
LS |
|
$ |
41,000.00 |
|
$ |
41,000 |
|
$ |
41,000 |
|
$ |
0 |
|
15-720100 |
|
Install/TrimOutAirHandlingUnits |
|
1 |
|
LS |
|
$ |
0.00 |
|
INCLUDED |
|
|
|
|
|
|||
15-732100 |
|
Pkgd Rooftop HVAC Units |
|
1 |
|
LS |
|
$ |
28,000.00 |
|
$ |
28,000 |
|
$ |
28,000 |
|
$ |
0 |
|
15-810000 |
|
Ductwork Galvanized |
|
1 |
|
LS |
|
$ |
277,200.00 |
|
$ |
277,200 |
|
$ |
277,200 |
|
$ |
0 |
|
15-810300 |
|
Ductwork Pressure/Leak Testing |
|
1 |
|
LS |
|
$ |
5,400.00 |
|
$ |
5,400 |
|
$ |
5,400 |
|
$ |
0 |
|
15-811000 |
|
Duct Hangers & Supports |
|
1 |
|
LS |
|
$ |
0.00 |
|
INCLUDED |
|
|
|
|
|
|||
15-830000 |
|
Exhaust Fans |
|
1 |
|
LS |
|
$ |
9,800.00 |
|
$ |
9,800 |
|
$ |
9,800 |
|
$ |
0 |
|
15-900000 |
|
Controls and Instrumentation |
|
1 |
|
LS |
|
$ |
107,475.00 |
|
$ |
107,475 |
|
$ |
107,475 |
|
|
|
|
15-950000 |
|
Testing Adjusting & Balancing |
|
1 |
|
LS |
|
$ |
12,000.00 |
|
$ |
12,000 |
|
$ |
12,000 |
|
$ |
0 |
|
15-960000 |
|
Mechanical Submittals/RFI’s |
|
1 |
|
LS |
|
$ |
3,000.00 |
|
$ |
3,000 |
|
$ |
3,000 |
|
$ |
0 |
|
15-965000 |
|
Rigging |
|
1 |
|
LS |
|
$ |
0.00 |
|
INCLUDED |
|
|
|
|
|
|||
15-991000 |
|
Commissioning |
|
1 |
|
LS |
|
$ |
0.00 |
|
INCLUDED |
|
|
|
|
|
|||
15-991100 |
|
Start-up Assistance |
|
1 |
|
LS |
|
$ |
0.00 |
|
INCLUDED |
|
|
|
|
|
|||
15-999999 |
|
Chiller |
|
1 |
|
LS |
|
$ |
58,500.00 |
|
$ |
58,500 |
|
$ |
58,500 |
|
$ |
0 |
|
15-999999 |
|
Hydro DI Water System |
|
1 |
|
LS |
|
$ |
38,988.00 |
|
$ |
38,988 |
|
$ |
38,988 |
|
$ |
0 |
|
15-999999 |
|
Specified Mechanical Equipment |
|
1 |
|
LS |
|
$ |
24,000.00 |
|
$ |
24,000 |
|
$ |
24,000 |
|
$ |
0 |
|
15-999999 |
|
Exterior Natural Gas Piping |
|
1 |
|
LS |
|
$ |
9,500.00 |
|
$ |
9,500 |
|
$ |
0 |
|
$ |
9,500 |
|
|
|
MECHANICAL |
$ |
1,139,463 |
|
$ |
1,129,963 |
|
$ |
9,500 |
|
||||||||
|
|
DIVISION
16 |
|
|
|
|
|
|
|
|
|
||||||||
16-000000 |
|
ELECTRICAL |
|
1 |
|
LS |
|
$ |
391,135.00 |
|
$ |
391,135 |
|
$ |
391,135 |
|
$ |
0 |
|
16-230000 |
|
Generators |
|
1 |
|
LS |
|
$ |
16,800.00 |
|
$ |
16,800 |
|
$ |
16,800 |
|
$ |
0 |
|
16-265000 |
|
Uninterruptible Power Systems |
|
1 |
|
LS |
|
$ |
0.00 |
|
NIC |
|
|
|
|
|
|||
00-000000 |
|
Telephone/Data Systems |
|
1 |
|
LS |
|
$ |
0.00 |
|
NIC |
|
|
|
|
|
|||
16-750000 |
|
Fire Alarm System |
|
1 |
|
LS |
|
$ |
0.00 |
|
INCLUDED |
|
|
|
|
|
|||
16-752000 |
|
Gas Alarm Systems |
|
1 |
|
LS |
|
$ |
0.00 |
|
NIC |
|
|
|
|
|
|||
16-760000 |
|
Security Systems/Card Readers |
|
0 |
|
LS |
|
$ |
26,000.00 |
|
Owner Supplied |
|
|
|
|
|
|||
16-761000 |
|
Access Control System |
|
1 |
|
LS |
|
$ |
0.00 |
|
INCLUDED |
|
|
|
|
|
PROTECS, INC. |
|
|
|
BIOMED REALTY TRUST—LINGUAGEN |
ESTIMATING |
|
|
|
EWING, NJ |
|
|
|
|
