Examples of Measured Availability in a sentence
For each year during the Term, within thirty (30) days after the anniversary of the Commencement Date, O&M Contractor shall deliver to Owner a written report containing the Measured Availability for the PV Plant during the prior twelve (12) month period and such information and data requested by Owner reasonably necessary to confirm the results of such determinations.
If the Measured Availability for the PV Plant is equal to or greater than ninety-eight percent (98%) (the “Guaranteed Performance”) for any annual reporting period (or, if shorter, the initial reporting period), then the Guaranteed Performance for the PV Plant shall be deemed satisfied for such period and O&M Contractor shall have no liability to Owner in relation to the Guaranteed Performance for the PV Plant.
If for any Availability Test Period the average Measured Availability is less than the Minimum Guaranteed Availability, the O&M Contractor shall pay to the Project Company the Availability Liquidated Damages .
If identified as applicable in the Key Information Table, for any Availability Test Period in which the average Measured Availability is more than the Minimum Guaranteed Availability, the Project Company shall pay to the O&M Contractor the Availability Bonus.
AVAILABILITY36 The O&M Contractor guarantees that the Measured Availability during each Availability Test Period shall meet or exceed the Minimum Guaranteed Availability.
Measured Availability represents the time in which the Facility is operating over the total possible time it is able to operate.
If the Measured Availability for the PV Plant is equal to or greater than ninety-eight percent (99%) (the “Guaranteed Performance”) for any annual reporting period (or, if shorter, the initial reporting period), then the Guaranteed Performance for the PV Plant shall be deemed satisfied for such period and O&M Contractor shall have no liability to Owner in relation to the Guaranteed Performance for the PV Plant.
Measured Availability shall be reported by Licensor to Licensee no later than ten (10) business days after the end of the agreed upon reporting frequency or period.
AVAILABILITY37 The O&M Contractor guarantees that the Measured Availability during each Availability Test Period shall meet or exceed the Minimum Guaranteed Availability.
Measured Availability (% yearly basis) Reduction in charges (% reduction for the affected year) 99.50 - 99.00% 5% 98.99 - 90.00% 15% Below - 90,00% 20% Any compensation given by Dualog to Customer shall be final and conclusive, and shall be Customer’s sole and only remedy against Dualog.