Common use of PROGRESS AND COMPLETION Clause in Contracts

PROGRESS AND COMPLETION. 8.1.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By executing the Design-Build Amendment the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.

Appears in 26 contracts

Samples: Agreement, www.durhamnc.gov, rfp.hawaiiconvention.com

AutoNDA by SimpleDocs

PROGRESS AND COMPLETION. 8.1.1 A.8.2.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By Design executing the Design-Build Amendment Contract, the Design-Builder confirms that the Contract Time is a reasonable period for i performing the Work.

Appears in 5 contracts

Samples: cdn.cocodoc.com, www.unlv.edu, www.unlv.edu

PROGRESS AND COMPLETION. 8.1.1 A.8.2.1 Time limits stated in the Design-Build Documents are of the essence of the Design-Build Contract. By executing the Design-Build Amendment Contract, the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.

Appears in 2 contracts

Samples: bnavisionnashville.com, asc67.org

PROGRESS AND COMPLETION. 8.1.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By executing the Design-Design- Build Amendment the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.

Appears in 2 contracts

Samples: Agreement, www.tsu.edu

PROGRESS AND COMPLETION. 8.1.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By executing the Design-Build Amendment Contract the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.

Appears in 1 contract

Samples: resources.finalsite.net

PROGRESS AND COMPLETION. 8.1.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By executing acknowledging and accepting the Design-Build Amendment Notice to Proceed, the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.

Appears in 1 contract

Samples: Agreement

PROGRESS AND COMPLETION. 8.1.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By executing the Design-Build Amendment the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work. e th trac ntract.

Appears in 1 contract

Samples: logoscharter.com

PROGRESS AND COMPLETION. 8.1.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By executing the Design-Build Amendment this Agreement the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.

Appears in 1 contract

Samples: www.bidnet.com

AutoNDA by SimpleDocs

PROGRESS AND COMPLETION. 8.1.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By executing the Design-Build GMP Amendment the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.

Appears in 1 contract

Samples: www.pdx.edu

PROGRESS AND COMPLETION. 8.1.1 1.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By executing the Design-Build Amendment the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.

Appears in 1 contract

Samples: rfp.hawaiiconvention.com

PROGRESS AND COMPLETION. 8.1.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By executing the Design-Build Amendment Amendment, the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.

Appears in 1 contract

Samples: jpshealthnet.org

PROGRESS AND COMPLETION. 8.1.1 Time limits with regard to Completion stated in the Design-Build Documents are of the essence of the Contract. By executing the Design-Build Amendment the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.

Appears in 1 contract

Samples: bchd.blob.core.windows.net

PROGRESS AND COMPLETION. 8.1.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By executing the Design-Build Amendment the Design-Builder DBC confirms that the Contract Time is a reasonable period for performing the Work.

Appears in 1 contract

Samples: Agreement