DETAILED ESTIMATE |
Cost Code |
|
Description |
|
Quantity |
|
Unit |
|
Unit Cost |
|
Subtotal |
|
Total Cost |
|
Total Cost |
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
|
|
(Linguagen) |
|
(BMR) |
|
|
|
||||
16-761000 |
|
Electrical to Panels in other Tenant space |
|
1 |
|
LS |
|
$ |
76,000.00 |
|
$ |
76,000 |
|
$ |
0 |
|
$ |
76,000 |
|
|
|
16-960000 |
|
Electrical Submittals/RFI’s |
|
1 |
|
LS |
|
$ |
3,000.00 |
|
$ |
3,000 |
|
$ |
2,550 |
|
$ |
450 |
|
Pro-Rated |
|
|
|
ELECTRICAL |
|
$ |
486,935 |
|
$ |
410,485 |
|
$ |
76,450 |
|
|
|
|||||||
DIVISION 17—PROCESS |
|
||||||||||||||||||||
17-000000 |
|
PROCESS |
|
0 |
|
LS |
|
$ |
0.00 |
|
$ |
0 |
|
|
|
|
|
|
|
||
17-150000 |
|
Process Piping Systems– |
|
0 |
|
LS |
|
$ |
7,000.00 |
|
$ |
0 |
|
|
|
|
|
|
|
||
|
|
PROCESS |
|
$ |
0 |
|
$ |
0 |
|
$ |
0 |
|
|
|
|||||||
|
DIVISION 80 |
|
|||||||||||||||||||
80-000000 |
|
CONTINGENCY |
|
1 |
|
LS |
|
$ |
172,243.65 |
|
$ |
172,244 |
|
$ |
148,407 |
|
$ |
25,837 |
|
Pro-Rated |
|
|
|
CONTINGENCY |
|
$ |
172,244 |
|
$ |
148,407 |
|
$ |
25,837 |
|
|
|
|||||||
|
DIVISION 81 |
|
|||||||||||||||||||
81-000000 |
|
INSURANCE & WARRANTY |
|
1 |
|
LS |
|
$ |
38,171.17 |
|
$ |
36,171 |
|
$ |
30,745 |
|
$ |
5,426 |
|
Pro-Rated |
|
81-100000 |
|
Insurance |
|
1 |
|
LS |
|
$ |
0.00 |
|
$ |
0 |
|
|
|
|
|
|
|
||
81-100100 |
|
Sales Tax |
|
1 |
|
LS |
|
$ |
0.00 |
|
NIC |
|
|
|
|
|
|
|
|||
81-100200 |
|
Building Permit |
|
1 |
|
LS |
|
$ |
0.00 |
|
NIC |
|
|
|
|
|
|
|
|||
81-110000 |
|
Acceleration Premium |
|
1 |
|
LS |
|
$ |
0.00 |
|
NIC |
|
|
|
|
|
|
|
|||
|
|
INSURANCE & TAXES SUBTOTAL |
|
$ |
36,171 |
|
$ |
30,745 |
|
$ |
5,425 |
|
|
|
|||||||
|
DIVISION 81 |
|
|||||||||||||||||||
81-999999 |
|
Building Permit |
|
1 |
|
LS |
|
$ |
27,100.00 |
|
$ |
27,100 |
|
$ |
23,035 |
|
$ |
4,065 |
|
Pro-Rated |
|
|
|
PERMITS ADD/DEDUCT |
|
$ |
27,100 |
|
$ |
23,035 |
|
$ |
4,065 |
|
|
|
|||||||
|
DIVISION 82 |
|
|||||||||||||||||||
82-000000 |
|
COMMISSIONING |
|
1 |
|
LS |
|
$ |
10,000.00 |
|
$ |
10,000 |
|
$ |
8,500 |
|
$ |
1,500 |
|
Pro-Rated |
|
|
|
COMMISSIONING SUBTOTAL |
|
$ |
10,000 |
|
$ |
8,000 |
|
$ |
2,000 |
|
|
|
|||||||
|
DIVISION 83 |
|
|||||||||||||||||||
83-000000 |
|
DESIGN & ENGINEERING |
|
0 |
|
LS |
|
$ |
0.00 |
|
NIC |
|
|
|
|
|
|
|
|||
|
|
DESIGN & ENGINEERING |
|
$ |
0 |
|
$ |
0 |
|
$ |
0 |
|
|
|
|||||||
|
DIVISION 84—FEE |
|
|||||||||||||||||||
84-000000 |
|
FEE ITEMS |
|
1 |
|
LS |
|
$ |
212,150.21 |
|
$ |
212,150 |
|
$ |
180,328 |
|
$ |
31,823 |
|
Pro-Rated |
|
|
|
FEE SUBTOTAL |
|
$ |
212,150 |
|
$ |
180,328 |
|
$ |
31,823 |
|
|
|
|||||||
|
|
DIVISION 85—VALIDATION |
|
||||||||||||||||||
85-000000 |
|
VALIDATION |
|
0 |
|
LS |
|
$ |
0.00 |
|
$ |
0 |
|
|
|
|
|
