Examples of Solar Power Generator in a sentence
MSEDCL shall inform the Solar Power Generator for procurement of excess power within 15 days of receiving a written intimation from the Solar power Generator for such excess generation.
If in case MSEDCL fails to reply to the Solar Power Generator within the above stipulated time period then the generator shall be free to sell it to any other entity.
This will, however be relaxable by MSEDCL to the extent of grid non-availability for evacuation, which is beyond the control of the Solar Power Generator.
The Solar Power Generator will declare the CUF of their project at the time of signing of PPA and will be allowed to revise the same once within first year of COD.
Solar Power Generator shall not be in default for non-supply of power during this period of repowering.
The lower limit will, however, be relaxed by MSEDCL to the extent of grid non-availability for evacuation which is beyond the control of the Solar Power Generator.
MSEDCL will be billed by the Solar Power Generator based on Joint Meter reading/AMR/SEA as certified by Maharashtra SLDC or MSEDCL authority as may be applicable following the end of each month for the energy supplied and payment will be due on the thirtieth day following the delivery of the billing invoice.
The Solar Power Generator shall follow the forecasting and scheduling process as per prevailing MERC regulations as amended from time to time.The Government of India, as per Clause 5.2(u) of the Indian Electricity Grid Code (IEGC), encourages a status of “must-run” to solar power projects.
During the PPA period, if for any contract year, it is found that the Solar Power Generator has not been able to generate minimum energy corresponding to the lower limit of CUF declared by the Solar Power Generator, such shortfall in performance shall make Solar Power Generator liable to pay the compensation to MSEDCL as mentioned in this Article.
During the “Suspension Period” mentioned herein above, MSEDCL shall allow the Solar Power Generator to sell power from the project, to any third party, in the open market either by finding the said consumers on its own or through any Central / State power trading utilities.