PROGRESS AND COMPLETION. 1.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By executing the Design-Build Amendment the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.
Appears in 27 contracts
Samples: Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder, Standard Form of Agreement Between Owner and Design Builder
PROGRESS AND COMPLETION. 1.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By executing the Design-Design- Build Amendment the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.
Appears in 2 contracts
Samples: Design Build Agreement, Design Build Agreement
PROGRESS AND COMPLETION. 1.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By executing the Design-Build Amendment Contract the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder
PROGRESS AND COMPLETION. 1.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By executing acknowledging and accepting the Design-Build Amendment Notice to Proceed, the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.
Appears in 1 contract
Samples: Design Build Agreement
PROGRESS AND COMPLETION. 1.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By executing the Design-Build GMP Amendment the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.
Appears in 1 contract
Samples: Design Build Contract
PROGRESS AND COMPLETION. 1.1 Time limits with regard to Completion stated in the Design-Build Documents are of the essence of the Contract. By executing the Design-Build Amendment the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder
PROGRESS AND COMPLETION. 1.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By executing the Design-Build Amendment Amendment, the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder
PROGRESS AND COMPLETION. 1.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By executing the Design-Build Amendment this Agreement the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder
PROGRESS AND COMPLETION. 1.1 A.
8.2.1 Time limits stated in the Design-Build Documents are of the essence of the Design-Build Contract. By executing the Design-Build Amendment Contract, the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.
Appears in 1 contract
Samples: Design Build Agreement
PROGRESS AND COMPLETION. 1.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By executing the Design-Build Amendment the Design-Builder DBC confirms that the Contract Time is a reasonable period for performing the Work.
Appears in 1 contract
Samples: Design Build Agreement
PROGRESS AND COMPLETION. 1.1 8.1.1 Time limits stated in the Design-Build Documents are of the essence of the Contract. By executing the Design-Build Amendment the Design-Builder confirms that the Contract Time is a reasonable period for performing the Work.
Appears in 1 contract
Samples: Standard Form of Agreement Between Owner and Design Builder