|
|
||
|
|
VALIDATION SUBTOTAL |
|
$ |
0 |
|
|
|
|
|
|
|
3
5.0 MILESTONE SCHEDULE
4
6.0 Appendix
6.1 Drawing / Document List
* |
|
BY |
|
DRAWING |
|
TITLE |
|
REV |
|
DESCRIPTION |
|
REV DATE |
ARCHITECTURAL DRAWINGS |
||||||||||||
* |
|
Architecture Plus |
|
GN1 |
|
NJ UCC Notes, General Notes, Details, Elevations & Key Plan |
|
2 |
|
Misc. Revisions Per Coordination With Contract And As Required By Client |
|
07/26/06 |
* |
|
Architecture Plus |
|
D1 |
|
Partial Demolition Plan |
|
2 |
|
Misc. Revisions Per Coordination With Contract And As Required By Client |
|
07/26/06 |
* |
|
Architecture Plus |
|
D2 |
|
Partial Demolition Plan |
|
2 |
|
Misc. Revisions Per Coordination With Contract And As Required By Client |
|
07/26/06 |
* |
|
Architecture Plus |
|
A1 |
|
Partial Floor Plan |
|
2 |
|
Misc. Revisions Per Coordination With Contract And As Required By Client |
|
07/26/06 |
* |
|
Architecture Plus |
|
A2 |
|
Partial Floor Plan |
|
2 |
|
Misc. Revisions Per Coordination With Contract And As Required By Client |
|
07/26/06 |
* |
|
Architecture Plus |
|
A3 |
|
Interior Elevations & Details |
|
2 |
|
Misc. Revisions Per Coordination With Contract And As Required By Client |
|
07/26/06 |
* |
|
Architecture Plus |
|
A4 |
|
Enlarged Floor Plan and Details |
|
2 |
|
Misc. Revisions Per Coordination With Contract And As Required By Client |
|
07/26/06 |
* |
|
Architecture Plus |
|
A5 |
|
Exterior Building Elevations, Partial Floor Plans and Details |
|
2 |
|
Misc. Revisions Per Coordination With Contract And As Required By Client |
|
07/26/06 |
* |
|
Architecture Plus |
|
F1 |
|
Room Schedule, Notes and Details |
|
2 |
|
Misc. Revisions Per Coordination With Contract And As Required By Client |
|
07/26/06 |
* |
|
Architecture Plus |
|
F2 |
|
Door Schedule, Notes and Details |
|
2 |
|
Misc. Revisions Per Coordination With Contract And As Required By Client |
|
07/26/06 |
* |
|
Architecture Plus |
|
RC1 |
|
Partial Reflected Ceiling Plan and Details |
|
2 |
|
Misc. Revisions Per Coordination With Contract And As Required By Client |
|
07/26/06 |
* |
|
Architecture Plus |
|
RC2 |
|
Partial Reflected Ceiling Plan and Details |
|
2 |
|
Misc. Revisions Per Coordination With Contract And As Required By Client |
|
07/26/06 |
* |
|
Architecture Plus |
|
CW1 |
|
Partial Casework Plan |
|
2 |
|
Misc. Revisions Per Coordination With Contract And As Required By Client |
|
07/26/06 |
* |
|
Architecture Plus |
|
CW2 |
|
Partial Casework Plan |
|
2 |
|
Misc. Revisions Per Coordination With Contract And As Required By Client |
|
07/26/06 |
* |
|
Architecture Plus |
|
CW3 |
|
Casework Elevations and Details |
|
2 |
|
Misc. Revisions Per Coordination With Contract And As Required By Client |
