Karst Plan Delay definition

Karst Plan Delay has the meaning set forth in Section 6.9.3 of this DBA. Key Personnel means the positions identified in Exhibit 18 to this DBA.

Examples of Karst Plan Delay in a sentence

  • A Karst Plan Delay begins on the date DB Contractor notifies TCEQ and TxDOT of the discovery of an Unknown Karst Feature in accordance with the RID entitled “Karst Feature Discovery and Mitigation” and ends when the applicable Karst Feature Mitigation Plan is approved by TxDOT and TCEQ.

  • DB Contractor shall not be entitled to delay or disruption damages resulting from a Karst Plan Delay or Karst Mitigation Delay.

  • If the Karst Plan Delay exceeds 35 days for a particular Unknown Karst Feature, then the risk of such Karst Plan Delay in excess of 35 days for that Unknown Karst Feature shall be borne by TxDOT.

  • If a Karst Plan Delay for which DB Contractor is entitled to a time extension is concurrent with another delay for which DB Contractor is also entitled to a time extension, only one of the delays shall be considered for purposes of the Change Order provisions in the Design-Build Contract.

  • The absence of any of the above mentioned elements may not be a guarantee of the structural integrity of the tank.

Related to Karst Plan Delay

  • income-related employment and support allowance means an income-related allowance under Part 1 of the Welfare Reform Act 2007;

  • Tenant Delay means an actual delay in the occurrence of the Substantial Completion Date or the Final Completion Date with respect to Landlord’s Work as the result of: (1) any unreasonable delay by Tenant in approving the Plans; (2) any request by Tenant that Landlord delay the commencement or completion of Landlord’s Work for any reason; (3) any request by Tenant to change the Plans after initial approval thereof by Tenant, or the making of any changes to Landlord’s Work requested by Tenant and agreed to by Landlord after initial approval of the Plans by Tenant; (4) any failure by Tenant to respond in writing within seven (7) business days after any written request by Landlord for clarification or interpretation of the Plans or for approval of changes in the Plans deemed necessary by Landlord; or (5) any other act or omission of Tenant or its officers, agents, employees or contractors; Notwithstanding the foregoing, no event shall be deemed to be a Tenant Delay until and unless Landlord has given Tenant written notice (the “Tenant Delay Notice”) advising Tenant (i) that a Tenant Delay is occurring, (ii) of the basis on which Landlord has determined that a Tenant Delay is occurring, and (iii) the actions which Landlord believes that Tenant must take to eliminate such Tenant Delay, and Tenant has failed to correct the Tenant Delay specified in the Tenant Delay Notice within forty-eight (48) hours following receipt thereof. No period of time prior to expiration of such 48-hour period shall be included in the period of time charged to Tenant pursuant to such Tenant Delay Notice if Tenant corrects the Tenant Delay specified in the Tenant Delay Notice within such 48-hour period.

  • main phase employment and support allowance means an employment and support allowance where the calculation of the amount payable in respect of the applicant includes a component under section 2(1)(b) or 4(2)(b) of the Welfare Reform Act 2007 except in Part 1 of Schedule 1;

  • Force Majeure Delay means with respect to the Servicer, any cause or event which is beyond the control and not due to the negligence of the Servicer, which delays, prevents or prohibits such Person’s delivery of the reports required to be delivered or the performance of any other duty or obligation of the Servicer under the Indenture, as the case may be, including, without limitation, computer, electrical and mechanical failures, acts of God or the elements and fire; provided, that no such cause or event shall be deemed to be a Force Majeure Delay unless the Servicer shall have given the Indenture Trustee written notice thereof as soon as practicable after the beginning of such delay.

  • Network Termination Point (NTP) means the physical point at which a subscriber is provided with access to a public communications network; in the case of networks involving switching or routing, the NTP is identified by means of a specific network address, which may be linked to a subscriber number or name;

  • Community Developmental Disability Program (CDDP means an entity that is responsible for planning and delivery of services for individuals with developmental disabilities in a specific geographic service area of the state operated by or under a contract with the Division or a local mental health authority.

  • Potential Takedown Participant shall have the meaning set forth in Section 3.2.5(b).

  • Developmental delay means that a child has not reached developmental milestones expected for his or her chronological age as measured by qualified professionals using appropriate diagnostic instruments and/or procedures.

  • converted employment and support allowance means an employment and support allowance which is not income-related and to which a person is entitled as a result of a conversion decision within the meaning of the Employment and Support Allowance (Existing Awards) Regulations 2008;

  • Extended school year services means special education and related services that are provided to a child with a disability and meet the standards of the State of Wisconsin. These services are provided beyond the normal school year of the local educational agency, in accordance with the individualized education program (IEP), and at no cost to the parents of the child.

  • contributory employment and support allowance means an allowance under Part 1 of the Welfare Reform Act 2007 as amended by the provisions of Schedule 3, and Part 1 of Schedule 14, to the Welfare Reform Act 2012 that remove references to an income-related allowance and a contributory allowance under Part 1 of the Welfare Reform Act 2007 as that Part has effect apart from those provisions;

  • Compensation Accrued at Termination means the following:

  • Force Majeure Delays means any actual delay in the construction of the Tenant Improvements, which is beyond the reasonable control of Landlord or Tenant, as the case may be, as described in Paragraph 33 of the Lease.

