PROGRESS AND COMPLETION Sample Clauses

PROGRESS AND COMPLETION. 8.2.1 All time limits stated in the Contract Documents are material terms and time is the essence of the Contract. A failure by Contractor to do what is required by the time specified in the Contract Documents is a breach of the contract. 8.2.2 The Contractor shall begin the Work on the date of commencement as defined in 8.2.3 If in the sole opinion of the State, the Contractor fails to commence work on the project or to complete the work of said project within the time specified above, or to prosecute the work in such a manner that it appears that the completion date can be assured, the State shall have the right to notify the Contractor by Certified Mail that the terms of the Contract have been violated, and that effective immediately the Contract is terminated and the State has the right to and in fact is taking over and attending to completion of the project without prejudice to the State's remedies for any losses sustained
AutoNDA by SimpleDocs
PROGRESS AND COMPLETION. ‌ 8.2.1 Contractor agrees that the Contract Time is reasonable for performing the Work and that Contractor is able to perform the Work within the Contract Time. .1 The Construction Schedule may reflect a period of performance that is shorter than the Contract Time; provided however, that the difference shall be deemed as float and nothing in this Paragraph or in any other provision of the Contract Documents shall be construed as creating any contractual right, express or implied, on the part of Contractor to finish the Project earlier than the Contract Time and under no circumstances shall City be liable to Contractor for any costs, damages or compensation due to the inability of Contractor to complete the Work earlier than the Contract Time, regardless of the cause, including, without limitation, acts or omissions (intentional or negligent) of City. .2 Contractor has included in its Bid price the costs of all Contractor and Subcontractor overhead (direct and indirect) for the entire duration of the Contract Time. The above costs are included in Contractor’s Bid notwithstanding Contractor's anticipation of completion in fewer days than established by the Contract Time. .3 No increase in the Contract Sum shall be made or granted for Delay if Contractor completes the Work before expiration of the Contract Time. .4 No reduction in the Contract Sum shall be made nor will Contractor be required to remain on the Project Site if the Work is completed before expiration of the Contract Time. .5 The Construction Manager will schedule and hold weekly progress meetings and other meetings to be required by progress of the Work as determined by the Construction Manager. Contractor and/or Contractor's designee shall be present at each meeting. Contractor may also be required to request attendance by representatives of Contractor’s suppliers, manufacturers and Subcontractors. 8.2.2 Except by agreement or instruction of City in writing, Contractor shall not commence operations on the Site or elsewhere prior to the effective date of insurance required by Article 11 to be furnished by Contractor. Contractor’s obligations to commence the Work and to complete the Work within the Contract Time shall not be changed by the effective date of such insurance. 8.2.3 Contractor shall proceed expeditiously with adequate forces and shall achieve Substantial Completion within the Contract Time. If City determines and notifies Contractor that Contractor’s progress is such that Contractor ...
PROGRESS AND COMPLETION. 1.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By executing the Design-Build Amendment the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.
PROGRESS AND COMPLETION. 4.2.2, 8.2, 9.8, 9.9.1, 14.1.4, 15.1.4 9.3, 9.6, 9.8.5, 9.10.3, 14.2.3, 15.1.4
PROGRESS AND COMPLETION. § 8.2.1 Time limits stated in the Contract Documents are of the essence of the Contract. By executing the Agreement, the Contractor confirms that the Contract Time is a reasonable period for performing the Work. § 8.2.2 The Contractor shall not knowingly, except by agreement or instruction of the Owner in writing, commence the Work prior to the effective date of insurance required to be furnished by the Contractor and Owner. § 8.2.3 The Contractor shall proceed expeditiously with adequate forces and shall achieve Substantial Completion within the Contract Time.
PROGRESS AND COMPLETION. Time limits stated in the Contract Documents are of the essence of this Agreement. By executing the Agreement, the Design/Builder confirms that the Contract Time is a reasonable period of time for achieving Substantial Completion of the Work. Design/Builder agrees to have all work substantially completed NOT LATER THAN, March 1, 2004.
PROGRESS AND COMPLETION. It is expressly understood by the Contractor and Owner that time is important in the performance of this Agreement. The Contractor shall begin the Work on the date of commencement set forth in the written notice to proceed. The Contractor shall carry the Work forward expeditiously with adequate forces and shall complete it in accordance with the Schedule.
AutoNDA by SimpleDocs
PROGRESS AND COMPLETION. 15.4.1 Time of the Essence Time limits stated in the Contract Documents are of the essence to the Contract Documents. By executing the Facilities Lease, Developer confirms that the Contract Time is a reasonable period for performing the Work.
PROGRESS AND COMPLETION. CONTRACTOR shall commence work on the services to be performed upon full execution of this Agreement and shall consider full execution of this Agreement as Notice to Proceed. All services shall be completed as mutually agreed upon by both parties; deviations from the schedule shall be approved by VCTC. Progress reports, which include a summary of work completed during the billing period, will be provided by the CONTRACTOR with each invoice.
PROGRESS AND COMPLETION. All time limits stated in the Contract Documents are of the‌ essence of the agreement between Owner and Contractor. Contractor shall begin each phase of the Project, where applicable, in accordance with the Project Schedule and shall commence the Work on the dates set forth in the applicable Construction Schedule. Contractor shall carry out the Work expeditiously, with adequate forces, and shall achieve Substantial Completion in accordance with the Project’s milestones, the Construction Schedule, and within the Contract Time.