|
07/26/06 |
* |
|
Architecture Plus |
|
RP1 |
|
Partial Roof Plan and Details |
|
2 |
|
Misc. Revisions Per Coordination With Contract And As Required By Client |
|
07/26/06 |
FIRE PROTECTION DRAWINGS |
||||||||||||
* |
|
Xxxxx Engineering |
|
FP-1 |
|
Fire Protection Specifications |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
FP-2 |
|
Fire Head Location Plan |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
PLUMBING DRAWINGS |
||||||||||||
* |
|
Xxxxx Engineering |
|
P-1 |
|
Plumbing Specifications |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
P-2 |
|
Plumbing Schedules and Details |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
P-3 |
|
Plumbing Part Plan |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
P-4 |
|
Plumbing Part Plan |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
P-5 |
|
Plumbing Part Plan |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
P-6 |
|
Plumbing Gas Piping Plan |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
P-7 |
|
Plumbing Riser Diagrams |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
P-8 |
|
Plumbing Part Sanitary Riser |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
MECHANICAL DRAWINGS |
||||||||||||
* |
|
Xxxxx Engineering |
|
M-1 |
|
Mechanical Specifications |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
M-2 |
|
Mechanical Symbols and Schedules |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
M-3 |
|
Mechanical Schedules and Abbreviations |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
M-4 |
|
Mechanical Demolition Plan |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
M-5 |
|
Mechanical Partial Ductwork Plan |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
M-6 |
|
Mechanical Partial Ductwork Plan |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
M-7 |
|
Mechanical Partial Ductwork Plan |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
M-8 |
|
Mechanical Partial Piping Plan |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
M-9 |
|
Mechanical Partial Piping Plan |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
M-10 |
|
Mechanical Roof Plan |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
M-11 |
|
Mechanical Controls |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
M-12 |
|
Mechanical Controls |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
M-13 |
|
Mechanical Details |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
M-14 |
|
Mechanical Details |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
M-15 |
|
Mechanical Details |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
ELECTRICAL DRAWINGS |
||||||||||||
* |
|
Xxxxx Engineering |
|
E-1 |
|
