Programmed Maintenance definition
Examples of Programmed Maintenance in a sentence
If the Authority's Representative does not raise comments on such proposed revision in accordance with Schedule Part 8 (Review Procedure), the Schedule of Programmed Maintenance as revised shall become the Schedule of Programmed Maintenance in respect of that quarter.
The Contractor shall undertake routine repair and maintenance of the Schools in accordance with a Schedule of Programmed Maintenance which has been approved or not commented on by the Authority under the Review Procedure.
At the end of each Academic Year the Contractor shall supply to the Authority an account of any damage and associated Repair Costs and Damage Funding, as well as money spent or saved or to be spent or saved in accordance with the Schedule of Programmed Maintenance.
The Authority shall, within a further period of [five (5)] Business Days following receipt by the Authority of notification of the amount of the Estimated Increased Maintenance Costs, at the Authority's option, either confirm or withdraw its request to accelerate or defer the Schedule of Programmed Maintenance.
Project Co shall notify the Authority of the amount of any additional reasonable costs which it will incur as a direct consequence of such acceleration or deferment (the "Estimated Increased Maintenance Costs") within [five (5)] Business Days of the receipt of the written notice advising of the requirement for an acceleration or deferment of the Programmed Maintenance.
In relation to any Repair Cost which has been funded or partly funded by the Authority or under any Required Insurance (Damage Funding) the Contractor shall take such funding and the timing of such repair or replacement into account in preparing and agreeing with the Authority the Schedule of Programmed Maintenance and any savings shall be offset against any future Estimated Increased Maintenance Costs pursuant to clause 23.4.7 (Schedule of Programmed Maintenance).
If the Authority's Representative does not raise comments on such proposed revision in accordance with Schedule 8 (Review Procedure), the Schedule of Programmed Maintenance as revised shall become the Schedule of Programmed Maintenance in respect of the next Term.
Schedule of Programmed Maintenance No later than two (2) months prior to the Planned Services Availability Date for each School, the Contractor shall submit to the Authority's Representative in accordance with Schedule 8 (Review Procedure) a Schedule of Programmed Maintenance for that School for the period from the Planned Services Availability Date to the expiry of that Academic Year.
If there are no Estimated Increased Maintenance Costs pursuant to clause 23.4.7 (Schedule of Programmed Maintenance), the savings shall be shared equally between the Contractor and the Authority.
Not later than twenty (20) Business Days prior to the end of any Term, the Contractor may submit to the Authority's Representative in accordance with paragraph 3.1.7 of Schedule 8 (Review Procedure) a revision to the Schedule of Programmed Maintenance for the Academic Year in which the relevant Term falls showing the effect of the proposed changes to the Programmed Maintenance Information.