  • Tenant Delays means (A) Tenant’s request for changes to Landlord’s Work, regardless of whether any such changes are performed, (B) construction of any such changes, (C) Tenant’s request for materials, finishes, or installations requiring unusually long lead times that were not originally included as a part of Landlord’s Work, (D) Tenant’s delay (which shall mean more than 5 business days) in reviewing, revising, or approving any plans and specifications relating to Landlord’s Work, (E) Tenant’s delay in providing information critical to the normal progression of the Project (Tenant shall provide such information as soon as reasonably possible, but in no event longer than 5 business days after receipt of any request for such information from Landlord), and (F) any other act or omission by Tenant or any Tenant Party (as defined herein), or persons employed by any of such persons, (iv) “Substantially Completed” means the substantial completion of Landlord’s Work (A) in a good and workmanlike manner, (B) in accordance with the requirements described in Exhibit C, and (C) in accordance with all applicable Legal Requirements (including, but not limited to, securing the applicable final building inspection for Landlord’s Work), subject only to normal “punch list” items, and (v) “Existing Tenant Delay” means the refusal or failure by the Existing Tenant (as defined below) to surrender the Premises by July 1, 2010 in accordance with the terms and conditions of the Existing Lease (as defined below). Landlord will promptly perform such punch list items. Tenant shall obtain, at its sole cost and expense, any applicable use and occupancy permit for the Premises issued by the applicable Governmental Authority. If Tenant does not elect to void this Lease within 5 business days of the lapse of such 60 day period, such right to void this Lease shall be waived and this Lease shall remain in full force and effect. If neither Landlord nor Tenant elects to void this Lease within 5 business days of the lapse of such 60 day period, such right to void this Lease shall be waived and this Lease shall remain in full force and effect. Sequoia Pharmaceuticals, Inc. (“Existing Tenant”), is currently leasing the Premises from Landlord, and the lease agreement (“Existing Lease”) between Landlord and Existing Tenant is scheduled to expire on July 1, 2010 subject to Landlord’s right to advance the expiration date. Tenant understands, acknowledges, and agrees that Landlord makes no guaranty, representation, or assurance that Landlord will be able to recapture the Premises from the Existing Tenant by July 1, 2010 and that Landlord shall have no obligation or duty to seek the vacation or removal of the Existing Tenant from the Premises.

  • maternity or paternity leave of absence means, for Plan Years beginning after December 31, 1984, an absence from work for any period by reason of the Employee's pregnancy, birth of the Employee's child, placement of a child with the Employee in connection with the adoption of such child, or any absence for the purpose of caring for such child for a period immediately following such birth or placement. For this purpose, Hours of Service shall be credited for the computation period in which the absence from work begins, only if credit therefore is necessary to prevent the Employee from incurring a 1-Year Break in Service, or, in any other case, in the immediately following computation period. The Hours of Service credited for a "maternity or paternity leave of absence" shall be those which would normally have been credited but for such absence, or, in any case in which the Administrator is unable to determine such hours normally credited, eight (8) Hours of Service per day. The total Hours of Service required to be credited for a "maternity or paternity leave of absence" shall not exceed 501.

  • extended reduction (qualifying contributory benefits means a reduction under this scheme for which a person is eligible in accordance with paragraph 88 or 95;

  • Reduced leave schedule means a leave schedule that reduces the usual number of hours per workweek, or hours per workday, of an employee.

  • Changes/Extra Work The SUBRECIPIENT shall make no changes to this CONTRACT without the COUNTY’s written consent. In the event that there are new or unforeseen requirements, the COUNTY with the SUBRECIPIENT’s concurrence has the discretion to request official changes at any time without changing the intent of this CONTRACT.

  • qualifying age for state pension credit means (in accordance with section 1(2)(b) and (6) of the State Pension Credit Act 2002)—

  • Economic Load Response Participant means a Member or Special Member that qualifies under Operating Agreement, Schedule 1, section 1.5A, and the parallel provisions of Tariff, Attachment K-Appendix, section 1.5A, to participate in the PJM Interchange Energy Market and/or Ancillary Services markets through reductions in demand.

  • Salary reduction plan means a benefit plan whereby state and

  • Non-Administrator Dialysis Facility means a Dialysis Facility which does not have an agreement with the Claim Administrator or another Blue Cross and/or Blue Shield Plan but has been certified in accordance with the guidelines established by Medicare.

  • Minor Administrative Change refers to a change to the Contract that does not increase the fees or term and done in accordance with Section 4.01 of these Special Conditions.

  • multiple-employer workplace means a workplace where workers of 2 or more employers are working at the same time:

  • Qualified Matching Contribution means any employer contribution allocated to an Eligible Employee's account under any plan of an Employer or a Related Company solely on account of "elective contributions" made on his behalf or "employee contributions" made by him that is a qualified matching contribution as defined in regulations issued under Code Section 401(k), is nonforfeitable when made, and is distributable only as permitted in regulations issued under Code Section 401(k).

  • In-Service Date means the date on which the Facility and System Modifications (if applicable) are complete and ready for service, even if the Facility is not placed in service on or by that date.