Electrical Specifications |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
E-2 |
|
Electrical General Information |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
E-3 |
|
Electrical Lighting Part Plan |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
E-4 |
|
Electrical Lighting Part Plan |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
E-5 |
|
Electrical Power Part Plan |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
E-6 |
|
Electrical Power Part Plan |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
E-7 |
|
Electrical Fire Alarm Part Plan |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
E-8 |
|
Electrical Fire Alarm Part Plan |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
E-9 |
|
Electrical Roof Plan |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
E-10 |
|
Electrical Mezzanine Power and Lighting Part Plan |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
E-11 |
|
Electrical Single Line Diagram & Distribution Plan |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
E-12 |
|
Electrical Schedules |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
E-13 |
|
Electrical Schedules |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
* |
|
Xxxxx Engineering |
|
PE-1 |
|
Plumbing/Electrical Site Plan |
|
3 |
|
Issued For Revision 3 And Permit Update |
|
8/1/06 |
|
|
|
|
|
|
|
|
|
|
|
|
|
STRUCTURAL DRAWINGS |
||||||||||||
* |
|
KPV Group |
|
S1 |
|
Foundation Plan |
|
|
|
Issued for LL & Tenant Final Review & Comment, Permit Review & Bid |
|
02/20/06 |
* |
|
KPV Group |
|
S2 |
|
Mezzanine Framing Plan |
|
|
|
Issued for LL & Tenant Final Review & Comment, Permit Review & Bid |
|
02/20/06 |
* |
|
KPV Group |
|
S3 |
|
Roof Framing Plan |
|
|
|
Issued for LL & Tenant Final Review & Comment, Permit Review & Bid |
|
02/20/06 |
* |
|
KPV Group |
|
S4 |
|
Sections |
|
|
|
Issued for LL & Tenant Final Review & Comment, Permit Review & Bid |
|
02/20/06 |
* |
|
KPV Group |
|
S5 |
|
Sections |
|
|
|
Issued for LL & Tenant Final Review & Comment, Permit Review & Bid |
|
02/20/06 |
* |
|
KPV Group |
|
S6 |
|
Sections |
|
|
|
Issued for LL & Tenant Final Review & Comment, Permit Review & Bid |
|
02/20/06 |
* |
|
KPV Group |
|
S7 |
|
Structural Notes and Typical Details |
|
|
|
Issued for LL & Tenant Final Review & Comment, Permit Review & Bid |
|
02/20/06 |
* |
|
KPV Group |
|
S8 |
|
Typical Details |
|
|
|
Issued for LL & Tenant Final Review & Comment, Permit Review & Bid |
|
02/20/06 |
|
|
|
|
|
|
|
|
|
|
|
|
|
* |
|
HACBM |
|
C-1 |
|
Mechanical Equipment Site Location Plan |
|
|
|
Issued For Bid |
|
03/01/2006 |
* |
|
SECTION |
|
TITLE |
|
ISSUED/REVISED |
|
|
|
|
REFER TO SHEET SPECIFICATIONS |
|
|
* |
|
00001 |
|
Index |
|
01/20/06 |
* |
|
00100 |
|
