Examples of Proposed Punchlist in a sentence
The Proposed Punchlist that is ultimately approved or deemed to have been approved by Owner shall be referred to as the “Punchlist”.
Such Proposed Punchlist shall include only Non-Critical Deficiencies and shall include a Punchlist Amount for the completion or repair of each such Non-Critical Deficiency.
If the Punchlist is not finalized by the Guaranteed Substantial Completion Date, the Proposed Punchlist as modified by Owner shall be deemed the Punchlist for all purposes hereunder until the Parties resolve such dispute and otherwise finalize the Punchlist.
This procedure shall be repeated until the Proposed Punchlist is approved or deemed to have been approved by Owner.
If Owner timely delivers any changes to the Proposed Punchlist to Contractor, then Owner and Contractor shall discuss such changes and Contractor shall deliver a revised Proposed Punchlist to Owner for its review in accordance with this subsection.
If the Punchlist is not approved or deemed to have been approved by Owner pursuant hereto by the Guaranteed Substantial Completion Date, the Proposed Punchlist as modified by Owner shall be deemed the Punchlist for all purposes hereunder until the Parties resolve such dispute and otherwise finalize the Punchlist.
If Owner delivers such a Notice to Contractor, Contractor shall complete any items of Work other than Non-Critical Deficiencies, revise the Proposed Punchlist to include all Non-Critical Deficiencies identified by Owner (whether or not such items are disputed by Contractor) and resubmit the revised Proposed Punchlist to Owner for review.
However, in polyimide aerogels the shrinkage phenomenon can be mainly described based on the three following factors: i) interactions between the polymer chains with each other as well as with the solvent molecules, ii) chains rigidities, and iii) chains packing ability with respect to chain geometry and co-planarity.10 Fig.
Owner may then re-inspect the Project and the foregoing process shall continue on an iterative basis until Owner has approved the Proposed Punchlist.
Owner and Contractor shall determine whether the Proposed Punchlist includes all Non-Critical Deficiencies for such system, whether the Proposed Punchlist includes only Non-Critical Deficiencies and whether the system is complete except for those items described in the Proposed Punchlist.