Excess Excavation definition

Excess Excavation means excavation in all material of whatever nature encountered outside the limit specified for Bulk, Trench, Structure or Incidental Excavation.
Excess Excavation means excavation outside the limits specified for Bulk, Trench, Structure, or Incidental Excavation.
Excess Excavation means excavation in all material of whatever nature

Examples of Excess Excavation in a sentence

  • Any extra excavation necessary to provide space for such support or other working space shall be held to be Excess Excavation.

  • Should the Contractor have excavated to within 150 mm above these specified levels or to within 150 mm of these specified limits before he is ready or able to commence the constructional work he shall, where required by the Engineer-in-Charge, excavate further so as to remove not less than 150 mm of material immediately before commencing the constructional work and such further excavation shall be held to be Excess Excavation.

  • The Contractor shall make his own allowance for any working space required, and any excavation outside the aforesaid limits which has not been ordered by the Engineer-in-Charge, whether it be excavated to suit the Contractor's method of working or unavoidable over break or due to his carelessness or error, shall be held to be Excess Excavation and shall not be paid.

  • Table 11-1 Locations for Placement of Excess Excavation Future Project Locations DescriptionAnticipated Project Need Embankment *Placement of material at any location other than those described in Book 2, Section 1 shall be Approved by CDOT.

  • Where the Contractor elects and is permitted by the Engineer-in-Charge to perform excavations with sloping faces (other than sloping excavations or required as permanent features of the Works) and without shoring, the excavated faces shall be to stable slopes and heights and the resulting extra excavation shall be held to be Excess Excavation.

  • Removal of Pavement, All Types and Thicknesses—for pavement structure 203-EX, Excess Excavation –for material below the pavement structure 907-403-C, Hot Mix Asphalt, ST, 19 mm, Trench Widening to replace failed areas NOTE: Replacement shall be made same day as excavation.

  • Rapid Transit Department, “Location of Dumps for Excess Excavation Materials” (map), 14 February 1949, drawing no.

  • If, for any reason, any portion of the bottoms, sides or ends of any excavations shall give way, the Contractor shall at his own expense take all necessary remedial measures including the excavation and removal of all the ground thereby disturbed both within and outside the nominal limits of excavation and such extraexcavations shall be held to be Excess Excavation.

  • Removal of Pavement, All Types and Thicknesses—for pavement structure 203-G, Excess Excavation –for material below the pavement structure 907-403-C, Hot Mix Asphalt, ST, 19 mm, Trench Widening to replace failed areas NOTE: Replacement shall be made same day as excavation.

  • Addendum #1 Exhibit ABASE BID Item No. ODOTSpec Description Unit Quantity Unit Cost Item Total 101 Excess Excavation CY 800 $ $ 102 114 Bidder’s Company Name: Authorized Signature Here  Printed Name: Bid 007-19/20 Addendum 2Special Provisions – Water Line Working HoursContractor shall perform work only on Monday through Friday excluding City-observed holidays and only between the hours of 8:00 AM and 5:00 PM.

Related to Excess Excavation

  • Excavation means the mechanical removal of earth material.

  • Excavation work means the making of any man-made cavity, trench, pit or depression formed by cutting, digging or scooping;

  • Excavation zone means the volume containing the tank system and backfill material bounded by the ground surface, walls, and floor of the pit and trenches into which the UST system is placed at the time of installation.

  • Excavator means any person performing excavation or blasting.

  • Built-Up Area and/or “Covered Area” in relation to a Flat shall mean the floor area of that Flat including the area of balconies and terraces, if any attached thereto, and also the thickness of the walls (external or internal) and the columns and pillars therein Provided That if any wall, column or pillar be common between two Flats, then one-half of the area under such wall column or pillar shall be included in the built-up area of each such Flat.

  • Excavate or "excavation" means ditching, dredging, or mechanized removal of earth, soil or rock.