Instructions to Bidders |
|
01/20/06 |
* |
|
00300 |
|
Form of Proposal |
|
01/20/06 |
* |
|
00500 |
|
Construction Agreement |
|
01/20/06 |
* |
|
01010 |
|
Summary of Work |
|
01/20/06 |
* |
|
01030 |
|
Alternates |
|
01/20/06 |
* |
|
01100 |
|
Special Project Procedures |
|
01/20/06 |
* |
|
01300 |
|
Submittals and Substitutions |
|
01/20/06 |
* |
|
01505 |
|
Temporary Facilities |
|
01/20/06 |
* |
|
01700 |
|
Contract Closeout |
|
01/20/06 |
* |
|
01732 |
|
Selective Demolition |
|
01/20/06 |
* |
|
02300 |
|
Earthwork |
|
01/20/06 |
* |
|
00000 |
|
Xxxx-xx-Xxxxx Concrete |
|
01/20/06 |
* |
|
04200 |
|
Unit Masonry |
|
01/20/06 |
* |
|
05120 |
|
Structural Steel |
|
01/20/06 |
* |
|
06100 |
|
Rough Carpentry |
|
01/20/06 |
* |
|
06400 |
|
Architectural Woodwork |
|
01/20/06 |
* |
|
06620 |
|
Seamless Polymer Composite Plastic Fabrications |
|
01/20/06 |
* |
|
07210 |
|
Building Insulation |
|
01/20/06 |
* |
|
07270 |
|
Fire Stopping |
|
01/20/06 |
* |
|
07531 |
|
Elastomeric Sheet Roofing Repair |
|
01/20/06 |
* |
|
07900 |
|
Joint Sealers |
|
01/20/06 |
* |
|
08111 |
|
Metal Frames |
|
01/20/06 |
* |
|
08210 |
|
Flush Wood Doors |
|
01/20/06 |
* |
|
08310 |
|
Floor Access Hatch |
|
01/20/06 |
* |
|
08410 |
|
Aluminum Entrances and Storefronts |
|
01/20/06 |
* |
|
08710 |
|
Finish Hardware |
|
01/20/06 |
* |
|
08800 |
|
Glazing |
|
01/20/06 |
* |
|
09111 |
|
Non-Load-Bearing Steel Framing |
|
01/20/06 |
* |
|
00000 |
|
Xxxxxx Board |
|
01/20/06 |
* |
|
09300 |
|
Tile |
|
01/20/06 |
* |
|
09511 |
|
Acoustical Panel Ceilings |
|
01/20/06 |
* |
|
09660 |
|
Resilient Tile Flooring |
|
01/20/06 |
* |
|
09666 |
|
Sheet Floor Coverings |
|
01/20/06 |
* |
|
09681 |
|
Carpet |
|
01/20/06 |
* |
|
09705 |
|
Resinous Flooring |
|
01/20/06 |
* |
|
09708 |
|
Resinous Tank Coating |
|
01/20/06 |
* |
|
09900 |
|
Painting |
|
01/20/06 |
23
* |
|
09950 |
|
Wall Coverings |
|
01/20/06 |
* |
|
10160 |
|
Toilet Partitions |
|
01/20/06 |
* |
|
10265 |
|
Wall Surface Protection System |
|
01/20/06 |
* |
|
10425 |
|
Signs |
|
01/20/06 |
* |
|
10800 |
|
Toilet Accessories |
|
01/20/06 |
* |
|
11132 |
|
Projection Screens |
|
01/20/06 |
* |
|
00000 |
|
Xxxxxxxxxxx Appliances |
|
01/20/06 |
* |
|
11600 |
|
Laboratory Equipment |
|
01/20/06 |
* |
|
11610 |
|
Laboratory Fume Hoods |
|
01/20/06 |
* |
|
00000 |
|
Xxxxxxxxxx Casework |
|
01/20/06 |
* |
|
12484 |
|
Walk-Off Mats |
|
01/20/06 |
* |
|
12491 |
|
Horizontal Louver Blinds |
|
01/20/06 |
24
6.2 ProTecs Proposed Project Team
PRINCIPAL IN CHARGE: |
Xxxxxxxxxxx XxXxxxx |
|
|
|
|
OPERATIONS MANAGER: |
Xxx Xxxxxxx |
|
|
|
|
PROJECT MANAGER: |
Xxxxx Xxxxxx |
|
|
|
|
PROJECT SUPERINTENDENT: |
Xxx Xxxxxx |
|
|
|
|
PROJECT ENGINEER: |
TBD |
25