  • Water Surface Elevation (WSE means the height, in relation to NAVD 1988, of floods of various magnitudes and frequencies in the floodplains of riverine areas.

  • Water surface elevation means the height, in relation to the National Geodetic Vertical Datum (NGVD) of 1929, the North American Vertical Datum (NAVD) of 1988, or other datum, where specified, of floods of various magnitudes and frequencies in the floodplains of riverine areas.

  • Area of shallow flooding means a designated AO or AH Zone on a community's Flood Insurance Rate Map (FIRM) with one percent or greater annual chance of flooding to an average depth of one to three feet where a clearly defined channel does not exist, where the path of flooding is unpredictable and indeterminate; and where velocity flow may be evident. Such flooding is characterized by ponding or sheet flow.

  • Generator Forced Outage means an immediate reduction in output or capacity or removal from service, in whole or in part, of a generating unit by reason of an Emergency or threatened Emergency, unanticipated failure, or other cause beyond the control of the owner or operator of the facility, as specified in the relevant portions of the PJM Manuals. A reduction in output or removal from service of a generating unit in response to changes in market conditions shall not constitute a Generator Forced Outage.

  • Building Common Areas means with respect to the Tower, the areas, facilities and amenities specified in Schedule [E] which are to be used and enjoyed in common with all the other Apartment Acquirers of the Units in the Building; and

  • Underground area means an underground room, such as a basement, cellar, shaft or vault, providing enough space for physical inspection of the exterior of the tank situated on or above the surface of the floor.

  • Decontamination means a procedure whereby health measures are taken to eliminate an infectious or toxic agent or matter on a human or animal body surface, in or on a product prepared for consumption or on other inanimate objects, including conveyances, that may constitute a public health risk;

  • Site area emergency means events may occur, are in progress, or have occurred that could lead to a significant release of radioactive material and that could require a response by off-site response organizations to protect persons off-site.

  • Underground tank means a device meeting the definition of tank whose entire surface area is totally below the surface of and covered by the ground.

  • Grading means the movement or redistribution of the soil, sand, rock, gravel, sediment, or other material on a site in a manner that alters the natural contour of the land.

  • Generator Planned Outage means the scheduled removal from service, in whole or in part, of a generating unit for inspection, maintenance or repair with the approval of the Office of the Interconnection in accordance with the PJM Manuals.

  • Elevated Building means a non-basement building which has its lowest elevated floor raised above ground level by foundation walls, shear walls, posts, piers, pilings, or columns.

  • Flood-related erosion area management means the operation of an overall program of corrective and preventive measures for reducing flood-related erosion damage, including but not limited to emergency preparedness plans, flood-related erosion control works and floodplain management regulations.

  • Maximum medical improvement means a point in time when any medically

  • Rear Yard means a yard extending across the full width of a parcel measured perpendicularly from the rear wall(s) of the main building situated on the parcel to the rear property boundary of the parcel [see sketch in Schedule B];

  • Planning area means a planning area or a development area or a local planning area or a regional development plan area, by whatever name called, or any other area specified as such by the appropriate Government or any competent authority and includes any area designated by the appropriate Government or the competent authority to be a planning area for future planned development, under the law relating to Town and Country Planning for the time being in force and as revised from time to time;

  • explosive actuated fastening device means a tool that is activated by an explosive charge and that is used for driving bolts, nails and similar objects for the purpose of providing fixing;

  • Slum area means any area where dwellings predominate which, by reason of depreciation, overcrowding, faulty arrangement or design, lack of ventilation, light or sanitary facilities, or any combination of these factors, are detrimental to the public safety, health or morals.

  • ILUA Area means the geographical area in relation to which the Framework ILUA applies, as specified in Schedule 2 of the Framework ILUA;

  • drainage work means any watercourse and includes any land which is expected to provide flood storage capacity for any watercourse and any bank, wall, embankment or other structure, or any appliance, constructed or used for land drainage or flood defence;